A.01.13_Specifications.pdf
PDF 722 KB Posted
- Solicitation number
- W91237-18-B-0006
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_for_W9123718B0006.DOCX | DOCX document | |
| Questions_and_Answers.pdf | ||
| A.01.13_Plans_REV_01.pdf | ||
| W9123718B0006-0001.pdf | ||
| W9123718B0006.pdf | ||
| A.01.13_Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications for
EMBEDDED ANCHORAGE REPAIRS
UPPER LAND WALL LEAF
WINFIELD LOCKS AND DAM
KANAWHA RIVER
RED HOUSE, WEST VIRGINIA
Certified Final Documents - RTA (Pending)
DEPARTMENT OF THE ARMY
HUNTINGTON DISTRICT, CORPS OF ENGINEERS
HUNTINGTON, WEST VIRGINIA
Contract No. June 2018
This page was intentionally left blank for duplex printing.
Embedded Anchorage Repairs Upper Land Wall Leaf WIN12
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00 SPECIAL CONTRACT REQUIREMENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 CONTRACT CONSIDERATIONS
01 22 00.00 20 APPLICATION FOR PAYMENT
01 28 00.00 10 CONTRACT MODIFICATIONS
01 31 19.00 40 PROJECT CONFERENCES
01 32 01.00 10 PROJECT SCHEDULE
01 32 16.00 20 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 38 10 PROGRESS PHOTOGRAPHS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 40 CONTRACTOR QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 60 00.00 40 MATERIAL AND EQUIPMENT
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 05 - METALS
05 50 14 STRUCTURAL METAL FABRICATIONS - GRATING AND GRATING
SUPPORT FRAMING
05 59 13 FABRICATION OF MITER GATE ANCHORAGE FRAME
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DIVISION 31 - EARTHWORK
31 68 14 PRE-GROUTED BAR ANCHORS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 16.33 01 MITER GATE ANCHORAGE REPLACEMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 80 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
1.3 SUBMITTALS
1.4 LIQUIDATED DAMAGES--CONSTRUCTION
1.5 DOCUMENT SECURITY
1.5.1 For Official Use Only (FOUO)
1.6 SECURITY REQUIREMENTS
1.6.1 Foreign Nationals
1.7 AT/OPSEC REQUIREMENTS
1.8 RECORDKEEPING AND REPORTING
1.9 CONTRACT DRAWINGS AND SPECIFICATIONS
1.10 SUBMISSION OF CONTRACT DOCUMENTATION
1.11 SIGNAL LIGHTS
1.12 SITE RESTRICTION
1.12.1 Navigation Small Boat Restriction. (Survey Boats, Crew Boats, Launches,....)
1.13 FLOATING PLANT AND TOWBOAT
1.14 FLOOD OUTAGE
1.15 WAGE RATES
1.16 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS
1.17 REQUIRED INSURANCE
1.17.1 Insurance Certification
1.18 PERFORMANCE EVALUATION OF CONTRACTOR
1.19 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
1.20.1 Government Furnished Utility Services
1.21 PROGRESS SCHEDULE
1.21.1 Schedule Preparation
1.22 PAYMENT
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
DOCUMENT 00 80 00 Page 1
SECTION 00 80 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
Comply with the Contract Clause 52.211-10.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Employees; G|SM Investigation Package for Contractor and Subcontractor Employees;
G|SM
1.4 LIQUIDATED DAMAGES--CONSTRUCTION
Comply with the Contract Clause 52.211-12. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
1.5 DOCUMENT SECURITY
Contractors working for and on USACE projects shall provide the appropriate physical security for all related items as detailed/prescribed in AR 380-5, dated 29 September 2000.
1.5.1 For Official Use Only (FOUO)
For Official Use Only (FOUO): The unauthorized disclosure of the information contained in the attached documents is forbidden to protect the Government's interest in compliance with program effectiveness under AR 380-5 and as follows:
a. During working hours, reasonable steps shall be taken to minimize risk of access by unauthorized personnel. After working hours, FOUO information can be stored in unlocked containers, desks or cabinets if U.S. Government or U.S. Government-contract building security is
DOCUMENT 00 80 00 Page 2 provided. If U.S. Government-contract building security is not provided, FOUO information must be stored in locked desks, file cabinets, bookcases, or similar locked containers.
b. FOUO documents and material can be transmitted via first class mail, parcel post, or, for bulk shipments, fourth class mail. Electronic transmission of FOUO information by voice, data, facsimile or similar means, shall be by approved secure communications systems whenever possible. (AR 380-5 (dated 29 September 2000))
c. Record copies of FOUO documents shall be disposed of in accordance with AR 25-400-2. Non-record FOUO documents shall be destroyed by shredding or tearing into pieces and discarding the pieces in regular trash containers.
1.6 SECURITY REQUIREMENTS
All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with "Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information in order to complete the basic background investigation in order to make a recommendation to the Contracting Office of an employee's suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results provided by the Huntington District Security Management Office of the background investigation. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.
Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities. The Contractor must also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number and (4) Task Order Number when applicable.
The documents listed below are required:
SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management office).
Contractor shall report any changes in personnel or at anytime conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.
DOCUMENT 00 80 00 Page 3
Following submission of paperwork, the Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, Security Management Office will make recommendations to the PCO or their Designated Representative. The Security Management Office cannot give approval due to unfavorable report(s). The Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise Contractor of the decision.
1.6.1 Foreign Nationals
The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to Headquarters Staff to accomplish. All Foreign Nationals must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, "Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives" dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers' contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.
In order to assure forms are properly completed, and to minimize time delays, Contractor is encouraged to work closely with the Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Security Management Office by phone, letter, or email at the following numbers/addresses:
US Army Corps of Engineers
ATTN: CELRH-SM
502 Eighth Street Huntington, WV 25701
Sandra L. Hardwick, phone (304) 399-5612;
e-mail sandra.l.hardwick@usace.army.mil or
DOCUMENT 00 80 00 Page 4
Stephen R. Curry, phone (304) 399-5695;
e-mail stephen.r.curry@usace.army.mil or
Matthew D. Green, phone (304) 399-5294;
e-mail matthew.d.green@usace.army.mil
1.7 AT/OPSEC REQUIREMENTS
Contractors are required to comply with the following:
1. AT Level I Training. This provision/contract text is for Contractor employees with an area of performance within an Army controlled installation, facility or area. All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within thirty (30) calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the Contracting Officer's Representative or to the Contracting Officer (if a Contracting Officer's Representative is not assigned), within five (5) calendar days after completion of training by all employees and subcontractor personnel.
AT Level I awareness training is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.
2. Access and General Protection/Security Policy and Procedures. All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
a. For Contractors who do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3. Suspicious Activity Reporting Training (e.g., iWATCH, CorpsWatch, or See Something, Say Something). The Contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the
DOCUMENT 00 80 00 Page 5 local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within thirty (30) calendar days of contract award and within thirty (30) calendar days of new employees commencing performance with the results reported to the Contracting Officer's Representative no later than five (5) calendar days after the completion of the training.
4. Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Contracting Officer's Representative no later than three (3) business days after the initial contract award.
5. Threat Awareness Reporting Program. All new Contractor employees will complete annual Threat Awareness and Reporting Program (TARP) Training provided by a Counterintelligence Agent, IAW AR 381-12. The Contractor shall submit certificates of completion for each affected Contractor and subcontractor employee(s) or a memorandum for the record, to the Contracting Officer's Representative or to the Contracting Officer (if a Contracting Officer's Representative is not assigned), within five (5) calendar days after completion of training. Authorized webbased TARP training for CAC card holders is available at the following website:
https://www.us.army.mil/suite/page/655474.
6. For Contracts that Require OPSEC Training. All new Contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training. The Contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the Contracting Officer's Representative or to the Contracting Officer (if a Contracting Officer's Representative is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
1.8 RECORDKEEPING AND REPORTING
The Contractor shall maintain a roster of all background investigation requests. The roster shall be maintained and available for inspection by the Contracting Officer upon request. A copy will also be provided to the Contracting Officer on a monthly basis. At a minimum, the roster shall include the following information:
Full Name of Employee Employer Date Phase I Background Check Requested Date of Phase I Approval/Disapproval Date Phase II Background Investigation Requested Date of Phase II Approval/Disapproval Date Foreign National/Recent U.S. Citizen Check Requested Date Foreign National/Recent U.S. Citizen Check Approval/Disapproval
DOCUMENT 00 80 00 Page 6
Other information may also be included on the roster. However, the Contractor is responsible for protecting all sensitive personal information such as social security numbers, birth dates, etc.
1.9 CONTRACT DRAWINGS AND SPECIFICATIONS
Comply with Contract Clause 252.236-7001. Contractor shall field verify all dimensions on drawings prior to commencing design and layout of the work.
1.10 SUBMISSION OF CONTRACT DOCUMENTATION
Provide contract documentation in an electronic format to the greatest extent practicable. Contract documentation to be submitted electronically includes, but is not limited to, the following:
Submittals, including ENG 4025 transmittal form
Meeting Minutes
Construction Photographs
Correspondence
Requests for Information
Payroll Documents
Statement and Acknowledgement Forms (SF 1413)
Request for Additional Classification (SF 1444)
Progress Payment Requests and Supporting Documentation
Contract Modification Documentation, including SF 30, Contractor's Offer, Cost/Pricing Audit Report, and Certificate of Current Cost or Pricing Data
Contractor Quality Control Reports (with attachments)
Accident Reports
Schedules and Schedule Updates
Closeout Documentation, including Release of Claims
Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer's Representative (COR).
Whenever possible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic documents fewer than 10MB to an email address as directed
DOCUMENT 00 80 00 Page 7 by the COR. Electronic documents over 10MB shall be provided on a CD/DVD, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/
The Government reserves the right to request hard copy submission of any item, if deemed necessary. The Contractor shall be prepared to provide up to eight (8) additional paper hard copies of any contract document at the discretion of the COR, at no additional cost to the Government. In addition to the electronic file format described above, the following list of documents shall be provided in their original format because law or other regulations require signed originals be kept in accordance with FAR
4.805 -- STORAGE, HANDLING, AND DISPOSAL OF CONTRACT FILES (this list is taken from Appendix 5 to Annex C to OPORD 2012-66):
Advance Payment Bond
Bid Bond including Annual Bid Bond
Performance Bond including Annual Performance Bond
Payment Bond
Patent Infringement Bond
Any performance security instruments
Certificate of Insurance
Novation/Change of Name Agreement
Assignment of Claims
Any document containing a raised seal. Examples include:
o Notarized documents o Architecture Drawings
Paper Payroll Documents
Physical signatures on contracts and modifications o SF 1442 o SF 30
1.11 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard, governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as approved by the Commandant, U. S. Coast Guard (33 C.F.R. 80.18-80.31a and C.F.R. 95.51-95.70).
DOCUMENT 00 80 00 Page 8
1.12 SITE RESTRICTION
1.12.1 Navigation Small Boat Restriction. (Survey Boats, Crew Boats, Launches,....)
a. Restricted Areas
No downstream access will be permitted when the Winfield Dam configuration to pass inflow requires a total gate opening on the dam in excess of twenty (20) feet. No upstream access will be permitted when the Winfield Dam configuration to pass inflow requires a total gate opening on the dam in excess of five (5) feet.
b. Required Equipment
All work boats and operators shall be maintained and operated in compliance with EM 385-1-1, Section 19.
(1) Each boat shall have an anchor sized for the boat, suitable for fast water service with the manufacturer's recommended length and size anchor line. Water depths in the area approach forty
(40) feet. The anchor and line shall be deployed and on deck ready for immediate use.
(2) Each craft shall be equipped with an operating marine radio capable of transmitting and receiving on Marine channels 16, 13, and 14.
(3) All other safety equipment for the class vessel as required by the United States Coast Guard shall be provided on each boat.
c. Personnel Interfacing
(1) Where multiple entries are made into the restricted area on a given day each entrance must be approved by the Lockmaster via marine radio.
(2) Should any trouble develop, while in the restricted area, the vessel operator must immediately notify the Lockmaster of the problem so they can take what, if any, actions they deem appropriate.
(3) Should the Lockmaster require the Work Crew to leave the area they will notify them by marine radio. The Work Crew and the boat will leave from the restricted area immediately.
The above requirements are the minimum acceptable for the proposed activities in the restricted area at the locks and dam.
1.13 FLOATING PLANT AND TOWBOAT
a. The Contractor shall notify the Contracting Officer, in writing, at least thirty (30) days in advance of the date he proposes to use a floating plant above or below the immediate vicinity of the Locks and Dam (within the confines of the designated lockage arrival points). The Contracting Officer will advise the Lockmaster so that action is coordinated with traffic in a timely manner. No priority lockage will be authorized for the Contractor.
DOCUMENT 00 80 00 Page 9
b. Stationing of floating plant above the immediate vicinity of the Locks and Dam will be prohibited whenever river flows are sufficient to require a total Dam gate opening exceeding 15 feet for above the Dam and 25 feet for below the Dam of total Dam gate opening. Projected increased river flow which may require total Dam opening to exceed 15 or 25 feet, of total Dam gate opening and/or possible accidents, will require the Contractor to immediately remove the floating plant. Therefore, the Contractor shall furnish the Contracting Officer a list of all the Contractor's key personnel, along with telephone numbers where they may be contacted day or night, so that on a short notice the floating plant may be removed from the vicinity of the Dam.
c. If the Contracting Officer or Lockmaster at Winfield Locks and Dam is unable to contact the Contractor or his key employees, or if after contact the floating plant is not removed within four hours following notice, the Government will take the necessary action required to have the floating plant removed from the immediate vicinity of the Dam. All costs and any damages resulting from the removal shall be at the expense of the Contractor.
d. The floating plant cannot be left unattended while stationed in the immediate vicinity of the Locks and Dam, unless written permission is obtained from the Contracting Officer for each and every occurrence.
e. Mooring facilities are available for use within the Main Lock Chamber once the main lock chamber has been closed to navigation traffic.
All equipment not authorized to be in the immediate Dam vicinity shall be moored at commercial mooring facilities at the expense of the Contractor.
Plant shall not be moored in lock chambers or on lock walls where it will affect navigation. This area shall be vacated before the upper pool elevation reaches 568.00 or at the direction of the Lockmaster.
f. The Contractor shall also provide a towboat with adequate horsepower and twin screws to handle the floating plant being utilized, or shall obtain a contract with a reputable towing or marine service company to provide towboat services on an as-needed basis. The towboat shall be available within four hours of notice of need to abandon the work position, as directed by the Contracting Officer, on a 24-hour-a-day, seven-day-a-week basis, anytime the Contractor's floating plant is on station at the Locks and Dam. Note: The towboat does not have to be on station but shall be available on notice to reach the project site as specified above. For the purpose of construction, the Contractor must have a copy of 33 CFR 207.300, "Regulations Prescribed by the Secretary of the Army for Ohio River, Mississippi River above Cairo, Ill., and their Tributaries, Use, Administration and Navigation" which can be obtained electronically at https://ecfr.io/Title-33/pt33.3.207#se33.3.207_1300.
g. During use of a floating plant, the Government will, to maximum extent practicable, operate the Dam in such manner that roller gate No. 1 will be closed while the Contractor is working in the immediate area.
1.14 FLOOD OUTAGE
During the course of the contract, high river flow conditions will develop in varying degrees. The Contracting Officer or the Lockmaster will inform the Contractor as to when he will be required to remove his floating plant from the work area to meet the requirements above. At above 15 feet of total Dam opening, the Lockmaster will make an evaluation of pending river conditions and will inform the Contracting Officer as to whether the
DOCUMENT 00 80 00 Page 10
Contractor shall be required to remove his floating plant.
b. The stage duration curves shown on the Contract Drawings represent the results of a statistical analysis of historical stage data for the upper and lower gages, on a monthly basis. For any given stage, these curves can be used to determine the percentage of time for which that particular stage could be expected to be equaled or exceeded on a monthly basis or for any given month. The historical stage duration curves shown on the drawings, are from the period of record 1 January 1990 to 11 February 2015 and 1 October 1984 to 11 February 2015, respectively. For the upper pool the gage datum is 548.0 feet. For the lower pool the gage datum is 529.0 feet.
1.15 WAGE RATES
Wage rates shall be in accordance with Contract Clause 52.222-6
CONSTRUCTION WAGE RATE REQUIREMENTS.
1.16 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING
DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS
(a) The Contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR clause 52.222-8, PAYROLLS AND BASIC RECORDS and FAR clause 52.222-13, COMPLIANCE WITH CONSTRUCTION
WAGE RATE REQUIREMENTS AND RELATED REGULATIONS.
(b) If the Contractor elects to use an electronic Davis-Bacon Act payroll processing system, then the Contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with Davis-Bacon and Related Act Regulations. When the Contractor uses an electronic Davis-Bacon Act payroll system, the electronic payroll service shall be used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required three (3) years after contract completion. If the Contractor chooses to use an electronic Davis-Bacon Act payroll system, then the Contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and Related Act Regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract admin office to the electronic payroll processing system used by the Contractor.
(c) The Contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://rms.usace.army.mil/Home/SiteMap) for export in an Excel spreadsheet to be imported into the Resident Management System (RMS)
DOCUMENT 00 80 00 Page 11
Contractor Mode, that in turn shall export payroll data to the Government's Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce Contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis-Bacon Act payrolls submitted to the Government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic D-B payroll processing system shall be provided to the Government during contract closeout.
(d) All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service shall be included in the Contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.
1.17 REQUIRED INSURANCE
In reference to Contract Clause INSURANCE--WORK ON A GOVERNMENT INSTALLATION, FAR 52.228-5, the Contractor shall procure and maintain, during the entire period of his performance under this contract, the following minimum insurance:
a. Workmen's Compensation. Workmen's Compensation and Occupational Disease Coverage, as legally required by the State wherein the work is being performed.
b. Comprehensive Automobile Liability Insurance. Bodily injury coverage with minimum limits of $200,000 per person and $500,000 per occurrence, and $100,000 per occurrence for property damage shall be required.
c. Comprehensive General Liability Insurance. Bodily injury coverage with minimum limit of $500,000 per occurrence shall be required.
Property damage coverage with a minimum limit of $100,000 per occurrence shall be required.
1.17.1 Insurance Certification
Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies evidencing the required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe or (2) until thirty (30) days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
1.18 PERFORMANCE EVALUATION OF CONTRACTOR
It is the Corps' standard operating procedure that the Contracting Officer evaluate the Contractor's performance and prepare a performance report using the web-based application CPARS (Contractor Performance Assessment Reporting System) for construction contracts of $650,000 or more. After an evaluation (interim or final) is written by the Corps, the Contractor has a
DOCUMENT 00 80 00 Page 12
60-day period to access, review and comment on the evaluation. Accessing and using CPARS requires having specific software, called PKI certification, installed on the user's computer. The certification, a Department of Defense requirement, was implemented to provide security in electronic transactions. The certification software could cost approximately $100-$125 per certificate, per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov. The Contractor is encouraged to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
1.19 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
(a) This special contract requirement does not apply to terminations.
See UAI 5152.249-9000, BASIS FOR SETTLEMENT OF PROPOSALS, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition, owned or controlled, and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE, REGION II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, RENTAL COSTS. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the Simplified Acquisition Threshold (SAT), the Contracting Officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
1.20.1 Government Furnished Utility Services
The Government will not provide any utilities under this contract.
DOCUMENT 00 80 00 Page 13
1.21 PROGRESS SCHEDULE
1.21.1 Schedule Preparation
Prepare schedules in accordance with Section 01 32 01.00 10 PROJECT
SCHEDULE.
1.22 PAYMENT
No separate payment will be made for the work covered under this section and all costs in connection therewith shall be included in the applicable contract price to which the work pertains.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
DOCUMENT 00 80 00 Page 14
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
CONTRACT CONSIDERATIONS
PART 1 GENERAL
1.1 SCOPE
1.2 SUBMITTALS
1.3 DESCRIPTION OF WORK
1.3.1 General Project Features
1.3.2 Limited Working Area and Times
1.3.3 Work Covered by Contract Documents
1.3.4 Work by Other Prime Contractors
1.4 CONTRACT CONSIDERATIONS
1.4.1 Contractor Use of Site
1.4.1.1 General
1.4.1.2 Site Layout Organization Plan
1.4.2 Identification of Government Furnished Property
1.4.3 Payments
1.4.3.1 Applications for Payment
1.4.3.2 Measurement and Payment
1.4.4 Contract Modifications (Change Orders)
1.4.5 Safety
1.4.6 Materials, Equipment and Workmanship
1.4.7 Permits, Licenses, Fees and Taxes
1.4.8 Shop Drawings, Product Data, and Samples
1.4.9 Network Analysis Schedules
1.4.10 Project Conferences
1.4.11 Reference Standards
1.4.12 Construction Photographs
1.4.13 Quality Control
1.4.14 Submittals
1.5 PAYMENT
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 00 00 Page 1
SECTION 01 00 00
CONTRACT CONSIDERATIONS
PART 1 GENERAL
1.1 SCOPE
a. Description of the Work.
b. Contract Considerations.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Site Layout Organization Plan; G|CM
1.3 DESCRIPTION OF WORK
1.3.1 General Project Features
a. The general description of the work of this contract consists of furnishing all materials, equipment, labor, layouts of work features, and supervision needed to accomplish work on the Upper Land Wall miter gate leaf embedded anchorage rehabilitation. The work will consist of fabricating a new anchorage frame, designing and procuring post-tensioned anchors, excavating concrete, installing and testing post-tensioned bar anchors, installing anchorage frame and installing grating and grating support framing.
b. The Winfield Locks and Dam project is an active navigation lock operated 24/7 located at river mile 31.1 on the Kanawha River. Original construction of the project was completed in 1935. The original project consists of a non-navigable gated dam with twin locks 56-foot wide by 360-foot long. A new lock chamber 110-foot wide by 800-foot long and a 110-foot wide non-navigable tainter gate where added to the project landward of the original locks. Construction of the new lock chamber and tainter gate was completed in 1997 and the features put into service at that time. The original lock chambers are still active today and function as the auxiliary locks.
c. The upper and lower pool elevations are subject to change due to river conditions. Contract drawings S-801 through S-806 provide the historical data of the Upper and Lower Pool Stages. The historical data consists of average monthly stage duration curves for the periods from 1 January 1990 to 11 February 2015 for the Upper Pool Stage and from 1 October 1984 to 11 February 2015 for the Lower Pool Stage.
SECTION 01 00 00 Page 2
1.3.2 Limited Working Area and Times
During the time of performance of this contract, the main lock chamber will remain open to navigation traffic until the point is reach were the existing embedded anchorage needs to be removed. This point will occur after the new post-tensioned anchor bars have been installed, performance and proof tested and accepted by the Government and the new anchorage frame has been fabricated and delivered to the Winfield Locks and Dam project.
Once this point has been reached the lock will be closed to navigation traffic and remain closed until the work has been completed and the miter gate leaf is operational to the acceptance of the Government. If the contractor places any equipment or materials in the main chamber during the closures, the contractor will need to remove their equipment and materials from the main lock chamber and its approaches if river conditions dictate as specified in Section 00 80 00 SPECIAL CONTRACT REQUIREMENTS.
1.3.3 Work Covered by Contract Documents
Perform all the work shown on the drawings and identified in Divisions 01 through 35 of the technical specifications and Section 00 80 00 SPECIAL
CONTRACT REQUIREMENTS.
1.3.4 Work by Other Prime Contractors
Comply with the Contract Clause 52.236-8 OTHER CONTRACTS.
1.4 CONTRACT CONSIDERATIONS
1.4.1 Contractor Use of Site
1.4.1.1 General
Comply with the Contract Clauses 52.236-7 PERMITS AND RESPONSIBILITIES, 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, 52.236-10 OPERATIONS AND STORAGE AREAS and
52.236-12 CLEANING UP.
1.4.1.2 Site Layout Organization Plan
Within fifteen (15) calendar days after the date of Notice of Award, submit a Site Layout Organization Plan showing the Contractor's proposed layout of facilities on the site. The Contracting Officer will review the plan and issue its comments within fifteen (15) calendar days of receipt of the same. Acceptance of the final plan by the Contracting Officer is a prerequisite to the Contractor's use of the site. Upon completion of the work, vacate from the site all plant and temporary facilities and complete post-construction as specified in Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION. Submit plant layout drawings in accordance with Section
01 50 00 TEMPORARY CONSTRUCTION FACILITIES.
1.4.2 Identification of Government Furnished Property
Comply with the requirements of Section 01 60 00.00 40 MATERIAL AND
EQUIPMENT.
SECTION 01 00 00 Page 3
1.4.3 Payments
1.4.3.1 Applications for Payment
Payments will be made in accordance with the Contract Clauses and with the applicable provisions of Section 01 22 00.00 20 APPLICATION FOR PAYMENT.
1.4.3.2 Measurement and Payment
Measurement and payment shall be determined in accordance with Contract Clauses 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS, 252.236-7008 CONTRACT PRICES--BIDDING SCHEDULES, and 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS and with the payment paragraphs of each of the technical specifications sections.
1.4.4 Contract Modifications (Change Orders)
Modifications shall be determined in accordance with the provisions of Section 01 28 00.00 10 CONTRACT MODIFICATIONS, Contract Clauses 52.243-4 CHANGES and 252.236-7000 MODIFICATION PROPOSALS--PRICE BREAKDOWN of Section
00 70 00 CONTRACT CLAUSES.
1.4.5 Safety
Safety shall be the responsibility of the Contractor. Comply with the provisions of the Contract Clauses 52.236-13 ACCIDENT PREVENTION and with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS of the specifications.
1.4.6 Materials, Equipment and Workmanship
Comply with the Contract Clause 52.236-5 MATERIAL AND WORKMANSHIP and with Section 01 60 00.00 40 MATERIAL AND EQUIPMENT of the specifications.
1.4.7 Permits, Licenses, Fees and Taxes
The Contractor shall ascertain the extent of, and pay for all necessary permits, licenses, fees, and taxes in accordance with the provisions of the Contract Clauses 52.236-7 PERMITS AND RESPONSIBILITIES and 52.229-3 FEDERAL, STATE, AND LOCAL TAXES of Section 00 70 00 CONTRACT CLAUSES.
1.4.8 Shop Drawings, Product Data, and Samples
Comply with the Contract Clause 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION and with Section 01 32 16.00 20 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES of the specifications.
1.4.9 Network Analysis Schedules
Comply with Section 01 32 01.00 10 PROJECT SCHEDULE.
1.4.10 Project Conferences
Comply with the provisions of Section 01 31 19.00 40 PROJECT CONFERENCES of the specifications.
1.4.11 Reference Standards
Comply with the individual technical specifications sections and with Section 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS.
SECTION 01 00 00 Page 4
1.4.12 Construction Photographs
Comply with Section 01 38 10 PROGRESS PHOTOGRAPHS of the specifications.
1.4.13 Quality Control
Comply with Contract Clauses 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR and 52.236-5 MATERIAL AND WORKMANSHIP and with Section 01 45 00.00 40
CONTRACTOR QUALITY CONTROL.
1.4.14 Submittals
Comply with the requirements of Section 01 33 00 SUBMITTAL PROCEDURES.
1.5 PAYMENT
No separate payment will be made for the work covered under this section and all costs in connection therewith shall be included in the applicable contract price to which the work pertains.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 00 00 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 20
APPLICATION FOR PAYMENT
PART 1 GENERAL
1.1 SCOPE
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 FORMAT
3.2 PREPARATION OF APPLICATIONS
3.3 SUBMITTAL PROCEDURES
3.4 SUBSTANTIATING DATA
3.5 ESTIMATED EARNINGS
3.6 PAYMENT
SECTION 01 22 00.00 20 Page 1
SECTION 01 22 00.00 20
APPLICATION FOR PAYMENT
PART 1 GENERAL
1.1 SCOPE
Procedures for preparation and submittal of Application for Payment.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 FORMAT
Use format approved by the Contracting Officer. For each item, provide a column for listing: Item Number; Description of work; Scheduled Value, Previous Applications; Work in Place under this Application; Authorized Changes; Total Completed to Date of Application; Percentage of Completion;
Balance to Finish; and Retainage. Other entries required by the Contract Clause 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS shall be included.
3.2 PREPARATION OF APPLICATIONS
a. Present required information on electronic media printout.
b. Execute certification by signature of authorized officer.
c. Use data from Bid Schedule. Provide dollar value in each column for each line item for portion of work performed.
d. List each authorized Change Order as an extension on continuation sheet, listing Changes number and dollar amount as for an original item of work.
3.3 SUBMITTAL PROCEDURES
a. Submit one (1) digital copy and one (1) hard copy of each Application for Payment.
b. Submit an updated construction schedule with each Application for Payment.
c. Payment Period: Submit at monthly intervals, as stipulated in the Contract Clause 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS.
d. Submit under transmittal form specified in Section 01 33 00
SUBMITTAL PROCEDURES.
3.4 SUBSTANTIATING DATA
a. Submit substantiating information, and data justifying dollar amounts in question.
b. Provide one (1) copy of data with cover letter for each copy of submittal. Show Application number and date, and line item by number
SECTION 01 22 00.00 20 Page 2 and description.
c. Comply with Contract Clauses 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACT and 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION
CONTRACTS.
d. Below is a list of substantiating data that is required to be submitted for each payment application:
Up-to-Date Payroll Records Signed Contractor Certification including all subcontractor information required by FAR 52.232-5(b)(1)(ii thru iv) Current Submittal Register Approved Submittals on Installed Property Up-to-Date Progress Chart Weekly Documentation of Safety Meetings and Attendance Up-to-Date Quality Control Reports Current Deficiency Report Satisfactory On-Site Safety Conditions Stored Materials Invoice Acceptable Work-in-Place Required Tests Performed and Reports Received Progress Percentage Recommended Payment Updated Contract Status in RMS
3.5 ESTIMATED EARNINGS
a. The Contractor shall submit estimated earnings through the 30th of each month no later than the 25th of each month. Supporting data shall be submitted as requested by the Contracting Officer.
b. The Contractor shall also prepare an estimated earnings report that outlines estimated earnings by month for the entire contract duration.
The Contractor shall also prepare an estimated earnings report that outlines estimated earnings by month by bid schedule line item for the entire contract duration. The first report shall be submitted no later than thirty (30) calendar days after Notice to Proceed. Supporting data shall be submitted as requested by the Contracting Officer.
3.6 PAYMENT
No separate payment will be made for work under this section and all costs in connection therewith shall be included in the applicable contract price for the item to which the work pertains.
SECTION 01 22 00.00 20 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 28 00.00 10
CONTRACT MODIFICATIONS
PART 1 GENERAL
1.1 SCOPE
1.2 SUBMITTALS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 DOCUMENTATION OF CHANGE IN CONTRACT SUM/PRICE AND CONTRACT TIME
3.2 CHANGE PROCEDURES
3.3 CORRELATION OF CONTRACTOR SUBMITTALS
3.4 PAYMENT
SECTION 01 28…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.