PERFORMANCE WORK STATEMENT

6 February 2017

SUBJECT AND LOCATION: Technical Support, Leviathan Mine Superfund Site, Alpine County, California

Task Order W91238-17-D-TBD

CONTRACTOR: TBD

CONTRACTOR: TBD

POC

USACE COR TBD

USACE POC: TBD

USACE Contracting Donald Sumner POC: U.S. Army Corps of Engineers, Sacramento District

Attn: CESPK-CT-B 1325 J Street Sacramento, CA 95814-2922 Phone: (916) 557-6752 Email: Donald.Sumner@usace.army.mil

U.S. EPA POC: TBD

mailto:Donald.Sumner@usace.army.mil

1.0 OBJECTIVE AND TASK DESCRIPTION: CERCLA response action and remedy requires completion of RI/FS, proposed plan, Record of Decision (ROD), remedial action work plan, remedial action completion report, etc. This PWS include review of ARCO, the potential responsible party (PRPs) or other contractor’s work products/deliverables on the RI/FS, response action and remedy, as requested by EPA, and other management and technical support as outlined in this PWS. The site is in many stages with many operable units. Support to EPA includes all actions required from RI/FS to reach ROD and implement the remedial action under EPA oversight, including review of deliverables and technical documents prepared by PRP or other contractors, and providing technical comments and recommendations. EPA will complete the ROD internally after the proposed plan and responsiveness summaries are completed.

This Task Order (TO) is to provide 12 months of support to EPA for the Leviathan Mine Site. All tasks required to support management, planning, meeting attendance, communications, day to day operations and continued support activities to EPA are included in this TO. The primary deliverables will typically be weekly and monthly reports for all requirements. All tasks required to develop and complete deliverables are included in this TO. No additional compensation outside this TO will be awarded to support the required deliverables.

1.1 Background. Leviathan Mine is an inactive mine located on the east side of the Sierra Nevada Mountains in California. Acid drainage from the mine (AMD) contributes pollutants to Leviathan and Bryant Creeks and to the Carson River. The Carson River is a significant source of water supply to agricultural, tribal, and urban users in western Nevada. Because of the interstate and tribal interests involved, and the lack of progress toward cleanup at the site, the U.S. Environmental Protection Agency (EPA) added the Leviathan Mine to its national priority list (NPL) in 2000.

The California Regional Water Quality Control Board - Lahontan Region (RWQCB), currently owns the mine. Before it was owned by California, the Anaconda Company, a former subsidiary of the Atlantic Richfield Company (ARCO), operated Leviathan Mine. ARCO and RWQCB are Potentially Responsible Parties (RPs) for the reclamation of Leviathan Mine, and since 2001, both PRs have implemented interim treatment systems at the site to reduce discharge of AMD.

Under EPA oversight, ARCO has been performing ongoing studies (RI/FS) to develop a long-term solution at the Leviathan Mine as part of the cleanup plan. RI began in 2008. Burleson has supported the EPA requirements for this project under contract to USACE and through an interagency agreement. Over the past several years, ARCO has prepared work plans to gather historical information and environmental data.

EPA, other federal and state agencies, and the Washoe Tribe, have reviewed and provided recommendations, and will continue to provide stakeholder support. EPA maintains a long list of previous documents on its publically available web site. Any references required to complete these tasks can be found at the EPA web site.

2.0 REQUIREMENTS: The Contractor shall provide the necessary expertise, materials, and supplies to complete tasks outlined in this task order. The Contractor shall be responsible for managing the various requirements defined below. The Contractor shall be responsible for delivery of the following items:

2.1 – Project Support and RP oversight

Following tasks are required to provide a complete technical support for the site for 6 months. The period of service will be 12 months to allow for startup and TO closeout. Programmatic documents required in the base contract award such as General Management Plan, Health and Safety Plan, Data

Management Plan are not specifically called out as they will not be included in compensated deliverable tasks but will be required during the period of service and the cost to support development of this document should be disbursed throughout the deliverables.. Tasks as noted below include all subtasks required to support the deliverable such as but not including calls, meetings, site visits, coordination, program and project management. During the project, Weekly Project Status Update Report, Site Status Reports, Monthly Status and Annual Summary Reports are required as evidence of costs for the EPA to perform cost recovery from RPs. All effort required to execute these deliverables will be included in each task below.

2.1.1 Task 1.1 – Deliverables

Task 1.1.1 -- Project Status Update Report. The contractor shall produce on a weekly basis a status memorandum/report to document progress on the project. For estimating purposes, the contractor shall assume that communication will occur in many formats i.e. phone calls and meetings, conference calls, site visits, email and written correspondence. The contractor shall assume that frequent coordination calls are required to provide the status update deliverable. The contractor shall send the Project Status Update Report to the Corps & EPA (electronic) on a weekly basis, and follow up with a phone call to verify delivery and accuracy of the Report. For estimating purpose, assume 30 project status update for the 6 month period.

Task 1.1.2 -- Site Status Update Report. The contractor shall produce on a periodic basis a memorandum/report to document progress on the site, including RI/FS field oversight visits. For estimating purposes the contractor shall assume that site status is documented by first hand observation of site activities and in accordance with EPA requirements for documentation of site activities. The contractor shall send the Site Status Update Report to the Corps and EPA (electronically within one week of the site visit and follow up with a phone call to verify delivery and accuracy of the Report). Elements of the Site Status Update Report will be similar to historical reporting i.e. status of water treatment systems, water treatment, water transfers, and discharge of treated waters in addition to measurements of pH, Eh, temperature and specific conductance of surface water at the site shall be included. Periodic collection of surface water or monitoring well samples may be required. The report shall also include observation of water flow volumes to the extent practical. Contractor shall assume that early response action (ERA) oversight is required and included in the status update reports. For estimating purpose, assume 3 site status update reports during the current Leviathan field season with an option for 3 additional site status reports.

Task 1.1.3 – Monthly Status Update Reports (MSR). The contractor shall produce on a monthly basis a status memorandum/report to document progress on the project during the duration of the project. The focus of this report includes information included in Task 1.1 as well as documentation of the previous months’ presentation. For estimating purposes it is assumed that 3 meetings shall occur. Meetings may be located near the mine site, and current progress and following months anticipated progress shall be included. The report will explain the financial status of the project and current invoice. The contractor shall send the Monthly Status Update Report to the Corps and EPA (electronic) on a monthly basis and follow up with a phone call to verify delivery and accuracy of the Report. The format for the MSR will be approved by the Corps and EPA. For estimating purpose, assume 6 site monthly status update reports with an option for another 6 MSRs.

Task 1.1.4 – Quarterly Technical Summary Memoranda. The contractor will participate in presentation/technical updates of the Project and Site meetings and prepare a summary memorandum documenting the discussions at or near the EPA offices, near the site or near the Corps offices in Sacramento Ca. The contractor shall send the summary memorandum to the Corps and EPA (electronic) after each presentation and follow up with a phone call to verify delivery and accuracy of the memorandum. For estimating purpose, assume 4 quarterly technical reports.

Task 1.1.5 – Option Annual Summary Report. The Annual Summary Report will be prepared as a compilation of previous reports for the Investigation and ERA season as well as analysis and recommendations of historic and new information gained during the annual task execution. A section shall be included for trend analysis and recommendations and conclusions. The contractor shall send the Draft Annual Report to the Corps and EPA (hard copy and electronic) 30 days after the receipt of Atlantic Richfield Company (ARCO) and Lahontan Regional Water Quality Control Board (RWQCB) annual reports. The format for the Report will be approved by the Corps and EPA. The Final Report shall be submitted 15 days after receipt of final comments (Option may be exercised 1 time).

2.1.2 Task 1.2 – Report Review Memorandum

The Contractor shall assume that report reviews outlined below also include review of Leviathan Mine stakeholder comments and generated as a response to comments as they pertain to the specific report.

Task 1.2.1 – Option Minor Report Review Memorandum. Minor reports are considered to be reports of less than 30 pages or initial draft submissions. Review of these reports may be technical or programmatic. A Review Memorandum will be generated for each review and the contractor shall send the Review Memorandum to the Corps and EPA (electronic) after each review. The contractor shall follow up with a phone call to verify delivery and accuracy of the Review Memorandum. (Option may be exercised for up to 8 reports)

Task 1.2.2 – Option Standard Report Review Memorandum. Standard reports are considered to be reports of less than 100 pages but greater than 30 pages. Review of these reports may be technical or programmatic. A Review Memorandum will be generated for each review and the contractor shall send the Review Memorandum to the Corps and EPA (electronic) after each review. The contractor shall follow up with a phone call to verify delivery and accuracy of the Review Memorandum. (Option may be exercised for up to 4 reports)

Task 1.2.3 – Option Large Report Review Memorandum. Large reports are considered to be reports greater than 100 pages. Review of these reports may be technical or programmatic. A Review Memorandum will be generated for each review and the contractor shall send the Review Memorandum to the Corps and EPA (electronic) after each review. The contractor shall follow up with a phone call to verify delivery and accuracy of the Review Memorandum. (Option may be exercised for up to 1 report)

2.1.3 Task 1.3 – Travel and Per Diem

Task 1.3.1 – Travel and Per Diem Applicable to Task 1.1.2. Travel and per diem expenses are authorized.

The Contractor shall submit backup documentation (proof of payment for Travel and Per Diem) along with respective paid receipts as specified in the payment and invoice paragraph. The amount billed shall not exceed the funded amount available on the line item. The contractor shall comply with Specific Travel & Per Diem Invoicing Instructions, Joint Travel Regulations, and FAR 31.205-46, Travel Costs. The contractor is authorized to include a 10% travel multiplier to applicable travel and per diem costs. Travel and per diem shall be proposed in accordance with travel requirements in the standard reoccurring tasks above.

Task 1.3.2 – Travel and Per Diem Applicable to Task 1.1.3. Travel and per diem expenses are authorized.

The Contractor shall submit backup documentation (proof of payment for Travel and Per Diem) along with respective paid receipts as specified in the payment and invoice paragraph. The amount billed shall not exceed the funded amount available on the line item. The contractor shall comply with Specific Travel & Per

Diem Invoicing Instructions, Joint Travel Regulations, and FAR 31.205-46, Travel Costs. The contractor is authorized to include a 10% travel multiplier to applicable travel and per diem costs. Travel and per diem shall be proposed in accordance with travel requirements in the standard reoccurring tasks above.

3. SCHEDULE and DELIVERABLES: As these tasks are part of the on-going program for Leviathan, these tasks are anticipated to continue until the ROD is publicly approved.

DELIVERABLES

Task 1.1 – Deliverables

Task 1.1.1 Weekly Project Status Update Report Draft due Tuesday of the following week

Final due Friday of the following week.

Task 1.1.2 Weekly Site Status Update Report Draft due Tuesday of the following week

Final due Friday of the following week.

Task 1.1.3 – Monthly Status Update Reports (MSR)

Draft due the 20th of the following month Final due the end of the following month.

Task 1.1.4 – Presentation Summary Memoranda

Draft summary memorandum due 20th of the following month Final due the end of the following month

Task 1.1.5 – Annual Summary Report Draft Annual Report due 1 May.

Final Annual Report due15 days after receipt of final comments

Task 1.2 – Report Review Memorandum

Task 1.2.1 – Minor Report Review Memorandum.

Draft due 10 days after review Final due 10 days after receipt of comments

Task 1.2.2 – Standard Review Memorandum.

Draft due 10 days after review Final due 10 days after receipt of comments

Task 1.2.3 – Large Review Memorandum.

Draft due 20 days after review Final due 10 days after receipt of comments

4. MISCELLANEOUS INSTRUCTIONS:

4.1 SAFETY REQUIREMENTS: The contractor shall provide for the protection of the lives and health of employees and other persons; preventing damage to property, materials, supplies and equipment; and avoid work interruptions. For these purposes, the contractor shall:

• Comply with Federal and California OSHA Safety and Health Regulations

• Comply with pertinent provisions of the Corps of Engineers’ EM 385-1-1

4.2 RELEASE OF INFORMATION: The contractor shall obtain approval from COE PM prior to release of any information received in the performance of this task order or developed pursuant to this task order. All inquires regarding the release of such information shall be referred to EPA and the COE

PM

5. DATA: All data, reports and material produced under or relative to this performance work statement will become the property of the U.S. Government and will not be released to other agencies or their Contractors without written approval by the Contracting Officer

5.1 SUBMITTALS: All submittals shall become the property of the USACE. The Contractor shall provide copies of backup data and all computations used in support of the contracted work.

5.2 QUALITY CONTROL: The Contractor shall be responsible for quality control of its own work.

The Contractor shall have a logical and functional quality control program to assure that errors and deficiencies in all submittals are minimal.

6. AUTHORITIES/TECHNICAL DIRECTION: The Contractor shall take no direction from any Government employee or any other person other than the Government Contracting Officer that changes the terms and conditions of this contract action, the scope, or any change that impacts the cost, price or schedule. Changes authorized by the Contracting Officer will be in the form of a written, official, signed modification to the contract action received by the Contractor before the Contractor will act upon those changes. The Contractor will comply with the Changes clause of this contract when the contractor believes direction has been given from persons other than the Government Contracting Officer that equate to a change by notifying the Contractor Officer as directed by the clause. Any direction given by any Government employee or any other person outside their authority must be reported to the Contracting Officer. Contracting Officer Representatives (CORs) are limited to the authorities stated in the COR appointment letters. If a COR is appointed under this contract, they will be appointed by written letter from the Contracting Officer to the Contractor and COR specific to this contract only. COR appointment letters from previous contracts at this installation are not valid for this contract.

7. PERIOD OF PERFORMANCE: The period of performance is from date of award to 30 June 2018.

8. INVOICING AND PAYMENTS:

a. INVOICES: Invoices for payment shall be submitted upon completion of tasks as outlines in the pricing/payment schedule. Invoices shall include all necessary information, including any necessary supporting documentation and shall be submitted to the following agencies and individuals.

Invoices may be mailed, emailed, or faxed.

Original invoice WITHOUT additional information or supporting documentation:

USAED, Finance Center Attn: CEFC-FP 5722 Integrity Dr.

Millington, TN 38054-5005 Fax: 901-874-8731 Email: CEFC-Payments@usace.army.mil

One copy each of Invoice WITH all required information including any necessary supporting documentation:

U.S. Army Corps of Engineers, Sacramento District Attn: CESPK-PM-M (Kay Chang) 1325 J Street Sacramento, CA 95814-2922 Kay.chang@usace.army.mil Ph: 916/557-7625

U.S. Army Corps of Engineers, Sacramento District Attn: CESPD-PDM (Dan McMindes) 1325 J Street, Sacramento, CA 95814-2922 Cell: (415) 297-0367. Phone: (916) 557-7399 Email: Daniel.C.McMindes@usace.army.mil

NOTE: All invoices must reflect contract number W91238-016-D-00xx-000x and the final invoice must be marked “FINAL”.

b. CONTACT PAYMENTS. The Government shall pay the Contractor upon submission of proper invoices for the services delivered and accepted for the portion of the work actually performed under the contract. Payment shall be made as indicated in the contract’s Payment Schedule not on percentage of completion. Deliverables as defined in the Payment Schedule of the contract must be accepted by the Government before payment will be made.

c. Travel and Per Diem Costs to Include Rental Vehicles and Mileage. These Other Direct Costs (ODCs) shall be billed to the Government on a reimbursable basis. ODCs are estimated as part of negotiations or competition, and billed to the Government in an amount not to exceed the total funding for ODCs. The Contractor shall also establish a tracking system for measuring the actual funds and costs expended versus the total funds and costs available for use. When either the actual available funding or costs negotiated reaches 85% of the total amount, the Contractor shall notify the Government’s Contracting Officer and Contracting Officer’s Representative (COR) in writing by fax or e-mail within two calendar days. Once the Government receives notification, if the Government determines that funds or costs need to be increased, the Contractor will receive an official modification to the contract action signed by the Contracting Officer increasing funds or costs. The Contractor must receive a modification BEFORE proceeding with work over the existing estimated quantity. The modification will establish a new funding level or negotiated costs that he Contractor may not exceed without another modification. A full accounting of each item billed, the actual amounts being billed, and full documentation to support amounts billed. Actual paid vendor / subcontractor invoices must be submitted as supporting documentation to each invoice where costs are invoiced to the Government for payment. ODC Costs will be reviewed by the Government for the tests of allowability, allocability, and reasonableness as required by FAR Part 31.2. Any questioned costs will be documented by the Government and forwarded to the Contractor in writing for resolution. Payment may be withheld for those costs that do not pass the determinations required in FAR Part 31.2 until such time they are resolved.

d. Specific Travel and Invoicing Requirements:

1) In no case will travel be taken if there is not enough money in the Not-to-Exceed line item; if necessary the Government will issue an official modification before the travel occurs to increase the amount in the line item. If the contractor finds during travel that the price for the travel will be more, the contractor will notify the Contracting Officer immediately and BEFORE incurring additional costs.

2) Reasonable costs shall be allowable only if the above information is provided with the invoice and the costs are allowable IAW the above referenced regulations and approved by the Contracting Officer.

3) Travel shall be billed to the Government on a reimbursable basis, to include a full accounting of each item billed, the actual amounts being billed, and full documentation to support amounts billed. Actual paid vendor / subcontractor invoices must be submitted as supporting documentation to each invoice where costs are invoiced to the Government for payment. The contractor shall include copies of travel documentation to include all lodging receipts (even if they are under $75.00), and all travel receipts equal to or more than $75.00. Documentation to support travel costs shall be in accordance with FAR 31.205-46, Travel Costs and Joint Travel Regulations, JTR Vol 2 DoD Civilians).

4) Transportation and per diem shall be in accordance with the Joint Travel Regulation for DOD Civilians, JTR Vol 2, and the Federal Acquisition Regulation (FAR) 31.205-45 (Travel Costs).

This shall be a not-to-exceed (NTE) per trip and payments will be made on actuals.

5) Costs shall be allowable only if the following information is documented:--

Date and place (city, town, or other similar designation) of the expenses, and

Purpose of the trip; and

Name of person on trip and that person’s title or relationship to the contractor.

6) Airfare: Costs shall be at the lowest customary standard, coach, or equivalent airfare offered during normal business hours (ref FAR 31.205-46.b.); anything in excess shall be unallowable.

7) Travel, Lodging, and Per Diem: Current per diem costs for the travel areas in the PWS for are located at: http://www.defensetravel.dod.mil/perdiem/perdiemrates.html

Max Lodging Rate per night. Prior approval by the Contracting Officer is required to exceed this amount. Justification for this request is required. A paid receipt is required regardless of amount.

Partial Meal Rate. The partial meal rate is applicable to the first and last days of travel only. (calculated at 75% of the full meal rate). No receipt is required.

Full Meal Rate. The full meal rate is applicable to the days between the first and last days of travel. No receipt is required.

Incidentals. Each individual is allowed $5.00 per day for incidentals. No receipt is required.

Employee Travel Vouchers. The contractor shall submit copies of the travel vouchers employees submitted to the company, showing the amounts the company paid for, or reimbursed, the employees.

Airfare. Paid airfare receipts are required.

8) Other transportation costs shall be in accordance with the JTR Vol 2 DoD Civilians & FAR 31.205-46. See http://www.gsa.gov/mileage for mileage reimbursement for POV transportation.

9) The contractor is authorized to apply a 10% multiplier for all travel and per diem costs.

9. SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

a. All Contractor employees (U.S. citizens and Non- U.S. citizens) working under this contract (to include grants, cooperative agreements and task orders) who require access to Automated Information Systems (AIS), (stand alone computers, network computers/systems, e-mail) shall, at a minimum, be designated into an ADP-III position (nonsensitive) in accordance with DoD 5220-22-R, Industrial Security Regulation. The investigative requirements for an ADP-III position are a favorable National Agency Check (NAC), SF-85P, Public Trust Position.

b. The contractor shall have each applicable employee complete a SF-85P and submit to the Sacramento District Security Officer within three (3) working days after award of any contract or task order, and shall be submitted prior to the individual being permitted access to an AIS. Contractors that have a commercial or government entity (CAGE) Code and Facility Security Clearance through the Defense Security Service shall process the NACs and forward visit requests/results of NAC to the Sacramento District Security Officer. For those contractors that do not have a CAGE Code or Facility Security Clearance, the Sacramento District Division Security Office will process the investigation in coordination with the Contractor and contract employees.

c. In accordance with Engineering Regulation, ER 380-1-18, Section 4, foreign nationals who work on Corps of Engineers’ contracts or task orders shall be approved by the HQUSACE Foreign Disclosure Officer or higher before beginning work on the contract/task order. This regulation includes http://www.gsa.gov/mileage subcontractor employees. (NOTE: exceptions to the above requirement include foreign nationals who perform janitorial and/or ground maintenance services.) The contractor shall submit to the Sacramento District Contract Office, the names of all foreign nationals proposed for performance under this contract/task order, along with documentation to verify that he/she was legally admitted into the United States and has authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B).

d. The address and telephone number for the Sacramento District Security Officer is as follows:

U.S. Army Engineer District, Sacramento Attn: Security Officer (CESPK-DE-S) 1325 J Street Sacramento, CA 95814-2922 Tel: (916) 557-6920

e. All transmittals of documentation and other information pertaining to this requirement must be marked with the applicable contract, grant, agreement, and/or task order number and the name of the contracting officer. Additionally, the contracting officer must be notified in writing whenever a SF 85P has been submitted to the Security Officer for processing.

10. PERFORMANCE ASSESSMENT METRICS: Performance of services/deliverables shall be assessed by the Contracting Officer’s Representative (COR) in accordance with the performance objectives and standards (expectations) established in the Quality Assurance Surveillance Plan (QASP), Attachment #1.

QUALITY ASSURANCE SURVEILLANCE PLAN

LEVIATHAN REMEDIAL ACTION AND EARLY ACTIN SUPPORT

1. INTRODUCTION. This plan sets forth procedures and guidelines that the U.S. Army Corps of Engineers (USACE) will use in evaluating the technical performance of the Contractor. A copy of this plan will be furnished to the Contractor so that the Contractor will be aware of the methods that the Government will employ in evaluating performance on this contract and address any concerns that the Contractor may have prior to initiating work.

2. PURPOSE OF THE QASP

• Confirm that the action is conducted utilizing proper procedures and in accordance with the approved work and safety plans;

• Define the roles and responsibilities of participating Government officials;

• Define the types of work to be performed with required end results;

• Document the evaluation methods that will be employed by the Government in assessing the Contractor’s performance;

• Provide the Surveillance Activities Table and Corrective Action Request (CAR) form that will be used by the Government in documenting and evaluating the Contractor’s performance; and

• Describe the process of performance documentation.

3. ROLES AND RESPONSIBILITIES OF PARTICIPATING GOVERNMENT OFFICIALS

The USACE Contracting Officer Representative (COR):

• Provides overall guidance to the contractor when necessary or requested for purposes of PWS/SOW clarification.

• Reviews vouchers and makes recommendations to the Contracting Officer for payment action based on completion of designated milestones.

• Reports problems or discrepancies to the Contracting Officer as soon as possible.

• Oversees the implementation of the QASP.

• Reviews contractor submittals.

• Initiates periodic contractor evaluations in the Past Performance Information Management System (PPIMS).

• Responsible for the execution of the work on schedule, within budget, in a safe manner, and at a level of quality consistent with the customer’s requirements.

• Periodically reviews contractor performance relative to the contract schedule and budget.

The USACE Contract Specialist:

• Monitors contract performance.

• Maintains central repository for all QA documents required for payment.

• Issues all acceptance/rejection statements.

The Project Manager (PM):

• Reviews contractor’s Technical Management Plan.

• Ensures that all necessary subject matter experts are involved in technical decisions.

• Conducts reviews of contractor submittals for compliance with contract requirements.

• Conducts or supports other surveillance activities as required by the project team.

4. METHODOLOGIES TO BE USED TO MONITOR THE CONTRACTOR’S PERFORMANCE:

Even though the Government will be monitoring the contractor’s performance on a continuing basis, the volume of tasks performed by the contractor makes technical inspections of every task and step impractical. Accordingly, USACE will use the Surveillance Activities Table as the basis for monitoring the contractor’s performance under this contract. The contractor’s performance will be evaluated by the Contracting Officer using the performance metrics.

5. QUALITY ASSURANCE REPORTING FORMS. The primary form used to document surveillance activities will be the review memorandum. The review memorandum format will be determined at the time of the first deliverable submittal.

Upon completion of field work and acceptance of all final reports, the COR will document QA activities in a final Quality Assurance memorandum.

SURVEILLANCE ACTIVITIES TABLE

Performance Objective

Performance Standard

Minimum Acceptance Criteria

Inspection Type and Frequency

Incentive or Remedy

Weekly Project Status Update Report

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level.

Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

Weekly Site Status Update Report

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level.

Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

Monthly Status Update Report

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level.

Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

Presentation Summary Memoranda

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level.

Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246)

Annual Summary Report

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level.

Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

SURVEILLANCE ACTIVITIES TABLE CON’T

Performance Objective

Performance Standard

Minimum Acceptance Criteria

Inspection Type and Frequency

Incentive or Remedy

Minor Report Review Memoranda

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level. Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

Standard Report Review Memoranda

Deliverable provide in timely manner

Complete, accurate report section

Qualitative Review, 100%

Contractor shall receive payment for services performed at an acceptable level. Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

Large Report Review Memoranda

Approach to Providing PWS requirements are consistent and meet the Government’s needs. All employees working under the contract have the required skills.

99% of the time all employees working on the contract have the right skill mix to fulfill the PWS requirements.

Time records are accurate and reflect work achieved.

Continuous

COR

observations and Government teammates semiannual evaluations.

Contractor shall receive payment for services performed at an acceptable level. Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246)

Contract Management

Approach to Providing PWS requirements are consistent and meet the Government’s needs. All employees working under the contract have the required skills.

99% of the time all employees working on the contract have the right skill mix to fulfill the PWS requirements.

Time records are accurate and reflect work achieved.

Continuous

COR

observations and Government teammates semiannual evaluations.

Contractor shall receive payment for services performed at an acceptable level. Remedy for an unacceptable quality level shall be in accordance with the inspection clause of the contract (FAR 52.246-6)

6. AUTHORITIES/TECHNICAL DIRECTION: The Contractor shall take no direction from any Government employee or any other person other than the Government Contracting Officer that changes the terms and conditions of this contract action, the scope, or any...