W91238-16-R-0013 Unrestricted Civil Works: Synopsis of Questions and Answers
1) Will Past Performance Questionnaires (PPQ) submitted for projects in Section F, each at least 4 pages, count towards the 200 page limit for our SF 330?
ANSWER: PPQ’s will not count toward the overall page limitation. Additionally, please do not include the PPQ’s in section F. The PPQ’s should be stand-alone.
2) Regarding the page size limits for the proposal response, you have allotted only three (3) 11 x 17 pages for organizational chart. If we only use one (1) 11 x 17 page for the org chart, can we use the other two (2) for graphics/charts/tables/etc. for SF330 Section H?
ANSWER: No. The 11 x 17 sheets are only for the organization charts.
3) Where should PPQs be placed in the SF330 submittal? Directly behind its respective Section F Project, or elsewhere?
ANSWER: Please do not include the PPQ’s in section F. The PPQ’s should be stand-alone.