1. Attached signed and returned-missing signature top/middle of page

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Title: Indefinite Delivery, Indefinite Quantity Maintenance Dredging, Sacramento and San Joaquin Deep Water Ship Channels, California

The purpose of this Amendment is to:

1) Incorporate a Revised Pricing Schedule.

2) Correct Order Limitation amounts, Section 00 70 00, FAR Clause 52.216-19 ORDER LIMITATIONS.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 9

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-May-2012

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-12-B-0001

X 9B. DATED (SEE ITEM 11)

26-Mar-2012

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-May-2012

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91238-12-B-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION - CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications and

Drawings

511 02-FEB-2012

Attachment 2 Wage Determination 37 27-JAN-2012 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Specifications and

Drawings

511 02-FEB-2012

Attachment 2 Wage Determination 37 27-JAN-2012 Attachment 3 Revised Price Schedule 25 02-MAY-2012

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 08-May-2012 01:00 PM to 17-May-2012 01:00 PM.

The following have been deleted:

SACRAMENTO DWSC PRICING

STOCKTON DWSC PRICING

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been modified:

LOCAL INSTRUCTIONS

SECTION 00 22 13

INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS/OFFERORS

AND EVALUATION CRITERIA FOR AWARD

SUBMITTAL INFORMATION FOR SUPPLIERS (RFQS), BIDDERS (IFBS) AND OFFERORS

(RFPS):

The following documents must be returned with your quote, bid, or offer.

--The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.

--Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.

Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your quote, bid, or offer.

--The completed Pricing Schedule with your proposed contract line item prices inserted in the appropriate spaces. Prices must be proposed for all contract line items and priced sub-line items. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off extended prices to the nearest dollar. Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

--Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).

--Your Bid Guarantee (e.g., Standard Form 24, “Bid Bond”)

INQUIRIES:

Prospective bidders should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

a. For information related to amendments, and the dates set for bid opening, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Number is : W91238-12-B-0001

The Bidder Inquiry Key is: 8DKMDU-R68649 http://www.fedbizopps.gov/� https://www.projnet.org/projnet�

c. The Bidder Inquiry System will be unavailable for new inquiries 10 days prior to the bid opening date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Bidders are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. The point of contact for this solicitation is:

Contract Specialist: Monica Walker/Marsha Sells Telephone: (916) 557-5182/557-5232

FAX: (916) 557-5278.

E-MAIL: Monica.D.Walker@usace.army.mil , Marsha.R.Sells@usace.army.mil , AND Carol.A.Dones@usace.army.mil

DIRECTIONS FOR SUBMITTING BIDS:

Envelopes containing bids must be sealed, marked and addressed as follows:

MARK ENVELOPES:

Solicitation No. W91238-12-B-0001 Bid Opening Date: May 17, 2012 Bid Opening Time: 1:00 PM Local Time

ADDRESS ENVELOPES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTIONS PERTAINING TO HAND-CARRIED BIDS:

Hand-carried bids must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, all Corps of Engineers visitors are now required to sign-in, leave a Photo-ID (such as a drivers license), and get a Visitor’s Pass at the Security Desk in the Building Lobby. Bidders may no longer hand-carry their bids directly to Contracting Division. Bids may NOT be either turned-in at the Security Desk or left unattended elsewhere in the Lobby.

Additionally, you are advised that there is no public parking in the Building.

The Bid Opening Officer will be in the Building Lobby 20 minutes prior to the scheduled bid opening time to accept sealed bids. After announcing that no mailto:Monica.D.Walker@usace.army.mil� mailto:Marsha.R.Sells@usace.army.mil� mailto:Donna.S.Hammock@usace.army.mil� further bids will be received, the bidders waiting in the Building Lobby will then be escorted as a group to the Bid Opening Room, where the bids will be publicly opened and read.

Bidders who desire to hand-deliver their bids at an earlier time must notify the contract specialist in advance to arrange to be met in the Building Lobby by Contracting Division personnel. In the event the contract specialist cannot be reached, please call the main Contracting Division telephone number, (916) 557-5201, in order to request assistance.

Please ensure that all courier and delivery personnel are aware of these procedures.

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Attachments, Preaward Survey). The Preaward Survey is attached to the solicitation for information purposes only. It will be required from only the low bidder. After the Bid Opening, the Government will request this information from the low bidder if the low bidder has not had a contract with the Sacramento District within the last twelve months and the Government will set a due date for its submission. The Preaward Survey is not required as part of the bid package.

In order to be determined to be responsible a prospective contractor must:

a. Have adequate financial resources to perform the contract or the ability to obtain them.

b. Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments.

c. Have a satisfactory performance record. In making the determination of responsibility, the Government Contracting Officer shall consider relevant past performance information. A prospective contractor shall not be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history except when there are special standards set forth in the solicitation which applies to all bidders that must be met in order to receive the award. These special standards may be necessary when unusual expertise or specialized facilities are necessary in the performance of the contract; therefore, in order to be determined to be responsible for that particular contract, the offeror must be able to meet those special standards. A prospective contractor that is or recently has been seriously deficient in contract performance shall be presumed to be nonresponsible unless the Contracting Officer determines that the circumstances were beyond the contractor's control or that the contractor has taken appropriate corrective action. Other responsibility considerations by the Contracting Officer will include past efforts by the contractor to apply sufficient tenacity and perseverance to perform acceptably, to meet quality requirements of contracts, and the contractor's past compliance with subcontracting plans (if required) under recent contracts.

d. Have a satisfactory record of integrity and business ethics.

e. Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).

f. Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.

g. Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in subparagraphs a, e, and f above) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.

AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

a. The internet URL for Corps of Engineers publications is:

http://140.194.76.129/publications/

b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications.

Information about the CCB can be obtained from:

http://www.wbdg.org/ccb/ccb.php

EVALUATION FOR AWARD:

The Government contemplates award of one contract to the responsive, responsible bidder who submits the low bid for the total of the following items in Pricing Schedule:

All line items listed in Pricing Schedule.

If the solicitation's Pricing Schedule contains options, see evaluation of options clause below for information on the procedure used by the Government to determine "low bid".

TELEGRAPHIC BIDS:

TELEGRAPHIC BIDS/OFFERS ARE NOT ACCEPTABLE.

http://140.194.76.129/publications/� http://www.wbdg.org/ccb/ccb.php�

However, bids may be modified or withdrawn by written or telegraphic notice. Any telegram to modify or withdraw a bid sent to this office must be received in the office designated in the Invitation for Bids (IFB) for receipt of bids not later than the exact date and time set for bid opening. A telegraphic modification or withdrawal of a bid received in such office by telephone from the receiving telegraph office not later than the exact date and time set for bid opening shall be considered. However, the telephone message shall be confirmed by the telegraph company by sending a copy of the written telegram that formed the basis for the telephone call. The written telegram shall be sealed in an envelope by a proper official and sent to the office designated in the IFB for receipt of bids. The official shall write on the envelope (1) the date and time of receipt and by whom, and (2) the number of the IFB, and shall sign the envelope. The bidder is responsible to inform the telegraph company of these requirements. No one from this office will be dispatched to the local telegraph office to pick up any telegram for any reason.

FACSIMILE BIDS/OFFERS:

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

PREPARATION OF SUBCONTRACTING PLAN:

(a) See FAR 52.219-9, Section 00 70 00, of this solicitation.

Subcontracting Plans will be developed considering only the subcontracts actually to be awarded. Subcontracting Plans are required from other than small businesses if the contract price is over $1,500,000; they are not required from small business firms regardless of the contract price.

(b) For information on the evaluation of subcontracting plans, see Army Federal Acquisition Regulation Supplement, Appendix DD.

(c) Contact Ms. Michelle Stratton (916)557-7641, Deputy for Small Business, with questions on the Subcontracting Plan requirements and further instructions on submission of Electronic Subcontracting Reporting System (eSRS) as required by FAR 52.219-9.

(d) The Corps of Engineers highly encourages all bidders/offerors to meet the recommended subcontracting goals as follows:

Small Businesses 50.0%

Small Disadvantaged Businesses 17.0%

Women-Owned Small Businesses 18.0%

HUBZone Small Business 10.0%

Veteran-Owned Small Business 8.5%

Service Disabled Veteran Owned Small Business 4.0%

The goals are calculated as a percentage of the TOTAL SUBCONTRACTING DOLLARS, NOT THE TOTAL CONTRACT AMOUNT.

PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15 located in Section 00 70 00.

INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate. If this is an IFB, failure to provide pledges of acceptable assets, with the bid, in the specified form, accompanied by a properly executed SF 24 and SF 28, will render the bidder nonresponsible and thus ineligible for award. If this is an RFP, failure to provide required documentation described herein may cause the offeror to be deemed "unacceptable".

BID GUARANTEE FORM AND AMOUNT:

The bidder shall furnish a separate bid guarantee in accordance with the solicitation provision titled "Bid Guarantee", FAR 52.228-1. In accordance with FAR 28.101-2 the bid guarantee amount shall be at least 20 percent of the "bid price" but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated. If there are option line items on the Pricing Schedule, the term "bid price" is hereby defined as the total bid not to include any amount for line items designated as "options". In bids/proposals that contain "additives", the "bid price" is defined as the total of all bid items including additive line items. FAR 28.106-1 states that a Standard Form (SF) 24 shall be used for the bid bond. In accordance with FAR 28.202(a)(1), corporate sureties utilized must appear on the list contained in the Department of Treasury Circular 570 titled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies."

ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

END

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

52.216-19 ORDER LIMITATIONS. (OCT 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than $20,000, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor:

(1) Any order for a single item in excess of $10,000,000;

(2) Any order for a combination of items in excess of $10,000,000; or

(3) A series of orders from the same ordering office within 5days that together call for quantities exceeding the limitation in subparagraph (1) or (2) above.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) above.

(d) Notwithstanding paragraphs (b) and (c) above, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 5days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons.

Upon receiving this notice, the Government may acquire the supplies or services from another source.

(End of clause)

(End of Summary of Changes)

Line Item

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

0101AA Mobilization 1 LS $ 0.000023 $

0101AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

0101AC Demobilization 1 LS $ 0.000023 $

0102AA Pumping less than 5,000 ft * 1* CY $ 1 $

0102AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0102AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0102AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0102AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0102AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0103AA Pumping less than 5,000 ft * 1* CY $ 1 $

0103AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0103AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

Sacramento Deep Water Ship Channel Pricing Schedule

FROM DATE OF AWARD TO 31 MAY 2013

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

Unclassified dredge material (mud) with a depth of cut less than or equal to 2.0 ft

Unclassified dredge material (mud) with a depth of cut greater than to 2.0 ft

IDIQ Maintenance Dredging, Mobilization, Demobilization

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

0103AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0103AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0103AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0104AA Pumping less than 5,000 ft * 1* CY $ 1 $

0104AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0104AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0104AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0104AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0104AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0105AA Pumping less than 5,000 ft * 1* CY $ 1 $

0105AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0105AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0105AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0105AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0105AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

Disposal Sites, Class I, Class II, Return pumping

0106AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

0106AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

0106AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

Classified dredge material (sand) with a depth of cut greater than 2.0 ft

Classified dredge material (sand) with a depth of cut less than or equal to 2.0 ft

0107AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 0107AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 0107AC Gis Technician* 1* HR $ 0.00023 $ 0107AD Statistician* 1* HR $ 0.00023 $ 0107AE Technical Writer* 1* HR $ 0.00023 $ 0107AF Sample Site Construction* 1* HR $ 0.00023 $ 0107AG Sample vessel* 1* HR $ 0.00023 $

0108AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 0108AB Sampling Events per DMPS* 1* EA $ 0.00023 $

0108AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Sacramento DWSC Sub-Total (##) (Line Items 0101AA thru 0108AC) $

(##) TOTAL BID EVALUATION PRICE. THE BIDDER WILL MULTIPLE THE ABOVE UNIT PRICES BY THE

CORRESPONDING BID EVALUATION FACTOR FOR THE PURPOSES OF EVALUATING THE LOW BID:

NOTE—Material classification is based upon the shoaled area’s geographic location

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

Fish Monitoring and Entrainment

Methyl Mercury Monitoring and Evaluation

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

IDIQ Maintenance Dredging, Mobilization, Demobilization

1101AA Mobilization 1 LS $ 0.000023 $

1101AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

1101AC Demobilization 1 LS $ 0.000023 $

1102AA Pumping less than 5,000 ft * 1* CY $ 1 $

1102AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1102AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1102AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1102AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1102AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1103AA Pumping less than 5,000 ft * 1* CY $ 1 $

1103AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1103AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

Sacramento Deep Water Ship Channel Pricing Schedule

FROM 1 JUNE 2013 TO 31 MAY 2014

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

Unclassified dredge material (mud) with a depth of cut less than or equal to 2.0 ft

Unclassified dredge material (mud) with a depth of cut greater than 2.0 ft

1103AD

less than 20,000 ft* 1* CY $ 1 $

1103AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1103AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1104AA Pumping less than 5,000 ft * 1* CY $ 1 $

1104AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1104AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1104AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1104AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1104AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1105AA Pumping less than 5,000 ft * 1* CY $ 1 $

1105AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1105AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1105AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1105AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1105AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1106AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

1106AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

1106AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

Disposal Sites, Class I, Class II, Return pumping

1107AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 1107AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 1107AC Gis Technician* 1* HR $ 0.00023 $ 1107AD Statistician* 1* HR $ 0.00023 $ 1107AE Technical Writer* 1* HR $ 0.00023 $ 1107AF Sample Site Construction* 1* HR $ 0.00023 $ 1107AG Sample vessel* 1* HR $ 0.00023 $

1108AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 1108AB Sampling Events per DMPS* 1* EA $ 0.00023 $

1108AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Sacramento DWSC Sub-Total (##) (Line Items 1101AA thru 1108AC) $

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

(##) TOTAL BID EVALUATION PRICE. THE BIDDER WILL MULTIPLE THE ABOVE UNIT PRICES BY THE

CORRESPONDING BID EVALUATION FACTOR FOR THE PURPOSES OF EVALUATING THE LOW BID:

Methyl Mercury Monitoring and Evaluation

Fish Monitoring and Entrainment

NOTE—Material classification is based upon the shoaled area’s geographic location

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

IDIQ Maintenance Dredging, Mobilization, Demobilization

2101AA Mobilization 1 LS $ 0.000023 $

2101AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

2101AC Demobilization 1 LS $ 0.000023 $

2102AA Pumping less than 5,000 ft * 1* CY $ 1 $

2102AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2102AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2102AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2102AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2102AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2103AA Pumping less than 5,000 ft * 1* CY $ 1 $

2103AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2103AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

Sacramento Deep Water Ship Channel Pricing Schedule

FROM 1JUNE 2014 TO END OF PERFORMANCE PERIOD

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

2103AD

less than 20,000 ft* 1* CY $ 1 $

2103AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2103AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2104AA Pumping less than 5,000 ft * 1* CY $ 1 $

2104AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2104AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2104AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2104AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2104AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2105AA Pumping less than 5,000 ft * 1* CY $ 1 $

2105AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2105AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2105AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2105AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2105AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

Disposal Sites, Class I, Class II, Return pumping

2106AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

2106AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

2106AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

2107AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 2107AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 2107AC Gis Technician* 1* HR $ 0.00023 $ 2107AD Statistician* 1* HR $ 0.00023 $ 2107AE Technical Writer* 1* HR $ 0.00023 $ 2107AF Sample Site Construction* 1* HR $ 0.00023 $ 2107AG Sample vessel* 1* HR $ 0.00023 $

Methyl Mercury Monitoring and Evaluation

2108AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 2108AB Sampling Events per DMPS* 1* EA $ 0.00023 $

2108AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Sacramento DWSC Sub-Total (##) (Line Items 2101AA thru 2108AC) $

Sacramento DWSC Total (##) (Line Items 0101AA thru 2108AC) $

Fish Monitoring and Entrainment

NOTE—Material classification is based upon the shoaled area’s geographic location

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

(##) TOTAL BID EVALUATION PRICE. THE BIDDER WILL MULTIPLE THE ABOVE UNIT PRICES BY THE

CORRESPONDING BID EVALUATION FACTOR FOR THE PURPOSES OF EVALUATING THE LOW BID:

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

0201AA Mobilization 1 LS $ 0.000023 $

0201AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

0201AC Demobilization 1 LS $ 0.000023 $

0202AA Pumping less than 5,000 ft * 1* CY $ 1 $

0202AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0202AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0202AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0202AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0202AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0203AA Pumping less than 5,000 ft * 1* CY $ 1 $

0203AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0203AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

Stockton Deep Water Ship Channel Pricing Schedule

FROM DATE OF AWARD TO 31 MAY 2013

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

IDIQ Maintenance Dredging, Mobilization, Demobilization

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

0203AD

less than 20,000 ft* 1* CY $ 1 $

0203AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0203AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0204AA Pumping less than 5,000 ft * 1* CY $ 1 $

0204AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0204AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0204AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0204AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0204AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

0205AA Pumping less than 5,000 ft * 1* CY $ 1 $

0205AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

0205AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

0205AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

0205AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

0205AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

Disposal Sites, Class I, Class II, Return pumping

0206AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

0206AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

0206AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

0207AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 0207AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 0207AC Gis Technician* 1* HR $ 0.00023 $ 0207AD Statistician* 1* HR $ 0.00023 $ 0207AE Technical Writer* 1* HR $ 0.00023 $ 0207AF Sample Site Construction* 1* HR $ 0.00023 $ 0207AG Sample vessel* 1* HR $ 0.00023 $

0208AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 0208AB Sampling Events per DMPS* 1* EA $ 0.00023 $

0208AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Stockton DWSC Sub-Total (##) (Line Items 0201AA thru 0208AC) $

Methyl Mercury Monitoring and Evaluation

Fish Monitoring and Entrainment

NOTE—Material classification is based upon the shoaled area’s geographic location

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

IDIQ Maintenance Dredging, Mobilization, Demobilization

1201AA Mobilization 1 LS $ 0.000023 $

1201AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

1201AC Demobilization 1 LS $ 0.000023 $

1202AA Pumping less than 5,000 ft * 1* CY $ 1 $

1202AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1202AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1202AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1202AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1202AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1203AA Pumping less than 5,000 ft * 1* CY $ 1 $

1203AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1203AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

Stockton Deep Water Ship Channel Pricing Schedule

FROM 1 JUNE 2013 TO 31 MAY 2014

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

1203AD

less than 20,000 ft* 1* CY $ 1 $

1203AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1203AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1204AA Pumping less than 5,000 ft * 1* CY $ 1 $

1204AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1204AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1204AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1204AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1204AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1205AA Pumping less than 5,000 ft * 1* CY $ 1 $

1205AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

1205AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

1205AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

1205AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

1205AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

1206AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

1206AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

1206AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

Classified dredge material (sand) with a depth of cut greater than 2.0 ft

Disposal Sites, Class I, Class II, Return pumping

1207AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 1207AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 1207AC Gis Technician* 1* HR $ 0.00023 $ 1207AD Statistician* 1* HR $ 0.00023 $ 1207AE Technical Writer* 1* HR $ 0.00023 $ 1207AF Sample Site Construction* 1* HR $ 0.00023 $ 1207AG Sample vessel* 1* HR $ 0.00023 $

1208AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 1208AB Sampling Events per DMPS* 1* EA $ 0.00023 $

1208AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Stockton DWSC Sub-Total (##) (Line Items 1201AA thru 1208AC) $

Fish Monitoring and Entrainment

Methyl Mercury Monitoring and Evaluation

NOTE—Material classification is based upon the shoaled area’s geographic location

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

Description QTY Unit of Issue

Unit Price Bid

Evaluation Factor

Bid Evaluation Price

IDIQ Maintenance Dredging, Mobilization, Demobilization

2201AA Mobilization 1 LS $ 0.000023 $

2201AB

Incremental Mobilization Between Disposal Sites or Dredging Reaches* 0.1* Mile $ 0.0114 $

2201AC Demobilization 1 LS $ 0.000023 $

2202AA Pumping less than 5,000 ft * 1* CY $ 1 $

2202AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2202AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2202AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2202AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2202AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2203AA Pumping less than 5,000 ft * 1* CY $ 1 $

2203AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2203AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

Unclassified dredge material (mud) with a depth of cut less than or equal to 2.0 ft

Stockton Deep Water Ship Channel Pricing Schedule

FROM 1JUNE 2014 TO END OF PERFORMANCE PERIOD

CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY TO

PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS SET FORTH IN

THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO. PRICING SCHEDULE UNIT PRICES WILL BE MULTIPLIED BY THE BID EVALUATION FACTOR SHOWN BELOW FOR THE BID EVALUATION PRICE

Dredging, Disposal, and Water Quality Monitoring with a pumping/1-way transit distance and dredge material consisting of:

2203AD

less than 20,000 ft* 1* CY $ 1 $

2203AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2203AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2204AA Pumping less than 5,000 ft * 1* CY $ 1 $

2204AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2204AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2204AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2204AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2204AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

2205AA Pumping less than 5,000 ft * 1* CY $ 1 $

2205AB

Pumping between 5,000 ft and less than 10,000 ft* 1* CY $ 1 $

2205AC

Pumping between 10,000 ft and less than 15,000 ft* 1* CY $ 1 $

2205AD

Pumping between 15,000 ft and less than 20,000 ft* 1* CY $ 1 $

2205AE

Pumping between 20,000 ft and less than 25,000 ft* 1* CY $ 1 $

2205AF

Pumping between 25,000 ft and less than 30,000 ft* 1* CY $ 1 $

Disposal Sites, Class I, Class II, Return pumping

2206AA Prep of Class I, Disposal Sites* 1* EA $ 0.000046 $

2206AB Prep of Class II, Disposal Sites* 1* EA $ 0.000046 $

2206AC

Disposal site return water pumping (for sites that require return water pumping per hour* 1* HR $ 0.0027 $

2207AA Sr. Fisheries Biologist* 1* HR $ 0.00023 $ 2207AB Jr. Fisheries Biologist* 1* HR $ 0.00023 $ 2207AC Gis Technician* 1* HR $ 0.00023 $ 2207AD Statistician* 1* HR $ 0.00023 $ 2207AE Technical Writer* 1* HR $ 0.00023 $ 2207AF Sample Site Construction* 1* HR $ 0.00023 $ 2207AG Sample vessel* 1* HR $ 0.00023 $

Methyl Mercury Monitoring and Evaluation

2208AA DMPS Prep for MeHg Evaluation* 1* EA $ 0.00023 $ 2208AB Sampling Events per DMPS* 1* EA $ 0.00023 $

2208AC Laboratory Samples per DMPS* 1* EA $ 0.00023 $

Stockton DWSC Sub-Total (##) (Line Items 2201AA thru 2208AC) $

Stockton DWSC Total (##) (Line Items 0201AA thru 2208AC) $

(##) TOTAL BID EVALUATION PRICE. THE BIDDER WILL MULTIPLE THE ABOVE UNIT PRICES BY THE

CORRESPONDING BID EVALUATION FACTOR FOR THE PURPOSES OF EVALUATING THE LOW BID:

Fish Monitoring and Entrainment

NOTE—Material classification is based upon the shoaled area’s geographic location

* THE ACTUAL DREDGE QUANTITY CAN VARY BETWEEN 0 AND 600,000 CY FOR THE DREDGING YEAR.

THE ACTUAL INCREMENTAL MOBILIZATION BETWEEN DISPOSAL SITES CAN VARY BETWEEN 500 FEET AND 50 MILES. THE NUMBER OF DISPOSAL SITES REQUIRING PREPARATION CAN VARY BETWEEN 1 AND 10 SITES. THE NUMBER OF DISPOSAL SITES REQUIRING METHYL MERCURY MONITORING CAN

VARY BETWEEN 2 TO 5 SITES.

ADDITIONAL INSTRUCTIONS:

Pricing Schedule

b. For the purpose of bid/offer evaluation, the Government will proceed on the assumption that the bidder/offeror intends the bid/offer to be evaluated on basis of the unit prices, the total arrived at by resolution of arithmetic discrepancies as provided above and the bid/offer will be so reflected on the abstract of bids/offers.

iv. Apparent errors in addition of lump-sum and extended prices will be corrected.

The second digit in the “Line Item No” indicates the deep water ship channel (1 is for Sacramento and 2 is for Stockton). The distinction is necessary for use in the Resident Management System (RMS) which the Corps uses for management of the contract.

This contract covers the mobilization, demobilization, dredging, operation and maintenance of upland disposal area(s), fish entrainment, and water quality monitoring along the Stockton and Sacramento Deep Water Ship Channels for a 3 year contract. Task Orders will be priced according to the average depth of cut and the distance between the shoal and the disposal site.

Notwithstanding any other provisions of this solicitation, the award will be made to the lowest responsible and responsive bidder. Bidders must submit prices on all items.

Prices must be submitted on all individual items of this Pricing Schedule. Failure to do so may be cause for rejection of bids.

The bidder/offeror shall distribute his indirect costs (overhead, profit, bond, etc.) over all the items in the Pricing Schedule. The Government will review all submitted Pricing Schedules for any unbalancing of the items. Any submitted Pricing Schedule determined to be unbalanced may be considered nonresponsive and cause the bidder to be ineligible for award.

The lump sum, "LS", line items above are not subject to the Variation in Quantity contract clause

EFARS 52.214-5000 APPARENT CLERICAL MISTAKES - ARITHMETIC

DISCREPANCIES (DEC 1995)—EFARS

a. For the purpose of initial evaluation of bids/offers, the following will be utilized in resolving arithmetic discrepancies found on the face of the Pricing Schedule as submitted by bidders/offerors:

i. Obviously misplaced decimal points will be corrected

ii. Discrepancy between unit price and extended price, the unit price will govern;

iii. Apparent errors in extension of unit prices will be corrected;

8 TASK ORDERS

9 PRICING OF TASK ORDERS

a. Each Task Order will be negotiated according to the requirements described in the Scope of Work. The limits of work will be divided into specific dredging reaches each identified with beginning and ending stationing and disposal site. The depth of cut and pumping/transit distance will be determined in 1000 ft increments within each dredging reach by the Contractor using dredge volume information from the most recent hydrographic survey which will accompany each scope of work. Generally, the survey information will be based on channel condition soundings collected in the spring of the current dredging year.

Using this information, the Contractor will then prepare and submit a cost proposal for the work. Dredging and other related costs will be based on the corresponding unit prices selected from the Pricing Schedule. Adjustments to the unit price may be made if the final dredge quantities for a particular reach will result in a different unit cost due to a change in the depth of cut or pumping/transit distance. Final pay yardage will be determined by pre-dredge and post-dredge construction surveys. The following example describes how the

c. These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

a. Each task order will have a scope of work that will describe the needed work. The major elements of the task order are: mobilization, demobilization, drawings indicating the limits of dredging and available disposal sites, and the need for any incremental mobilization.

Accompanying the scope of work will be a request for cost proposal which will be based on the Pricing Schedule that the Contractor will provide within the specified preparation period.

Upon the Contracting Officer’s acceptance of the Contractor’s cost proposal, a task order will be awarded. An example of a task order and the procedures for pricing the task order cost proposal is provided.

b. The Government may issue multiple task orders requiring performance at multiple locations within one or both ship channels. In such instances, the Contractor shall perform the work at multiple locations consecutively and in the order of priority described in the applicable task order(s). Task orders may be delayed or not issued for such reasons as funding limitations, delays due to obtaining the necessary regulatory permits, disposal sites, high river stages, resolution of water quality issues, or other circumstances. The contractor will not be entitled to any compensation for any delays caused by the Government in issuing or awarding task orders within the dredging window of each respective ship channel.

c. Historically, the Government has issued task orders that cumulatively resulted in dredging an estimated amount of 300,000 (or more) cubic yards of material.

d. Initial Task Order: The Government intends to negotiate and issue its first task order as soon as practicable after award of the contract.

EXAMPLE -- Pumping/Transit Distance:

Determine Starting Point = Sta 645+50;

Determine Landing Line Put in Location = sta 645+50;

Determine mid-points of the 1000' and fractional segments beginning at the starting pt

MP-1 = sta 650+50 MP-2 = sta 660+50 MP-3 = sta…