Section B - Supplies or Services and Prices

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
3
Each

Aluminum Dock Sections

FFP

Furnish all drawings, labor, materials and equipment necessary to fabricate, haul and install three (3) new aluminum dock sections to be inserted in-between existing docks, at three different site locations within the recreation area. Each dock will be 8-foot wide x 20-foot long and include one (1) 12-inch wheel on each corner of the dock [total four (4)], six (6) powder-coated yellow cleats, yellow UHMW fenders and a chain box at end for chain tie-ups and all anchor-chain/pulley/buoy hardware associated for main cable attachment. (All items will be per reference drawing #10043 and technical specifications). The docks will be for the Fiddleneck Recreation Area Boat Ramps at New Hogan Lake, Calaveras County, Valley Springs, California. All tasked will be completed in accordance with the attached Statement of Work, Special Provisions and Specifications.

Notes:

1. Contractor is requested to submit one copy of the invoice to the Park Manager upon completion of Service (this will help expedite receipt of payment).

2. For information or a site visit of the work area, please contact the, the Park Manager or his authorized representative. (209) 772-1625.

Technical Point of Contact: Duane Johnson (209) 772-1343

Contracting Point of Contact: Tilsen Brooks Jr. (916) 557-7929

FOB: Destination

PROJECT: New Hogan Docks

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lump Sum

Delivery and Installation

Deliver and unload docks at sites, hook-up to existing docks and anchor wire ropes and supply of all required materials.

PROJECT: New Hogan Docks

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Lump Sum

ARRA Reporting Costs

Costs associated with the reporting requirements of the American Recovery and Reinvestment Act of 2009. Requirements at section I, clause 52.204-11. If no additional charge enter NSP (Not Separately Priced) for this line item.

NET AMT

Section C - Descriptions and Specifications

SCOPE OF WORK

SCOPE OF WORK

1. GENERAL:

A. SCOPE - Contractor shall provide all drawings, labor, transportation, materials and equipment necessary to fabricate, haul and install these docks. Contractor shall be responsible for all job planning, programming, permitting, scheduling, administration, inspection, and management required to accomplish specified project. Contractor shall ensure that all work is accomplished in accordance with contract specifications and scope of work, all applicable laws, municipal codes, regulations and/or written directives issued by the Contracting Officer.

B. INTENT

1) NEW HOGAN LAKE ITEMS 0001A-B:

Three (3) new aluminum dock sections will be delivered and installed in-between existing docks, at three different site locations within the recreation area. Each dock will be 8-foot wide x 20-foot long and will include one (1) 12-inch wheel on each corner of the dock, six (6) powder-coated yellow cleats, yellow UHMW fenders and a chain box at end for chain tie-ups and all anchor-chain/pulley/buoy hardware associated for main cable attachment. All items must be per the attached reference drawing #10043 and technical specifications, to maintain the integrity of the current docking system and assure the safety of users. The dock will be for the Fiddleneck Recreation Area Boat Ramps at New Hogan Lake, Calaveras County, Valley Springs, California.

C. LOCATION DESCRIPTION

NEW HOGAN LAKE ITEMS 0001A-B: Work site is located at 2713 Hogan Dam Road, Valley Springs CA 95252.

D. PERMITS - The contractor shall, without any additional expense to the government, provide any necessary/required licenses or permits for the completion of this contract. The contractor shall comply with all Federal, State, County and municipal laws, codes, and/or regulations in connection with the performance of specified work.

E. SAFETY - All work shall be performed in accordance with safety requirements set forth in Corps of Engineers Manual, EM 385-1-1, entitled Safety and Health Requirements Manual, 15 Sept 08. Copies are available at the Englebright Lake Park Office.

2. WORK SCHEDULE:

A. PREWORK CONFERENCE

NEW HOGAN LAKE ITEMS 0001A-B: A pre-work conference between the Contractor, his/her representatives, supervisors, workers, etc. and the New Hogan Lake Park Manager, shall be scheduled prior to the installation of the docks. The Contractor shall submit to the Contracting Officers Representative (Park Manager), all required reports, plans, permits, licenses, and other items outlined in this contract.

3. CONTRACTOR OBLIGATIONS:

A. EXPOSURE REPORT - A safety exposure report shall be submitted to the Park Manager prior to the completion of the contract.

4. CONTRACTOR RESPONSIBILITIES:

A. The contractor is liable for all damage to property, equipment, and landscape features in performance of this work. Any such damage shall be immediately reported to the Park Manager and repaired at the contractor's expense.

B. All waste material generated in performing this contract shall be removed from government property and disposed of at an approved waste disposal site. The contractor shall comply with all Federal state and local guidelines as they pertain to the proper excavation, removal and disposal of waste material generated during the performance of this contract.

5. FACILITIES AND EQUIPMENT:

A. STORAGE - Government storage space shall be provided under this contract. Equipment and material storage areas will be identified after the contract has been awarded.

B. GOVERNMENT FURNISHED SUPPLIES AND MATERIALS - The Government shall not provide any supplies or materials under this contract.

C. CONTRACTOR FURNISHED SUPPLIES AND MATERIALS - The Contractor shall furnish all supplies and materials to be consumed or incorporated in the execution of this contract. The Contractor shall be responsible for maintaining an adequate supply of materials each working day as necessary for performing the project as described.

6. PERSONNEL:

A. MINIMUM PERSONNEL REQUIREMENTS - The Contractor shall provide an adequate number of fully qualified personnel to perform the specified project safely, properly and efficiently within the time constraints of this contract.

B. QUALITY CONTROL - The Prime Contractor is responsible for ensuring that all work performed under this contract, including that performed by subcontractors, is in accordance with the specifications. To accomplish this, the Contractor will appoint in writing, subject to the approval of the COR, a Quality Control Inspector (QCI).

7. INSPECTION:

A. GOVERNMENT QUALITY ASSURANCE - The government shall monitor the Contractor’s services through scheduled, unscheduled, and in some cases, 100% inspections of the project as described.

B. CONTRACTOR PERFORMANCE DEFECTS, DEFICIENCIES AND REPERFORMANCE - Defects and deficiencies in Contractor performance and re-performance shall be determined and addressed by the COR. The government reserves the right to deduct portions of payment for any deficiencies in the completed project.

8. SITE SHOWING:

NEW HOGAN LAKE ITEMS 0001A-B: A site showing is available. To arrange a site visit, call the project office at (209) 772-1343 for more information.

9. PAYMENT:

NEW HOGAN LAKE ITEMS 0001A-B: Payment shall be made in arrears; invoices shall be submitted to: U.S. Army Corps of Engineers Finance Center, ATTN: CEFC-AO-P, 5720 Integrity Drive, Millington, TN 38054-5005 after completion and acceptance of contract specifications to the address indicated on the purchase order. One copy of the invoice shall be sent to the Park Manager at New Hogan Lake, 2713 Hogan Dam Road, Valley Springs, CA 95252.

TECHNICAL SPECIFICATIONS

TECHNICAL SPECIFICATIONS

1. ALUMINUM-DECKED TUB-FLOATATION DOCK SPECIFICATIONS GENERAL REQUIREMENTS:

These specifications are for a fully CAD designed and engineered aluminum decked tub flotation dock system and are the minimum standards for design and fabrication.

A. ENGINEERING - Dock flotation shall be designed to support the dead weight of the complete dock, including any permanently attached accessories, plus an additional live load of 20 pounds per square foot over the entire dock area. Flotation material shall be distributed as widely as possible under the dock for maximum stability. Minimum freeboard under combined dead and live load shall not be less than 8 inches. Freeboard under dead load only shall be between 16 and 22 inches.

B. FACTORS OF SAFETY - The deck and structural components shall be designed with minimum safety factors on working stresses, which conform to those specified in the American Association Design Manual specification for aluminum structures, as applicable.

C. VERTICAL DESIGN LOADS - The dock structure and deck shall include the dead weight of the dock components as well as a vertical distributed live load of 20 pounds per square foot of dock area. The deck and structural components shall also be designed to support the dead load plus a concentrated vertical live load of 400 pounds applied over a 6”x 6” area located anywhere on the deck surface. The distributed and concentrated live loads need not be applied simultaneously.

D. HORIZONTAL DESIGN LOADS - The dock structure and deck shall be designed for a lateral load of 150 pounds per foot of length to account for wind and water currents.

E. CONNECTIONS BETWEEN DOCK MODULES - Connecting hardware (hinges) and its attachments between any adjacent dock modules shall be designed to support a bending moment in the horizontal plane of 3000 foot- pounds.

2. MATERIALS DECKING:

A. DECKING - Decking shall be aluminum deck slat 6” wide by 1.61” deep produced from alloy 6061-T6 with ribbed non-skid surface. The deck slats shall interlock the top and bottom with rolled interlocks that cause the slats to act together when loaded. The ends of the deck slats interlock into the structural frame and are retained without welding. After installation, the decking shall give an AA-M44 (course matte) finished to increase skid resistance, reduce glare, and give a uniform appearance.

B. FENDERS

NEW HOGAN LAKE ITEMS 0001A-B: Fenders shall be 2”x 10” yellow UHMW plastic lumber bolted to the side frame with 3/8” galvanized bolts

C. STEEL BOLTS - Bolts shall be American standard regular with hexagonal heads and nuts, and shall be hot-dipped galvanized in accordance with ASTM Al 5 3.

D. FLOTATION TUBS - The buoyant units of the docks shall be polyethylene tubs having a wall thickness of at least 0.150”. The tubs shall conform to ASTM D 1248 and shall be manufactured in such a way as to be resistant to UV radiation from sunlight for 20 years. The tubs shall be completely filled with polystyrene foam. A manufacturer who has been continuously engaged in production of polystyrene foam for flotation for at least five years shall produce the foam. The foam shall have a minimum density, in place, of 0.9 pounds per cubic foot and a maximum density of 1.2 pounds per cubic foot.

E. CONNECTION OF TUBS - The dock structure shall bear on the polyethylene tubs and tubs shall be attached to the dock frame with 3/8” hot-dipped galvanized bolts. The bolts shall pass through the aluminum channel edge binding, the flange of the tub, and through the frame of the docks.

F. MOORING CLEATS – Powder-coated yellow mooring cleats shall be installed on the dock as specified in this contract. The cleats shall have, as a minimum, the dimensions shown on the drawings, be fabricated steel, galvanized after fabrication, powder-coated yellow cleats, and shall be sufficient to withstand a static load of 500 pounds in any direction, applied to a rope secured to the cleat.

3. FABRICATION & WORKMANSHIP:

A. WORKMANSHIP - The quality of workmanship shall be equal to the best general practice in modern structural fabrication shops.

B. EXPERIENCE - The fabricator must be able to furnish adequate evidence of a minimum of five years of ongoing successful experience in fabricating aluminum dock structures, and show that all workmen employed in dock fabrication are properly experienced and skilled in the work they are called upon to perform.

C. CORNER WHEELS

NEW HOGAN LAKE ITEMS 0002A-C: Each dock shall have (4) 12” wheels one each corner mounted on a galvanized frame and positioned below the floatation tubs. Wheels shall have a urethane tread, polyolefin hub, and Delrin bearings equal to Payson.

4. PERFORMANCE PERIOD: To be completed within 30 days of award date.

DRAWING #10043

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
0001
N/A
N/A
N/A
Government
0002
N/A
N/A
N/A
Government
0003
N/A
N/A
N/A
Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC
0001
30-SEP-2009
3
NEW HOGAN LAKE

MR. RICHARD MARMOLEJO

2713 HOGAN DAM ROAD

VALLEY SPRINGS CA 95252-0128

L2M0434

0002
30-SEP-2009

(SAME AS PREVIOUS LOCATION)

L2M0434

0003
N/A
N/A
N/A
N/A

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

252.211-7003
Item Identification and Valuation
AUG 2008

CLAUSES INCORPORATED BY FULL TEXT

52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009 (MAR 2009)

(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5).

(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.

(End of clause)

CLAUSES INCORPORATED BY FULL TEXT

52.204-11 AMERICAN RECOVERY AND REINVESTMENT ACT-REPORTING REQUIREMENTS (MAR 2009)

(a) Definitions. As used in this clause—

Contract, as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.

First-tier subcontract means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.

Jobs created means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as “full-time equivalent” (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.

Jobs retained means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as “full-time equivalent” (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.

Total compensation means the cash and noncash dollar value earned by the executive during the contractor’s past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):

(1) Salary and bonus.

(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) ( FAS 123R), Shared Based Payments.

(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.

(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.

(5) Above-market earnings on deferred compensation which is not tax-qualified.

(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.

(b) This contract requires the contractor to provide products and/or services that are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.

(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009. Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.

(d) The Contractor shall report the following information, using the online reporting tool available at www.FederalReporting.gov.

(1) The Government contract and order number, as applicable.

(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government's on-line reporting tool.

(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.

(4) Program or project title, if any.

(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.

(6) An assessment of the contractor’s progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.

(7) A narrative description of the employment impact of work funded by the Recovery Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor’s workforce. At a minimum, the contractor shall provide—

(i) A brief description of the types of jobs created and jobs retained in the United States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor’s existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and

(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.

(8) Names and total compensation of each of the five most highly compensated officers of the Contractor for the calendar year in which the contract is awarded if—

(i) In the Contractor’s preceding fiscal year, the Contractor received—

(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(ii) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

(9) For subcontracts valued at less than $25,000 or any subcontracts awarded to an individual, or subcontracts awarded to a subcontractor that in the previous tax year had gross income under $300,000, the Contractor shall only report the aggregate number of such first tier subcontracts awarded in the quarter and their aggregate total dollar amount.

(10) For any first-tier subcontract funded in whole or in part under the Recovery Act, that is over $25,000 and not subject to reporting under paragraph 9, the contractor shall require the subcontractor to provide the information described in (i), (ix), (x), and (xi) below to the contractor for the purposes of the quarterly report. The contractor shall advise the subcontractor that the information will be made available to the public as required by section 1512 of the Recovery Act. The contractor shall provide detailed information on these first-tier subcontracts as follows:

(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor’s parent company, if the subcontractor has a parent company.

(ii) Name of the subcontractor.

(iii) Amount of the subcontract award.

(iv) Date of the subcontract award.

(v) The applicable North American Industry Classification System (NAICS) code.

(vi) Funding agency.

(vii) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.

(viii) Subcontract number (the contract number assigned by the prime contractor).

(ix) Subcontractor’s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(x) Subcontract primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(xi) Names and total compensation of each of the subcontractor’s five most highly compensated officers, for the calendar year in which the subcontract is awarded if—

(A) In the subcontractor’s preceding fiscal year, the subcontractor received—

(l) 80 percent or more of its annual gross revenues in Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(2) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(B) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

(End of clause)

CLAUSES INCORPORATED BY FULL TEXT

52.212-4 CONTRACT TERMS AND CONDITIONS-- COMMERCIAL ITEMS (MAR 2009)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights (1) within a reasonable time after the defect was discovered or should have been discovered; and (2) before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement or any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include--

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, contract line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer--Central Contractor Registration, or 52.232-34, Payment by Electronic

Funds Transfer--Other Than Central Contractor Registration), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.--

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall--

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the--

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected contract line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if--

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on--

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; Section 1553 of the American Recovery and Reinvestment Act of 2009 relating to whistleblower protections for contracts funded under that Act; 49 U.S.C. 40118, Fly American; and 41 U.S.C. 423 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order: (1) the schedule of supplies/services; (2) the Assignments, Disputes, Payments, Invoice, Other Compliances, and Compliance with Laws Unique to Government Contracts paragraphs of this clause; (3) the clause at 52.212-5; (4) addenda to this solicitation or contract, including any license agreements for computer software; (5) solicitation provisions if this is a solicitation; (6) other paragraphs of this clause; (7) the Standard Form 1449; (8) other documents, exhibits, and attachments; and (9) the specification.

(t) Central Contractor Registration (CCR). (1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(2)(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the

Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor's CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.

(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423 or 269-961-5757.

/ / / / / / / / / / / / / / /(End of clause)/ / / / / / / / / / / / / / /

CLAUSES INCORPORATED BY FULL TEXT

52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS--COMMERCIAL ITEMS (JUN 2009) ALTERNATE II (MAY 2009)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

(1) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).

Alternate I (Aug 2007) of 52.222-50 (22 U.S.C. 7104(g)).

(2) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(3) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)

___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (SEP 2006), with Alternate I (OCT 1995) (41 U.S.C. 253g and 10 U.S.C. 2402).

___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (DEC 2008)(Pub. L. 110-252, Title VI, Chapter 1 (41 U.S.C. 251 note)).

___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (MAR 2009) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

__(4) 52.204-11, American Recovery and Reinvestment Act—Reporting Requirements (MAR 2009) (Pub. L. 111-5).

___ (5) 52.219-3, Notice of HUBZone Small Business Set-Aside (Jan 1999) (15 U.S.C. 657a).

___ (6) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (JUL 2005) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

___ (7) [Reserved].

XXX (8)(i) 52.219-6, Notice of Total Small Business Set-Aside (JUNE 2003) (15 U.S.C. 644).

___ (ii) Alternate I (OCT 1995) of 52.219-6.

___ (iii) Alternate II (MAR 2004) of 52.219-6.

___ (9)(i) 52.219-7, Notice of Partial Small Business Set-Aside (JUNE 2003) (15 U.S.C. 644).

___ (ii) Alternate I (OCT 1995) of 52.219-7.

___ (iii) Alternate II (MAR 2004) of 52.219-7.

___ (10) 52.219-8, Utilization of Small Business Concerns (MAY 2004) (15 U.S.C. 637 (d)(2) and (3)).

___ (11)(i) 52.219-9, Small Business Subcontracting Plan (APR 2008) (15 U.S.C. 637(d)(4)).

___ (ii) Alternate I (OCT 2001) of 52.219-9 ___ (iii) Alternate II (OCT 2001) of 52.219-9.

___ (12) 52.219-14, Limitations on Subcontracting (DEC 1996) (15 U.S.C. 637(a)(14)).

___ (13) 52.219-16, Liquidated Damages--Subcontracting Plan (JAN 1999) (15 U.S.C. 637(d)(4)(F)(i)).

___ (14)(i) 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns (OCT 2008) (10 U.S.C. 2323) (if the offeror elects to waive the adjustment, it shall so indicate in its offer).

___ (ii) Alternate I (JUNE 2003) of 52.219-23.

___ (15) 52.219-25, Small Disadvantaged Business Participation Program--Disadvantaged Status and Reporting (APR 2008) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).

___ (16) 52.219-26, Small Disadvantaged Business Participation Program--Incentive Subcontracting (OCT 2000) (Pub. L. 103-355, section 7102, and 10 U.S.C. 2323).

___ (17) 52.219-27, Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside (MAY 2004) (U.S.C. 657 f).

XXX (18) 52.219-28, Post Award Small Business Program Rerepresentation (APR 2009) (15 U.S.C. 632(a)(2)).

XXX (19) 52.222-3, Convict Labor (JUNE 2003) (E.O. 11755).

XXX (20) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (FEB 2008) (E.O. 13126).

XXX (21) 52.222-21, Prohibition of Segregated Facilities (FEB 1999).

XXX (22) 52.222-26, Equal Opportunity (MAR 2007) (E.O. 11246).

___ (23) 52.222-35, Equal Opportunity for Special Disabled Veterans, Veterans of theVietnam Era, and Other Eligible Veterans (SEP 2006) (38 U.S.C. 4212).

XXX (24) 52.222-36, Affirmative Action for Workers with Disabilities (JUN 1998) (29

U.S.C. 793).

___ (25) 52.222-37, Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEP 2006) (38 U.S.C. 4212).

___ (26) 52.222-39, Notification of Employee Rights Concerning Payment of Union Dues or Fees (DEC 2004) (E.O. 13201).

___ (27) 52.222-54, Employment Eligibility Verification (Jan 2009). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.) (Not Applicable until June 30, 2009.)

___ (28)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

___ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(c)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

___ (29) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) .

___ (30)(i) 52.223-16, IEEE 1680 Standard for the Environmental Assessment of Personal Computer Products (DEC 2007) (E.O. 13423).

___ (ii) Alternate I (DEC 2007) of 52.223-16.

XXX (31) 52.225-1, Buy American Act--Supplies (JUNE 2003) (41 U.S.C. 10a-10d).

___ (32)(i) 52.225-3, Buy American Act--Free Trade Agreements--Israeli Trade Act (JUN 2009) (41 U.S.C. 10a-10d, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, Pub. L. 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, and 110-138).

___ (ii) Alternate I (JAN 2004) of 52.225-3.

___ (iii) Alternate II (JAN 2004) of 52.225-3.

___ (33) 52.225-5, Trade Agreements (JUN 2009) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

XXX (34) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

___ (35) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).

___ (36) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov 2007) (42 U.S.C. 5150).

___ (37) 52.232-29, Terms for Financing of Purchases of Commercial Items (FEB 2002) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)) ___ (38) 52.232-30, Installment Payments for Commercial Items (OCT 1995) (41 U.S.C. 255(f), 10 U.S.C. 2307(f)).

XXX (39) 52.232-33, Payment by Electronic Funds Transfer--Central Contractor Registration (OCT 2003) (31 U.S.C. 3332).

___ (40) 52.232-34, Payment by Electronic Funds Transfer--Other than Central Contractor Registration (MAY 1999) (31 U.S.C. 3332) ___ (41) 52.232-36, Payment by Third Party (MAY 1999) (31 U.S.C. 3332).

___ (42) 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).

___ (43)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. Appx 1241(b) and 10 U.S.C. 2631).

____ (ii) Alternate I (APR 2003) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)

____ (1) 52.222-41, Service Contract Act of 1965 (Nov 2007) (41 U.S.C. 351, et seq.).

____ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 1989) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).

____ (3) 52.222-43, Fair Labor Standards Act and Service Contract Act--Price Adjustment (Multiple Year and Option Contracts) (NOV 2006) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.).

____ (4) 52.222-44, Fair Labor Standards Act and Service Contract Act--Price Adjustment (February 2002) (29 U.S.C. 206 and 41 U.S.C. 351, et seq.)

____ (5) 52.222-51, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (Nov 2007) (41 U.S.C. 351, et seq.).

____ (6) 52.222-53, Exemption from Application of the Service Contract Act to Contracts for Certain Services--Requirements (FEB 2009) (41 U.S.C. 351, et seq.).

____ (7) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (MAR 2009) (Pub. L. 110-247).

____ (8) 52.237-11, Accepting and Dispensing of $1 Coin (SEP 2008)(31 U.S.C. 5112(p)(1)).

(d) (1) The Comptroller General of the United States, an appropriate Inspector General appointed under section 3 or 8G of the Inspector General Act of 1978 (5 U.S.C. App.), or an authorized representative of either of the foregoing officials shall have access to and right to—

(i) Examine any of the Contractor’s or any subcontractors’ records that pertain to, and involve transactions relating to, this contract; and

(ii) Interview any officer or employee regarding such transactions.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form.