W91238-17-R-0011 Attachment 1 14 March
Summary 649 MUNS Precision Guided Missile Maintenance Facility
Hill AFB, UT
1. Scope of Work
The work for this project is to design and construct a 14,820 square foot single story Precision Guided Missile (PGM) Maintenance Facility at Hill Air Force Base (HAFB), Utah. The Contractor shall provide all labor, equipment, transportation, material and supervision to perform the design, and construction of the complete operational facilities. Design and construction shall include all civil, architectural, geotechnical, structural, utilities, landscaping, security, mechanical, electrical, demolition, and communications work to support the necessary construction.
Note: This intent of this Summary is to provide general project information to interested Offerors of the subject procurement. Conceptual drawings are provided for reference. The complete project requirements will be issued in the Phase 2 solicitation.
2. Description
2.1 The Contractor shall furnish and install all labor, materials, tools, equipment, and supervision necessary to provide a complete and usable project per the Specific Technical Engineering and Design Criteria, Function Design Criteria Room by Room Requirements, including all attachments, Base Facility Design Standard, Architectural Compatibility Guide and requirements specified herein. Contractor shall include in the design the following features:
• Single story, multi-bay PGM maintenance facility
• Facility to include an administrative support core for offices and personnel. Facility will be designed as a permanent construction in accordance with UFC 1-200-01.
• Provide reinforced concrete exterior walls, insulated standing seam metal roof, explosion proof lighting, lightning protection system, fire protection, and supporting facilities including utilities, exterior lighting, site improvements, communication infrastructure and exterior apron pavement.
• Each work bay to be equipped with 400 Hz/3 phase power, high pressure air, and an 18 foot wide by 20 foot high overhead door.
• Provide adequate number of parking spaces to support the mission of the facility. This project will comply with DOD Antiterrorism Protection requirements per UFC 4-010-01.
Sustainable principles will be integrated into the design, development, and construction of this project in accordance with UFC 1-200-02.
This is a design-build stand-alone contract; therefore, the Contractor is required to perform design work prior to construction. The design of architectural, interior design, structural, mechanical, electrical, civil, landscape and other engineering features of the work shall be accomplished, reviewed, approved and sealed by engineers, architects and interior designers who are licensed professionals with a minimum of six years’ experience to practice in their respective professional field in a state or possession of the United States.
2.2 Special Design Requirements: The structural interior design (SID) shall be designed/supervised by a registered or certified (as appropriate for the state) interior designer who is National Council for Interior Design Qualification (NCIDQ) certified. The Contractor’s team shall include a Leadership in Energy and Design (LEED) accredited professional (LEED AP). The LEED AP shall have the responsibility to coordinate the design and construction efforts in achieving a US Green Building Council (USGBC) LEED Silver rating, using LEED for New Construction version 2009. The hydraulic design, drawings and layout of the sprinkler system shall be prepared by a registered Fire Protection Engineer or National Institute for Certification in Engineering Technologies (NICET) Level 4 technician with at least four years current experience in design of fire protection systems. The geotechnical design shall be performed by a Geotechnical firm with at least 5 years experience geotechnical design work within the Ogden/Salt Lake City region. Communications Systems Engineering and Design shall be performed by a Building Industry Consulting Service International (BICSI) Registered Communications Distribution Designer (RCDD). The shop drawings shall be stamped and signed by the RCDD certifying compliance with the applicable Electronic Industries Alliance/Telecommunications Industry Association (EIA/TIA) standards as required. Design of fire alarm system shall be done by a registered NICET Level 4 designer, with at least 3 years of current and applicable experience in similar designs. The design drawings must bear the designer's NICET Level 4 certification and signature. Contractor shall have experience in Building Envelope with continuous Air Barrier Systems, and Lightning Protection. The Contractor is responsible and liable for the complete design and shall not assume that the provided design criteria and drawings in this solicitation will alleviate him/her from performing any additional design as required to produce a complete set of construction documents.
The Government’s conceptual facility and site design provided illustrates intent and functional relationships and does not indicate all necessary construction requirements or components. The written Phase 2 RFP describes associated technical, performance and systems requirements, and includes all specifications, attachments, and drawings. The Contractor is responsible for the complete project design, shall retain all responsibilities, and be recognized as the Designer of Record.
3. General Project Requirements:
Contractor shall follow all security requirements for base access. All Contractor and subcontractor personnel will need to obtain badges for all access on base from the security office.
AT Level I Training: All Contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at http://jko.jten.mil.
The Contractor shall be responsible for the coordination of work performed by their employees and all subcontractors. The Contractor shall inspect all work areas prior to bidding. It shall be the Contractor’s responsibility to verify all current record drawings prior to the start of any and http://jko.jten.mil/ all design and /or construction work. The Contractor shall be responsible for the coordination and proper relationship of this work to the building premises and thoroughly familiarize themselves with all details of the work and working conditions, to verify all dimensions in the field, and advise the ACO of any discrepancies before performing any work.
Contractor is responsible for maintaining the site and all other Contractor controlled areas in such a manner as to minimize the risk of injury or accident to site personnel or others who may be in the area. The specific security procedures will be include in the Phase 2 RFP.