W91238-10-R-0061 1 of 5 Task Order Statement of Work August 20, 2010
Statement of Work August 20, 2010
Renovation of Bathrooms BT Collins
Sacramento, CA
Scope of Work
The work consists of renovations to various bathrooms in Building 650 at the Sacramento USARC located at BT Collins, Sacramento, CA.
Task Order Description
The intent of this project is to renovate two existing bathrooms, and install a public ADA bathroom located at the BT Collins Army Reserve Center, Army Lodging Facility. Renovation shall include the complete removal of non-compliant fixtures and the installation of new ADA compliant plumbing fixtures in Suites 1 and 3. All work will be accomplished per the scope of work, as shown in both the written scope and the drawings.
Specific:
The Contractor shall provide all plant, labor, equipment, and material necessary to perform renovations to various bathrooms at Building 650 at BT Collins in Sacramento, California as described on the attached sketches and per the following scope.
Demolition:
1. Prior to the start of any demolition of the two bathrooms, the Contractor shall locate all utilities and secure the electrical panel and lock out the circuits associated with the bathroom renovations. All water supplies to the existing bathrooms shall be isolated and shut off. If no shut off is available to isolate the bathrooms, then the water will be turned off to the building and a shut off valve will be installed. Water shut off valves shall be installed for the new ADA latrine. The main supply water lines and electrical must be maintained throughout the building during the length of construction. The Contractor shall protect at all times, the existing heating system on the North walls.
2. The Contractor shall completely remove and dispose of all floor tile, carpet, base boards, and mastic.
3. All asbestos containing material shall be disposed of in accordance with all federal, state and local laws and regulations. The Contractor shall submit an asbestos abatement plan prepared by a Certified Industrial Hygienist. All asbestos abatement shall be performed by a Certified Asbestos Abatement Contractor.
W91238-10-R-0061 2 of 5
4. The Contractor shall remove all furniture from Suites 1 and 3 and the break areas to a designated location coordinated with the Contracting Officer’s Representative.
5. The Contractor shall remove all bathroom fixtures in both Suites to include the fiberglass showers, commodes, sinks, cabinets, towel bars, hooks, and removable soap and cup holder.
Remove all associated plumbing fixtures and discard back to the wall area supply. Any existing plumbing, such as drain and supply lines that will not be re-used, shall be properly capped off behind the walls or under the flooring.
6. All electrical lighting, exhaust fans, outlets, and switches shall be removed, along with associated wiring back to a control junction box. All light tubes, ballast, and electrical lock sets shall be turned into the maintenance personnel at the Army Lodging Facility.
7. Interior bathroom doors and walls shall be removed per the attached plans. These walls are non-load bearing and shall be rebuilt, providing additional required space. All existing bathroom flooring materials shall be removed and the floor areas properly cleaned for the future installation of ceramic tile. The existing hard ceiling in the bathrooms shall be demolished to provide access to all electrical removal and changes.
8. The existing ceiling mounted HVAC units in Suites 1 and 3 shall be removed and stored for re-installation. During removal of the HVAC units, all ceiling T-Bar grids shall be removed to accommodate the new walls being installed and allow for the new T-bar grid and tiles to be installed at a later time.
9. The existing carpeting in Suites 1 and 3 in the area for the new bathroom shall be pulled back halfway through the room, covered and protected for re-installation.
10. Demolish hallway doors to Suites 1 and 3 saving the door hardware for re-installation later.
The existing doors and all door framing shall be removed. The new openings shall be installed per the plans to accommodate a proper Handicap door width.
Installation:
1. After all demolition is complete, Suites 1 and 3 and the public bathroom will have the same type of ADA compliant bathrooms installed, except for no shower in the public bathroom. The Contractor shall install new living quarter entry doors to the rooms, providing a minimum 3’6” opening. All framing shall be metal construction and constructed in a solid manner, attaching to the existing all framing. The existing door location shall be closed up using new metal studs. A new one hour fire rated door shall be installed in each Suite and the previously removed hardware and lock shall be re-installed. The remainder of the exposed walls shall have 5/8” sheetrock installed, and taped and textured to match the existing.
2. The Contractor shall install the new 2 x 4 steel wall studs to form the new outline of the bathrooms. All studs shall be tightly secured to both the floor and the hard lid ceiling above.
The new bathroom ceiling shall also be constructed out of 2 x 4 steel studs and secured to the existing exterior walls and the new interior wall studs. All required plumbing and electrical changes shall be made prior to closing in the walls, ceilings and floors.
W91238-10-R-0061 3 of 5
3. Installation of the new rough-in plumbing shall be inside the walls. The relocated shower lines, and extension of the shower supply hot and cold lines shall be inside the walls. All water lines shall have solid supports built into the wall system to keep them from vibrating and pulling loose.
4. The shower plumbing shall have an anti-scald adjustable valve with a slide bar hand-held shower head and lose long enough to reach all areas of the shower stall. The shower head shall have a self-cleaning spray area with a minimum of two settings, one for full spray and one for pulsating spray.
5. A new handicap shower stall shall be installed using a pre-formed ADA approved Roll-in shower, 63” x 34” x78-3/4” with a inside dimension of 60” x 30” overall clearance. The unit shall have a ¾” threshold with a pre-leveled reinforced base for easy installation. The unit shall have an inside corner grab bar, two molded soap ledges, a molded foot ledge, frameless white HDPE fold-up seat, and a curtain rod and drain.
6. New recessed can lighting and exhaust fans shall be installed into the hard shell ceiling. The ceiling shall be sheet rocked, textured and painted. There shall be two can lights in the main bathroom area, one each explosion proof light over the new shower stall and a new sconce light above the sink and mirror. New wiring shall be linked to a new wall switch located by the door entry and placed at ADA approved height. The sconce light shall use the existing electrical location and work in conjunction with all other lighting in the room. Low energy light bulbs shall be used where possible.
7. Install new walls of 5/8” sheet rock with moisture proof green board in the interior of the bathroom and regular on the exterior. All joints shall be taped and textured and prepared for tile installation from floor to ceiling.
8. The Contractor shall install new 2” x 2” ceramic floor tile and 6” x 6” ceramic wall tile as shown on the drawings. All tile shall be properly grouted using approved matching color grout.
All corner joints shall be caulked rather than grouted to allow for expansion and contraction. All tile and grout shall be properly sealed using an approved grout and tile sealer. A double row of accent tile shall be placed around the entire room, five feet above the floor level. The accent tile shall be place using alternating locations between rows.
9. A new ADA compliant, floor mounted, tank type toilet shall be installed with a tank mounted flush valve. Toilet seats shall be white in color, shall have an open front and securely fastened to the toilet.
10. A new free standing solid surface countertop shall be installed, using appropriate metal wall supports, at ADA compliant height. The countertop shall have a four inch back splash made from the same material as the countertop. Install new soap dispensers, faucets and drains per attached drawings. A new 36” x 24” framed wall mirror shall be installed centered above the countertop. The new sconce light shall be installed above the mirror and sink.
W91238-10-R-0061 4 of 5
11. Install a new T-Bar ceiling with new HVAC vents and reinstall the existing ceiling mounted HVAC units in Suites 1 and 3. The new ceiling tiles shall be 2’ x 2’ in the living area of Suites 1 and 3 and in new storage area.
12. The carpet in the area that the public ADA latrine is to be installed shall be removed, stored and re-installed in the area marked “new storage area”. A new 4’-inch base board shall be installed on the walls.
13. The light switch located on the north column to the right of the public bathroom shall be relocated to the south column.
NOTE: All material and fixture listed in the attached drawings shall be considered equal to or better than.
General Requirements:
1. The intent of this project is to provide the government with a complete and usable product at the completion.
2. The Contractor shall furnish all plant, labor, equipment, and materials necessary to provide a complete and usable project per the Scope of Work and Manufacturer’s recommendations. All work shall be free from defects.
3. All work shall be performed in accordance with the current International Building Codes (IBC), and the parent SATOC contract specifications.
4. The Contractor shall verify all dimensions, site conditions, and any other items required to for this construction project.
5. The Contractor shall, at all times, keep the premises free from accumulation of waste material and rubbish caused by his work, or his subcontractors. The Contractor shall coordinate site location for placement of debris container (if necessary) and equipment and material storage area with the COR. At the completion of work, the Contractor shall thoroughly clean the work site.
All debris, rubbish, and waste material shall be removed from the property at the Contractor’s expense and disposed of in accordance with all federal, state and local laws and regulations at an official disposal site.
6. The Contractor shall submit for approval on all new items being installed on this project prior to ordering of any materials. Submittal may be shop drawings, diagrams, catalogue cut-sheets, and any other related material.
7. Adhere to general requirements within the environmental protection section. Hazardous material shall be disposed of in accordance with all Federal, state and local regulations. ACM removal shall be performed by a California Contractor certified to conduct asbestos-related work and or an employer/contractor registered with the California Division of Occupational Safety and Health (DOSH)) to perform asbestos-related work. Contractor is responsible for all notification
W91238-10-R-0061 5 of 5 and coordination with the local Air Pollution Control District in accordance with Rule 424 as well as Cal/OSHA requirements.
8. Safety. It is the contractor’s responsibility to comply with the pertinent sections of the “construction safety orders” issued by the State of California, latest editions; all OSHA requirements as they apply to this project; and the USACE Safety and Health Requirements Manual EM 385-1-1, latest edition.
9. Work plan. Construction work shall not commence work until the Contracting Officer’s Representative approves the contractor’s work plan.
10. Contractor will set up lay-down /staging areas in accordance with the Contracting Officer or guidance established. Contractor storage shall be fenced and secured by the contactor.
11. The Contractor shall coordinate work schedule with the Contracting Officer's Representative (COR), Mr. Steven Scholten, prior to the execution of work. Normal work schedule is from 0745 - 1645, Monday through Friday, except for Federal Holidays.
12. The Contractor shall submit a list of employees to the COR for security access processing and approval. List shall contain the employee's full name, state driver's license number and date of birth. Contractor shall be prepared upon request to be searched by the installation security guard force.
13. The Contractor shall obtain all required permits for prior to the commencement of work.
14. The Contractor shall maintain a set of As-Built drawings on site at all times, and shall submit the As-Built drawings to the Contracting Officer’s representative upon completion of the project.
Submittals
Site safety and health plan, quality control plan, all materials to be used in the contact, and all additional submittals required in the specifications.
General Information (definitions, etc) None
Government-Furnished Property None
Appendices
Drawings (total of 7 pages).