RFQ Questions & Answers:
W91238-15-Q-0055 Success Lake Restroom & Fish Cleaning Station Janitorial Services RFQ
1. What is the current contract number, the incumbent contractor’s name and contract amount?
Answer: W91238-15-Q-0055 RFQ, the previous contract (W91238-13-C-0008) Success Lake Restroom &
Fishing Cleaning Station Janitorial was initially awarded for a base year plus 4 options, totaling $242,375.00 for all 5 years. We are not allowed to provide the current contractor’s name for the previous contract.
2. Are all 3 RFQs (i.e. W91238-15-Q-0053/W91238-15-Q-0054/W91238-15-Q-0055) new requirements and/or contracts?
Answer: Yes, they will be new requirements and/or contracts.
3. When will there be a site visit and how many site visits will be scheduled?
Answer: There will be only one official site visit. However, Contractors can call to request an alternate time for a site visit pending the staff's availability. Site Visit details are located under the "Addendum to Instructions to the Offerors" section of the RFQ: Site Visit Date & Time: Thursday, 6/25/15 at 10am (PDT), Location:
Success Lake, 29330 Highway 190, P.O. Box 1072, Porterville, CA 93258 and Mainline: 559-784-0215.
4. Were any of the current contracts previously joint with the janitorial contracts pertaining to W91238-15-
Q-0053/W91238-15-Q-0054/W91238-15-Q-0055? If not, may you provide the incumbent contractor for that contract along with the previous bid price?
Answer: No, these were all individual contracts and not joint contracts. We are not allowed to provide the incumbent contractor’s name. See answer in the above Question #1.
5. May we fax or email our proposal and other required RFQ documents? If so, what is the fax number and/or email address? What are the RFQ deadline(s)?
Answer: Please email all proposals and other required solicitation documents to the following Contracting
POC and by the RFQ deadline(s):
US Army Corps of Engineers, Sacramento District, Contracting Division
Attn: Ms. Healon Knight, Contract Specialist
1325 J St., Sacramento, CA 95814
Email: Healon.D.Knight@usace.army.mil
W91238-15-Q-0055 Success Lake Restroom & Fish Cleaning Station Janitorial RFQ, Deadline: 06 July
2015, 5pm (PST)
6. Can a Prime Contractor use subcontractors for a project? Is there a minimum requirement for the prime’s percentage of participation in the actual work?
Answer: If the Prime Contractor is awarded the contract and subcontracts the work out, the Prime Contractor must perform at least 50% of the work, while the subcontractor performs the remaining 50% of the work.
7. What is the deadline to submit questions/inquiries regarding the solicitation?
Answer: Tuesday, 30 June 2015 at 5pm (PST). There will be no more inquires or questions answered after this date.