NASA USACE INDUSTRY DAY PRESENTATION 3.18.26 (1).pdf
PDF 3 MB Posted
- Solicitation number
- W9123626SA1002
About this file
This document is an Industry Day presentation for the Wallops Island Shoreline Stabilization Project conducted by the Norfolk District Army Corps of Engineers on March 18, 2026. The project involves two separate anticipated construction contracts: a beach renourishment/dredging contract valued at $25M–$100M and a breakwater construction contract valued at $10M–$25M, with both scheduled for advertisement in the fourth quarter of FY26. The beach renourishment will cover approximately 15,000 linear feet using approximately 1.5 million cubic yards of material from Shoal "A1," located 11 miles offshore at depths of 34–62 feet below NAVD88. The project requires open-water hopper dredge operations with pump-off capability and no seasonal restrictions, with approximately 2.25 million cubic yards of sandy material available in the borrow area and low probability of encountering munitions and explosives of concern. The breakwater design includes structures measuring 14 feet wide by 130 feet long, Type II armor stone, Class III core stone, approximately 10,000 tons each, with crest elevation of 6 feet in depths ranging from –6 feet to –13 feet.
The project is subject to significant operational constraints due to NASA Wallops Flight Facility's active launch operations, with 34 launches projected for 2026 (5 orbital, 29 sub-orbital) requiring pre-launch and day-of-launch restrictions, including personnel and equipment relocation from designated hazard areas. Environmental requirements include time-of-year restrictions for protected bird and sea turtle species (March 15–August 31 for avian species; May 1–August 31 for loggerhead sea turtles), turtle excluder devices on dredging dragheads, 24-hour bridge watch for endangered species, and American beach grass sprigging on created dunes. Sources Sought notices were issued March 5, 2026 (breakwater, closes March 20) and March 12, 2026 (beach renourishment, closes March 25), with contract awards anticipated January–March 2027 and construction completion targeted January–June 2028. The government seeks industry feedback on innovative construction methods, dredge availability and scheduling, risk mitigation strategies for simultaneous versus consecutive contracts, and optimal coordination methods. Small Business contact: Ms. Stormie Wicks, Deputy for Small Business Programs, (757) 675-4428.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY
WALLOPS ISLAND SHORELINE
STABILIZATION PROJECT
Norfolk District Army Corps of Engineers Wednesday, 18 March 2026
0900 – 1100
AGENDA
Topic Moderated By
Welcome Remarks and Introduction Scope and Schedule Overview
Shadera Williams Project Manager USACE
Design Overview Nick Ingold, PE Civil Engineer USACE
Dredging Tom Luehman, PE Civil Engineer USACE
Site Location and Restrictions John Saecker, PE Project Manager Civil Engineer Wallops Flight Facility
Break
Environmental Megan Wood, PhD Environmental Scientist USACE
Contracting Tiffany Kirtsey, KO Civil Branch Chief
Question and Answer Shadera Williams
WELCOME AND OPENING REMARKS
PROJECT OVERVIEW
SCOPE AND SCHEDULE
SHADERA WILLIAMS
PROJECT MANAGER USACE
The following presentation is preliminary information only.
All information provided is subject to change
Government is not currently soliciting proposals
Both verbal and written answers are not binding: the circumstances of the proposed acquisition may change over time
No part of Industry Day will be evaluated
Your involvement in Industry Day is strictly voluntary. No costs shall be charged to the Government
Feedback is encouraged and greatly welcomed
Slides will be posted to Sam.gov no later than 7 days after Industry Day
DISCLAIMER
Today’s Goal: to obtain insight and feedback from industry for a two future shoreline protection project at NASA Wallops Island Flight Facility.
Information gathering for anticipated construction using innovative, modern methods for construction in a highly complex workspace.
Information gathering on open-water hopper dredge with 11 miles from borrow area to nourishment location.
Expectations of dredging availability and scheduling.
Primary means and methods, challenges for construction, recommendations for risk/challenge mitigation.
The government also wishes to understand the risk, impact, and possible methods of risk mitigation in the case of two separate contracts for dredging/beach nourishment and breakwater construction.
Costs and benefit of simultaneous versus consecutive contracts, overlapping contracts, and possible coordination methods.
GOALS
NASA WALLOPS ISLAND
October 2023Post Replenishment 2021Pre Replenishment 2021
Low tide water-level at Launch pads 0-C, 0-A, and 0-B on 30 July 2024.
SCHEDULE
COMBINATION OF DREDGING/RENOURISHMENT AND CONSTRUCTION
KEY ACTION SCHEDULED
Topo/Bathy Survey Draft & Report DEC 2024
Value Engineering AUG 2025
Geotechnical Exploration NOV 2025
Shoreline Modeling DEC 2025
Design Completion JUL 2026
Solicitation AUG 2026
Award (Breakwaters/Renourishment) JAN 2027 / MAR 2027
Construction Start Duration 12 to 18 months
Construction Completion JAN 2028 – JUN 2028
* DRAFT SCHEDULE
* ALL DATES ARE ESTIMATED
DESIGN
NICK INGOLD, PE
CIVIL ENGINEER USACE
CURRENT DESIGN
• Beach renourishment
• Length: ~15,000 feet
• Material: Borrow area (Shoal "A1“)
• Design Template: ~1.5 MCY
• Borrow Area (Shoal “A1”)
• ~ 11 miles offshore
• Size: ~474 acres
• Depth: 34 feet to 62 feet
• Breakwaters
• Size: 14 ft wide, 130 ft long
• Type II (armor)
• Class III (core)
• ~10,000 tons/each
~11 MILES
BEACH RENOURISHMENT & TEMPLATE
BEACH RENOURISHMENT AREA
~15,000 FT
BREAKWATER DESIGN & LAYOUT
DEPTH RANGE
-6 FT TO -13 FT
CREST ELEVATION = 6 FT
OUTSTANDING DESIGN TASKS
• Final assistance with permitting
• Finalize design and construction documents (plans, specifications)
• QC Reviews
• Support with contracting & solicitation
DREDGING
TOM LUEHMAN, PE
CIVIL ENGINEER WATER RESOURCES DIVISION USACE
DREDGING
• Hopper dredge with pump-off only, no seasonal restrictions
• Dredge Site
• Borrow area dimensions of 0.15 Miles by 2.05 miles
• Existing depths in borrow site range from -34 ft NAVD88 to -62 ft NAVD88
• Dredge to a maximum depth of 7 ft below existing bottom
• Pre/post surveys of borrow area will be required
• Anticipate sandy material
• Approximately 2.25 M CY of material available in borrow area
• Low probability for encountering MEC
PROJECT SITE
LOCATION AND RESTRICTIONS
JOHN SAECKER, PE
PROJECT MANAGER
CIVIL ENGINEER WALLOPS FLIGHT FACILITY
NASA Wallops Flight Facility- Shoreline Location
Assateague Island
Wallops Island Work Location
Wallops Main Base
Badging Office
Island Gate
NASA Wallops Flight Facility
- Secure facility, badged access only
- Vehicular Access via the Wallops Island Causeway
- Active Launch Range- Launch Cadence Increase
- 34 launches projected 2026 (2027 TBD)
- 5 orbital, 29 sub-orbital
- Pre-Launch restrictions
- Day of Launch restrictions
- NASA will provide required laydown and office area space, along with a fueling location, using prior approved locations on the island.
- New access points to the beach at the seawall will be considered.
- 2012 Dredge Project- Great Lakes 3.3M CY
- 2014 Dredge Project- Weeks Marine 650K CY
- 2020 Breakwater/Backpassing Project- CHC 1.1M CY of sand backpassed and 5 breakwaters installed.
Single Access Road to Island Badged Access
Renourishment Area and Potential Breakwater Set(s)
Launch Pads
Launch Pad
Sample Pre-Launch Hazard Area (PLDA) and Launch Hazard Area (LHA)- Pad 2
PLDA- Varies per rocket/payload. Area shown in sample is at Pad 2, a highly used launch area for sub-orbital launches.
PLDA’s can include a rocket simply sitting on the rail. For breakwater construction access in this area, NASA will provide the most likely PLDA area that will be encountered and advise that construction and use of any constructed breakwater access be located just outside of the area.
LHA- In effect hours prior to launch. No personnel allowed in the LHA.
Some LHA’s close the entire island.
NASA will communicate PLDA’s and LHA’s on a weekly basis at construction meetings and a daily basis as an operation gets close.
Past Dredging Sample Communication Plan- Rockon Launch
Un-named Shoal A Dredge Locations
Dodge/Padre Island Crew
Liberty Island Crew
Marine Constraints Impact Dredge and Placement Ops Majority of Launches will Impact
BEACH PLACEMENT CREW- Relocation During Launch
T-2 hours and 30 min (3:30 AM) NASA will ask for the (Beach personnel only) to clear the area.
NASA has given the beach personnel 15 min to clear this area and get to their designated site outside the LHA and confirm they are all there and accounted for. Beach personnel will remain at that designated site, outside the hazard area until after the rocket is launched and the NASA Range Operations Assistant (ROA) has provided an ALL clear to resume activities.
Based on recent 2020/2021 shoreline project, high likelihood on-beach mobile equipment must also be moved outside LHA on the beach, working specifics with Range Safety.
DREDGE OPERATION- Relocation During Launch
T-2 hours (4:00 am) NASA will ask the Beach rep. BOAT assets to clear the area.
Boats will have one hour to clear the hazard area and to confirm their new location outside this hazard area. The boats will remain outside the hazard area until after the rocket is launched and the NASA ROA has provided an ALL clear to resume activities. The ROA can be reached at (757) 824.2224.
10 MINUTE BREAK
ENVIRONMENTAL CONSIDERATIONS
MEGAN WOOD, PHD
ENVIRONMENTAL SCIENTIST USACE
ENVIRONMENTAL CONSIDERATIONS FROM PREVIOUS CONTRACTS
• Wallops Beach
• Typically time-of-year restrictions for protected birds and sea turtles
• March 15 – August 31 (or last chicks have fledged) for red knots, piping plovers, and oystercatchers
• May 1 – August 31 (or last nest has hatched) for loggerhead sea turtles
• NASA staff conducts beach surveys during TOYR
• Sprigging of American beach grass on created dune
• Dredge/borrow site
• Turtle excluder devices (TEDs) on both dragheads, inspection prior to start of dredging
• 24-hour/100% coverage bridge watch for endangered species and marine mammals
• Inspection of both dragheads after every load for impinged turtles/other endangered species
NASA ENVIRONMENTAL CONSIDERATIONS REFERENCES
https://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7.
https://www.nasa.gov/goddard/memd/nepa/shoreline/ blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/wp-content/uploads/2024/05/sripp-final-peis-volume-ii.pdf?emrc=674f6afc265e7 blockedhttps://www.nasa.gov/goddard/memd/nepa/shoreline/
GROUND NEST LOCATIONS 2020-2024
CONTRACTING
TIFFANY N. KIRTSEY,
CIVIL BRANCH CHIEF – CONTRACTING OFFICER
NASA WALLOPS BREAKWATER AND BEACH RENOURISHMENT:
PROCUREMENT SNAPSHOT
NASA Breakwater Project
- Sources Sought issued 5 March 2026 and closes at 5:00 PM on 20 March 2026.
- Magnitude $10M - $25M
- Contract scheduled to be advertised in 4th Quarter of FY26
NASA Beach Renourishment
- Sources sought issued 12 March 2026 and closes at 2:00 PM 25 March 2026.
- Magnitude $25M - $100M
- Contract scheduled to be advertised in 4th Quarter of FY26
SAM: https://sam.gov/ https://sam.gov/
NORFOLK DISTRICT SMALL BUSINESS
Ms. Stormie Wicks Deputy for Small Business Programs Norfolk District, U.S. Army Corps of Engineers 803 Front Street Norfolk, VA 23510-1096
Phone: (757) 675-4428 stormie.b.wicks@usace.army.mil
QUESTIONS
• Are the marine mattresses usually assembled on site or are they imported from offsite? If they are assembled on site typically how large of an area is required to assemble them?
• What means and methods would the Contractor propose to construct the breakwater structures within the area offshore of the seawall since there is limited beach available?
• If construction equipment is mobilized within NASA’s flight zone, what advance notice would be required to demobilize the equipment from the flight zone prior to a launch date? How long does it generally take to mobilize and demobilize the equipment from a construction area to a staging area outside of the flight zone?
• With the limited availability of hopper dredges, what would be a period of performance that would encourage bidding?
• How could scheduling be accomplished with the known site limitations/restrictions?
• Is there industry interest in one contract or two separate contracts?
• Does the Contractor have had experience with constructing access roadways to breakwaters that are 200 feet offshore during construction? What measures and methods would they consider constructing and using?
• What time of the year would the contractors typically consider dredging for the project?
• When breakwaters are constructed, are they usually constructed around the clock until the structure is complete if the structure is in an active tidal environment? How long does it typically take to construct one breakwater structure (depending on size)?
| Industry day�Wallops Island Shoreline Stabilization Project |
| agenda |
| Welcome and opening remarks��Project overview�SCOPE and Schedule��Shadera williams�project manager usace |
| Disclaimer |
| goals |
| Nasa wallops island |
| Slide Number 7 |
| Schedule�combination of dredging/renourishment and construction |
| Design��Nick Ingold, PE�Civil Engineer USACE |
| Current design |
| Beach RENOURISHMENT & template |
| Breakwater design & layout |
| Outstanding Design taskS |
| Dredging��Tom Luehman, PE�Civil Engineer Water Resources Division USACE |
| dredging |
| Project site�location and restrictions��John Saecker, PE�Project Manager �Civil Engineer Wallops Flight Facility |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
| 10 Minute break |
| Environmental considerations��Megan Wood, PhD�Environmental Scientist USACE |
| Environmental considerations from previous contracts |
| Nasa environmental considerations references |
| Ground nest locations 2020-2024 |
| CONTRACTING��TIFFANY N. Kirtsey,�Civil branch chief – Contracting officer |
| NASA Wallops Breakwater and Beach Renourishment: Procurement Snapshot |
| Norfolk district Small business |
| QUESTIONS |