DRAFT Specifications Sandbridge Beach Renourishment_26BA011.pdf
PDF 25 MB Posted
- Solicitation number
- W9123626BA011
About this file
This is a Draft Specifications document for the Sandbridge Beach Erosion and Hurricane Protection Beach Renourishment Project, issued by the U.S. Army Corps of Engineers Norfolk District. The document outlines comprehensive technical and administrative requirements for a hopper dredge beach renourishment contract valued between $25 million and $100 million, with an anticipated construction completion date of approximately 365 calendar days from Notice to Proceed.
The primary scope of work includes dredging beach fill material from the Government-furnished Sandbridge Shoal Borrow Area A (located 3-5 miles offshore with depths ranging from -35 to -67 feet MLLW) and placing approximately 3,260 acres of material on Sandbridge Beach in Virginia Beach, Virginia. Contractors must perform before-dredge and after-dredge hydrographic surveys, transport dredged material via hopper dredge to pump-out buoys, and deposit material through hydraulic pipeline systems within designated beach segments. The specifications mandate hopper dredging prohibitions between September 1 and November 14, strict environmental compliance including sea turtle protection protocols with negotiated rehabilitation fees ($1,502-$61,073 per turtle depending on injury severity), and archaeological resource avoidance. Key administrative requirements include submission of a Marine Plant Anchorage Plan, Borrow Area Material Removal Plan, and Remote Sensing Survey prior to dredging; notification to National Marine Fisheries Service, U.S. Coast Guard, and BOEM within specified timeframes; compliance with the Seagoing Barge Act; and coordination with Navy firing exercises. Payment is structured as lump sum for mobilization/demobilization (60% upon completion, 40% upon demobilization) and unit prices per cubic yard for dredging/beach fill placement. The Contractor must maintain a qualified Professional Engineer or Surveyor for all survey work, provide daily operations reports, furnish project photography, maintain adequate insurance coverage, and comply with strict noise control, public safety, and environmental protection measures throughout the contract period.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9123626BA011: Sandbridge Beach Renourishment Project DRAFT Specifications
The following DRAFT specifications are distributed with the pre-solicitation notice for planning purposes. Final specifications will be posted with the solicitation.
United States Army Corps of Engineers Norfolk District
SANDBRIDGE BEACH EROSION AND
HURRICANE PROTECTION BEACH
RENOURISHMENT PROJECT
Virginia Beach, VA
Specifications
Final
July 2026
Prepared By:
United States Army Corps of Engineers Norfolk District Engineering Division Design Branch 803 Front Street Norfolk, VA 23510
Sandbridge Renourishment FY2027 Final
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 55 SOIL BORING DATA
01 14 00 11/22, CHG 2: 05/24 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 16.00 10 05/16 DESIGN DATA (DESIGN AFTER AWARD)
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 30 09/11 GOVERNMENT PROVIDED MUNITIONS AND
EXPLOSIVES OF CONCERN (MEC)
CONSTRUCTION SUPPORT
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 30 10/15 ENVIRONMENTAL PERMIT WORK REQUIREMENTS
01 57 40 07/11 SPECIAL EQUIPMENT AND PROCEDURE
REQUIREMENTS FOR PROTECTION OF
ENDANGERED SPECIES AND AVOIDANCE OF
ARCHEOLOGICAL RESOURCES
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 08/20 DREDGING
35 20 23.23 02/22 NATIONAL DREDGING QUALITY MANAGEMENT
PROGRAM - HOPPER DREDGE
35 20 24 04/15 BEACH FILL
-- End of Project Table of Contents --
DOCUMENT PROJECT Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/24
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET NO. TITLE
G001 COVER SHEET, INDEX OF DRAWINGS, VICINITY, AND LOCATION
MAP
G002 GENERAL NOTES, DATUM DIAGRAM, AND LEGEND
CN001 BORROW AREA AND BEACH RENOURISHMENT AREA
CN101 DREDGE AREA LIMITS IN BOEM BORROW AREA A AND
BATHYMETRIC SURVEY
CN102 REMOTE SENSING CONTACTS AND OBSTRUCTIONS IN BORROW AREA
A
CS101 EXISTING CONDITIONS SITE PLAN (1)
CS102 EXISTING CONDITIONS SITE PLAN (2)
CS103 EXISTING CONDITIONS SITE PLAN (3)
CS104 EXISTING CONDITIONS SITE PLAN (4)
CS105 EXISTING CONDITIONS SITE PLAN (5)
CS106 EXISTING CONDITIONS SITE PLAN (6)
CS107 EXISTING CONDITIONS SITE PLAN (7)
CS108 EXISTING CONDITIONS SITE PLAN (8)
CS109 EXISTING CONDITIONS SITE PLAN (9)
CS110 EXISTING CONDITIONS SITE PLAN (10)
CS111 EXISTING CONDITIONS SITE PLAN (11)
CS112 EXISTING CONDITIONS SITE PLAN (12)
DOCUMENT 00 01 15 Page 1
SHEET NO. TITLE
CB101 BEACH RENOURISHMENT GRADING PLAN (1)
CB102 BEACH RENOURISHMENT GRADING PLAN (2)
CB103 BEACH RENOURISHMENT GRADING PLAN (3)
CB104 BEACH RENOURISHMENT GRADING PLAN (4)
CB105 BEACH RENOURISHMENT GRADING PLAN (5)
CB106 BEACH RENOURISHMENT GRADING PLAN (6)
CB107 BEACH RENOURISHMENT GRADING PLAN (7)
CB108 BEACH RENOURISHMENT GRADING PLAN (8)
CB109 BEACH RENOURISHMENT GRADING PLAN (9)
CB110 BEACH RENOURISHMENT GRADING PLAN (10)
CB111 BEACH RENOURISHMENT GRADING PLAN (11)
CB112 BEACH RENOURISHMENT GRADING PLAN (12)
CB401 BEACH RENOURISHMENT BERM SECTIONS (1)
CB601 CONSTRUCTION BASELINE AND BERM CREST COORDINATE TABLES
BB101 VIBRACORE SAMPLING LOCATIONS IN BOEM BORROW AREA A
BB301 SCHNABEL BORING LOGS
BB302 SCHNABEL BORING LOGS (CONTD.)
BB303 SCHNABEL BORING LOGS (CONTD.)
BB304 SCHNABEL BORING LOGS (CONTD.)
BB305 SCHNABEL BORING LOGS (CONTD.)
BB306 SCHNABEL BORING LOGS (CONTD.)
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Document --
DOCUMENT 00 01 15 Page 2
SECTION 01 00 55
SOIL BORING DATA
PART 1 GENERAL
1.1 Soil Classification
The soil was visually classified in the field according to the "Unified Soil Classification System" and described utilizing the "Burmister's Method of Material Proportions". While it is believed that borings accurately indicate subsurface conditions for boring locations on the date taken, the Government assumes no responsibility for actual conditions which may be encountered in execution of Contract. Should the Contractor rely, for any purpose, upon the accuracy or completeness of said borings, or log thereof, he does so at his own risk. The geotechnical report, including soil boring drilling logs and data, is shown in the 2018 Schnabel Geotechnical Report at the end of the specifications. Soil borings shown in Appendix A, Laboratory Analysis is shown in Appendix B, and Beach Laboratory Analysis data is shown in Appendix C of the Geotechnical Report. All samples contained in the appendices at the end of the specifications were obtained on various dates as designated on the respective boring. Geotechnical analysis data is available for review at Norfolk District, 803 Front Street, Norfolk, VA 23510 (Attention: Matt McKeehan telephone 757-201-7172).
1.2 Sampling Method
All boring samples were obtained utilizing a vibracore sampler.
1.3 Soil Consistency Determination
Estimated consistencies (med. stiff, soft, etc.) are from Terzaghi & Peck "Soil Mechanics in Engineering Practice".
1.4 Boring Elevations and Locations
All boring elevations and locations are approximate and their respective location indicated.
1.5 Abbreviations (if applicable)
BOH Bottom of Hole moist moisture bot bottom MP medium plasticity brk broken mrb marbled brwn brown mst moist cly clayey NP nonplastic const consistency OD Outside diameter crs, c coarse org organic dk dark PI Plastic Index dns dense PL Plastic Limit fn, f fine sam sample frac fracture sat saturated frag fragments (fragmented) sft soft grn green slt slight(ly) gry gray sly silty
SECTION 01 00 55 Page 1
HP high plasticity sm some hrd hard sta station hrs hours tr trace len lense v very lit little v.f. very fine LL Liquid Limit w moisture content
LP Low Plasticity w/ with lt light wd weathered med, m medium & and mica micaceous %200 Minus No. 200 Sieve
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
SECTION 01 00 55 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 2: 05/24
PART 1 GENERAL
The work consists of dredging beach fill material from the Government furnished borrow site located offshore approximately 3 to 5 miles east of Sandbridge Beach (location shown in the project plans/drawings). The Contractor shall perform the scheduled work with one or more Hopper dredges, and transport the material to a pump out buoy or series of pump out buoys to be provided by the Contractor. The material shall then be carried from the pump out buoy or buoys to the beach by hydraulic pipeline and deposited within the designated beach placement area segments as indicated and specified on the construction plans.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-1005 (2007) Control and Topographic Surveying
EM 1110-2-1003 (2013) Hydrographic Surveying
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Marine Plant Anchorage And Equipment Working Area Plan ; G
Prior to commencement of dredging, submit a Plan indicating all work activities proposed for marine plant anchorage, storage, maintenance, refueling, and routine or major repairs to marine plant and equipment that cannot be performed from the beachfront during this contract and planned use of the City Dredge Operations Facility (CDOF), Lake Rudee or Croatan Point.
Notify Commander, East Coast Guard District
Notify National Marine Fisheries Service
Marine Remote Sensing Survey ; G, DO
Borrow Area Material Removal Plan ; G, DO
SECTION 01 14 00 Page 1
1.3 CONTRACTOR'S NOTIFICATION
A Dredging Intent Notification shall be prepared and sent to the agencies identified below identifying the dredging locations, placement areas, and dates the Contractor intends to start and complete dredging. When the Contractor sends a Notification to an agency, proper signatures shall be affixed. A copy of all Notifications furnished shall at the same time be provided to the Contracting Officer.
1.3.1 Dredging Intent Notifications
a. Notify National Marine Fisheries Service . The Contractor shall notify the National Marine Fisheries Service by email (Incidental.Take@noaa.gov) within 3 days of the commencement of dredging and again within 3 days of the completion of dredging activity.
b. Notify Commander, East Coast Guard District . The Contractor shall notify the Commander, East Coast Guard District of his intended operations to dredge and request that it be published in the Local Notice to Mariners. This Dredging Intent Notification to U.S. Coast Guard must be given in sufficient time so that it appears in the Notice to Mariners at least 21 calendar days prior to the commencement of this contract.
1.3.2 Notification Of Beach Fill Operations
The Contractor shall maintain a current register of planned beach fill operations indicating where the beach fill operations will be on a given day, including street locations for the beach fill operations and the pump out facility, and their daily projected locations along the beach fill placement area for the duration of the contract. The register shall be updated daily and provided with the Daily Report of Operations in a format approved by the Contracting Officer for ready release to the public.
1.4 CONTRACTOR WORK REQUIREMENTS
The dredging and placement areas are accessible to the general public;
however, the Contractor is informed the Government will not undertake to exclude the public or restrict public access to the dredging or placement areas during the work. The Contractor shall be solely responsible for protection of the public at all times for the duration of work performed as a part of the contract and fully comply with the provisions of OSHA safe working practices and the Safety and Accident Prevention requirements of these specifications. The Contractor shall employ the use of signs, barricades, barriers, flagmen, and any other devices and measures required to ensure public and worker safety at the dredging and placement areas at all times. Unless directed otherwise, the Contractor may perform the scheduled dredging and material placement work 24 hours a day, 7 days a week, except for Memorial Day and Independence Day. During actual dredging and material placement operations, the Contractor shall ensure adequate monitoring of operations by competent employees at the placement areas and contact with the dredge by monitoring personnel is maintained at all times.
All lighting associated with the project shall be limited to the immediate area of active construction only. Such lighting shall be shielded, low-pressure sodium vapor lights directed to the maximum extent
SECTION 01 14 00 Page 2 practical away from populated areas where applicable and to avoid excessive illumination of the water. Orange or yellow light filters shall be installed on lighting and equipment operating on the beach at night from May 1 through November 15. Light shall comply with OSHA and Corps' Occupational Health and Safety regulations, standards, or technical guidance or otherwise jeopardize or threaten human safety.
1.4.1 Order of Work
The Contractor shall perform all required beach fill placement operations, as shown on the drawings commencing from the south (0+00) to the north.
1.4.2 Hopper Dredge Seasonal Restrictions
Hopper dredging shall be prohibited between 1 September and 14 November.
See 01 57 30 ENVIRONMENTAL PERMIT WORK REQUIREMENTS and the Biological Opinion (attached to the end of these specifications) for more information.
1.4.3 Access to Work Site
The contractor shall use all access locations shown on the project construction plans.
The Sandbridge Beach oceanfront is served by an all weather surfaced road network. The Contractor's equipment and vehicular access into the work area will be available from Little Island Park at the South end of the project area. The Contractor shall prepare, as a part of his Accident Prevention Plan and Progress Schedule, his proposed methods for gaining access to the workplace by the designated right-of-way that does not unnecessarily impact convenient and safe access to and from the beach by the public. Access and egress to the work area is the responsibility of the Contractor and is subject to permit approvals required by the City of Virginia Beach. All roads approved for the Contractor's use shall be maintained throughout construction and restored to as good condition as existed prior to their use. The Contractor shall keep all roads free of mud and other foreign materials resulting from his operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles and vehicles with flashing lights. All temporary construction shall be removed and the affected area restored to its original condition. All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.
1.4.4 Designated Marine Plant Anchorage and Equipment Working Area Restrictions
The City Dredge Operations Facility (CDOF), Lake Rudee and Croatan Point are designated for marine plant anchorage, storage, maintenance, refueling, and routine or major repairs to marine plant and equipment that cannot be performed from the Sandbridge beachfront during this contract.
The Contractor shall submit a Marine Plant Anchorage and Equipment Working Area Plan for approval, indicating all proposed plant anchorage and other scheduled activities at the CDOF, Lake Rudee or Croatan Point. The Plan shall be coordinated with the CDOF and include the proposed plant and scheduled activities and be coordinated with the Activity Hazard Analysis and Safety Plan. The Contractor must comply with all rules and regulations
SECTION 01 14 00 Page 3 governing use of the CDOF and all costs for use of the facility are the responsibility of the Contractor.
The Contractor is informed the use of Lake Wesley (inside Rudee Inlet to the Southeast of Lake Rudee) will not be allowed for storage, maintenance, refueling, or repairs to marine plant and equipment, or for any other non-emergency purpose. The use of Lake Wesley will only be allowed for anchorage of plant that, due to size and height restrictions, cannot reasonably be stored at the CDOF, Lake Rudee or Croatan Point. If it becomes necessary for the Contractor to request anchorage of plant or to perform other non-emergency functions in Lake Wesley, the Contractor must verify the CDOF, Lake Rudee and Croatan Point are unavailable or otherwise unsuitable for use and shall obtain written permission from the Contracting Officer's Representative at least 48 hours in advance of the use of Lake Wesley.
Prior to commencement of dredging, submit a Marine Plant Anchorage and Equipment Working Area Plan indicating all work activities proposed for marine plant anchorage, storage, maintenance, refueling, and routine or major repairs to marine plant and equipment that cannot be performed from the beachfront during this contract.
1.4.5 Contracting Officer Stand By Time
During the contract period, the Government reserves the right to issue stand by orders to the Contractor for periods up to 24 hours at a cost and in a number as reflected in the bid schedule item 0008, in 01 20 00 PRICE AND PAYMENT PROCEDURES. If the Contracting Officer directs that plant be placed in a standby status, the Contractor shall cease all beach fill operations and secure his on beach plant and equipment off the beach in the Contractor’s approved Staging Area. During this period the Contractor will be allowed to perform dredging, but will not be allowed to operate any plant on the beach including operations that utilize the pump out mooring facility. The Contracting Officer will give the Contractor a minimum 72 hour notice before plant is to be placed on standby status.
When in standby status, plant will not be moved from the designated location unless approved by the Contracting Officer.
1.4.6 Noise Control and Abatement
The Contractor shall employ the use of properly installed and maintained mufflers, silencers, and manufacturer's recommended sound suppressors on all plant, machinery, and equipment used on this work. The use of sound signals such as whistles, horns, or bells shall not be used if two-way radio communication can accomplish the required function. During the time between 7:00pm and 7:00am, the Contractor shall plan and schedule his work operations to minimize operations of plant and equipment on the beach, and in waterways near populated areas. Noise of alarms from the backward use of plant on the beach during this period will not be allowed except to meet safe working practices as prescribed by OSHA. Accordingly, the Contractor shall operate plant in a forward mode and limit beach fill operations to the maximum extent practical during this time. The Contractor shall not use sound signals, with the exception of those signals required for vessel operations by the U.S. Coast Guard, during the time between sunset and sunrise.
SECTION 01 14 00 Page 4
1.5 PHYSICAL DATA
1.5.1 Physical Conditions Information
The physical conditions indicated on the drawings and in the specifications are the result of site investigations and surveys.
Information and data furnished or referred to below is furnished for the Contractor's information; however, it shall be expressly understood that the Government will not be responsible for any interpretation or conclusion drawn from this information or data by the Contractor.
1.5.2 Site Related Weather Conditions
The locations of the work are in open ocean waters and along the Virginia Beach oceanfront; accordingly, the Contractor shall anticipate that severe weather conditions may occasionally interfere with the progress of work.
The area is tidal with a mean range of tide of approximately 3.5 feet based on NOS observations at the Virginia Beach Fishing Center. Currents are normally not of a sufficient velocity to interfere with dredging operations; however, offshore winds and other natural weather events may lead to shoaling hazards. The Contractor shall satisfy himself as to the hazards likely to arise from the weather conditions during the dredging period. Complete weather forecasts, records and reports may be obtained from the National Weather Service in Wakefield, Virginia, telephone (757) 899-4200, Menu selection service or operator assisted as applicable.
1.5.3 Additional Information for Local Physical Conditions
The Contractor shall consult the following publications for additional information on local conditions:
a. United States Coast Pilot 4, Atlantic Coast, Cape Henry, Virginia to Key West, Florida, published annually by the National Ocean Service.
b. Tide Tables, High and Low Water Predictions, East Coast of North and South America, published annually by the National Ocean Service.
c. Tide Current Tables, Atlantic Coast of North America, published annually by the National Ocean Service.
d. Local Notice to Mariners, published by the U.S. Coast Guard East District and the broadcast local notice to mariners.
1.5.4 Condition of Borrow Areas
The plans for dredging show the condition of the offshore borrow area at the time of the most recent survey. There are no known pipes, bridges, or tunnels that cross the area to be dredged; however, there exist cables in the borrow area and are shown on the borrow plan. The Contractor shall avoid the restricted area shown on the borrow area plan. The contractor shall submitted a Borrow Area Material Removal Plan which will display how the contractor will conduct the dredging activities in the borrow area.
Additional guidelines regarding archaeological finds can be found in paragraph 1.15 of this section.
1.5.5 Obstruction of Borrow Areas
The Government will not undertake to keep the vicinity in and around the
SECTION 01 14 00 Page 5 borrow areas or offshore areas within the project limits, free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act, approved 3 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractors' plant so obstructs the water way as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under this contract in navigable water or on shore.
1.5.6 Borrow Area Traffic
Traffic in the borrow area is anticipated to include various commercial, government, military, and fishing vessels as well as pleasure craft.
1.5.7 Condition of Beach Fill Areas
The required beach fill areas and quantity estimates specified are based on the condition of the beach at the time of the most recent surveys as indicated. The conditions shown by the surveys and the required beach fill quantities specified are subject to change due to the constantly changing shoreline and the natural forces of wind and waves acting on the beach.
The actual quantities to be placed and paid for in each respective beach fill segment will be determined by the Contracting Officer from the surveys and volume computations to be performed by the independent surveyor or engineer as specified immediately before the Contractor commences fill operations in a respective beach fill section. The Contracting Officer may make alterations in the plan dimensions, grade of slopes, or volume of fill per linear foot in a respective beach fill segment in order to increase or decrease the volume of fill placed along the beach. The Contractor shall work closely with the Contracting Officer to ensure that the total quantity of sand allowed under this contract is uniformly distributed along the entire length of the beach fill area in a manner to construct a finished beach berm of constant dimensions along the entire project length. Please refer to SECTION 35 20 24 BEACH FILL for beach fill construction dimensions and tolerances.
1.5.7.1 Globalinx Subsea Conduits
There are four (04) subsurface conduits under the northern end of the beach placement area which daylight in theocean east of Sta 222+00. The location of these conduits and an avoidance area of two hundred (200) feet are shown on the plans. As-built information is available upon request.
1.5.8 Oyster Grounds
There are no known oyster grounds in the vicinity of the borrow areas or placement area.
1.6 NAVY FIRING AREA
a) A Navy Firing Area (204.52) encompasses the offshore Sandbridge borrow site. The extent of the firing exercises involve mostly small arm ranges, located north of Sandbridge, and are used 5 to 7 days per week. An inactive gun line is also located north of Sandbridge. Both the gun line and small arms range are operated in accordance with 33
SECTION 01 14 00 Page 6
CFR 334.390 and 33 CFR 334.380, respectively. Neither of these activities is expected to impact operations within the borrow area.
b) Drone firing exercises, which when conducted require a borrow site shut down, occur on the average twice per month (over a three day period) for a duration of 4 to 6 hours per event. The Contractor shall anticipate these delays and plan his operations accordingly so as to minimize down time.
c) It is the Contractor's responsibility to coordinate all of his borrow area activities so as to prevent conflicts between Navy operations and dredging operations.
For drone firing exercises, please coordinate dredging and beach placement efforts with:
Gilbert Orosco Atlantic Range & Targets Department Naval Air Warfare Center 2140 Regulus Avenue, Bldg 481 Virginia Beach, VA 23461 757-492-8399 gilbert.l.orosco.civ@us.navy.mil
For the Navy Firing Area, please coordinate dredging and beach placement efforts with:
Gregory Thomas Fleet Forces Atlantic Exercises Coordination Center 757-433-1345 gregory.w.thomas.civ@us.navy.mil
d) The contractor is not to spud, anchor, place buoys, or dredge between the two borrow areas and north of the line indicated on the plans.
1.7 LAYOUT OF WORK AND SURVEYS
1.7.1 General
The Contractor shall be responsible for the expense and layout of all work. When the Contractor's work methods require physical markings to be placed for the purpose of dredged material placement control, including all placement area and easement control points and all range markers and buoys indicated or that otherwise are required to accomplish the work, shall be placed in the field and marked by a licensed Professional Engineer or Surveyor currently licensed in the Commonwealth of Virginia.
The licensed Professional Engineer or Surveyor shall have coastal topographic and hydrographic surveying experience. All hydrographic survey techniques shall be in accordance with EM 1110-2-1003 . All topographic survey techniques shall be in accordance with EM 1110-1-1005 . The markings shall be minimum 1 inch diameter steel pipe marked with orange flagging and orange paint, placed in the immediate work areas only and shall be removed once a work area has been accepted. The Government reserves the right to verify all in-place markings before dredging and placement operations commence, and at any time during the contract.
SECTION 01 14 00 Page 7
1.7.2 Datum and Bench Marks
The plane of reference for the project is NAVD 88, North American Vertical Datum 1988 as indicated. The bench mark elevations are shown on the drawings for the respective work areas. The government will furnish monument descriptions for these bench marks at the Preconstruction Conference.
1.7.3 Responsibility for Tide Measurements
It shall be the responsibility of the Contractor to obtain tide level measurements and predictions as required to conduct his dredging operations for the duration of the work.
1.7.4 Contractor Layout for Survey of Beach Requirements
The Contractor shall submit for approval a base line drawing showing all offsets, elevations, reference lines, and range line locations to be utilized for the entire project prior to performing any surveying. This drawing shall be prepared and stamped by the independent Professional Engineer or Surveyor employed as specified above.
1.8 CONTINUITY OF BEACH FILL WORK
Placement of the beach fill shall proceed in an orderly and consecutive manner. No payment will be made for work done in any acceptance section of the beach designated by the Contracting Officer until the entire acceptance section is brought to the shape and grade indicated and specified. When the Contractor moves his pipeline upon completion of a beach segment section and commences placing material in a manner that the new beach segment section adjacent to the completed section is tied into the completed section, acceptance for payment purposes will not be made on either section until both sections are completely finished contiguously.
1.9 CONTINUITY OF BORROW AREA DREDGING
The Contractor shall submit for approval a Borrow Area Material Removal Plan. The plan shall indicate the operations and procedures he intends to perform in each respective borrow area, work methods to be employed that will result in efficient hydraulic placement of the required amount of materials within the beach fill section, and the proposed station locations where material is to be removed. The material removal operations shall be performed to the maximum extent practical in contiguous sections that do not result in the creation of deep pits or holes in the borrow area.
1.10 AGREEMENT WITH BOEM TO USE THE SANDBRIDGE BORROW AREA
A Memorandum of Agreement (MOA) with BOEM authorized the use of sand resources from the Sandbridge Shoal Borrow Area A. The agreement states that USACE or its contractor(s) may only extract, transport, and place such Outer Continental Shelf (OCS) sand resources from the borrow area in accordance with the terms and conditions set forth in the agreement.
This agreement is included as an attachment to these specifications. All conditions within the BOEM MOA are also conditions of this solicitation.
Any questions regarding the agreement shall be directed to the USACE Contracting Officer.
SECTION 01 14 00 Page 8
1.10.1 MOA required Notifications
As part of the agreement to use the borrow area, the following events require notification to BOEM by USACE:
1. 72 hours prior to commencing operations in the borrow area.
2. 24 hours after termination of operations.
3. Immediate notification of any dredging outside of the approved borrow area.
4. Any noncompliant discharges and remedial actions taken in the borrow area.
5. Any encounter of ordnance must be reported to BOEM within 24 hours.
6. If any previously unknown historic or archeological resources are encountered during operations.
In order for USACE to meet these requirements, the Contractor will provide the Contractor will notify the Contracting Officer, the Contracting Officer's Representative (COR), or the Construction Representation of the following events:
1. 96 hours prior to the commencing of operations in the borrow area.
2 - 6. Immediate notification
1.11 INSPECTION
1.11.1 General Inspection Requirements
The presence of the construction representative shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor will be required:
a. To furnish, on the request of the Contracting Officer or any construction representative, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the dredging.
b. To furnish, on the request of the Contracting Officer or any construction representative, suitable transportation from all points within the placement area, to and from the various pieces of plant and the staging areas, and within the material placement area as may be reasonably necessary in inspecting and supervising the work. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and any resultant cost incurred by the government will be deducted from any amounts due or to become due the Contractor.
c. To furnish the Government construction representative a portable radio capable of communicating with the dredge for the duration of work under this contract. The Contractor shall maintain the radio as required.
SECTION 01 14 00 Page 9
d. Hopper dredges shall be provided with a fixed vertical ship ladder system (in compliance with the requirements of ASTM F1166) as the primary means of safe access/egress for works and visitors embarking / disembarking the vessel. A double rung of flat tread Jacob's ladder shall not be used as the vessel's primary means of safe access.
1.11.2 Accommodations Aboard Dredge For Construction Representatives
1.11.2.1 Accommodations
Work Space - The Contractor shall furnish regularly to Government construction representatives on board the dredge a suitable working and storage space, equipped and maintained to the satisfaction of the Contracting Officer or his representative. As a minimum the facilities shall include a desk with chair for plan study, and a file drawer, approximately 15" by 24", capable of being locked with a padlock. The working space need not be a separate room, but shall be properly lighted, ventilated, and heated.
1.11.2.2 Costs
The entire cost to the Contractor for furnishing, equipping, and maintaining the foregoing accommodations shall be included in the contract price. If the Contractor fails to meet these requirements, the Contracting Officer will secure the facilities referred to above, and their costs will be deducted from payments due to the Contractor.
1.12 SPECIAL COAST GUARD REQUIREMENTS
1.12.1 Local Notice To Mariners
The Local Notice To Mariners (LNM) for the East Coast Guard District is available by phone at (757) 398-6367. Additionally, LNM are on the Internet at:
https://www.dco.uscg.mil/Featured-Content/Mariners/Local-Notice-to-Mariners-LNMs/ The LNM is the primary means for disseminating information concerning aids to navigation, hazards to navigation, and other items of marine information of interest to mariners on the waters of the United States, its territories, and possessions. These notices are essential to all navigators for the purpose of keeping their charts, light lists, Coast Pilots and other nautical publications up-to-date. These notices are published weekly. They may be obtained free of charge, by making application to the East Coast Guard District, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704.
The timeline for notification is outlined in the Memorandum of Agreement with BOEM, which is included as an attachment to these specifications.
If the Contractor encounters any objects on the bottom during dredging operations or transport of his plant that could be a hazard to navigation, he shall notify the Coast Guard immediately as to location and at the same time notify the Contracting Officer.
1.12.2 Relocation of Navigation Aids
The Contractor shall not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under
SECTION 01 14 00 Page 10 this contract, the Contractor shall notify the U.S. Coast Guard in writing at the address above with a copy to the Contracting Officer not less than 45 calendar days prior to such need for movement. The Contractor shall notify the U.S. Coast Guard of the approximate time the navigation aid may be relocated to its original position. All notifications to the U.S. Coast Guard shall at the same time be provided to the Contracting Officer and recorded in the Daily Report of Operations. In the event that the Contractor disturbs or damages any navigation aid during work operations, which includes during mobilization or demobilization of his plant, the Contractor shall immediately stop the activity which disturbed or damaged the navigation aid, take immediate corrective action to prevent further disturbances or damage, and shall notify the Coast Guard immediately as to location, and at the same time notify the Contracting Officer.
1.13 MISS UTILITY
The Contractor shall comply with all requirements of the Virginia Underground Utility Damage Prevention Act § 56-265.14 (the Miss Utility law). The Contractor must call the Miss Utility Notification Center at 811 OR 1-800-552-7001 before commencing any excavation work, including dredging.
The Contractor shall provide to the government, in writing, all Ticket numbers, Miss Utility system responses and other information upon completion of the Contractor's notification process to Miss Utility prior to dredging. Requirements of the law, procedures to followed by the Contractor and other pertinent information for the Contractor's use can be found at http://www.missutilityofvirginia.com (or http://va811.com/lawspolicies/). Each "person" as defined in the Underground Utility Damage Prevention Act must provide their own notice of excavation. Subcontractors may not work under another company's ticket unless they are under the direct supervision of the company that provided the notice of excavation.
The Contractor shall allow a minimum of 48 hours after notifying the Miss Utility notification center and begin excavation only after checking the Positive Response System, and confirm through the Ticket Information Exchange (TIE) System, that all applicable utilities have either marked their underground line locations or reported that no lines are present in the work vicinity. The Contractor shall wait an additional 24 hours before commencing excavation work if any utility operators have failed to respond to the Ticket Information Exchange within the first 48 hours.
1.14 ENVIRONMENTAL LITIGATION
1.14.1 Litigation
If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the "Suspension of Work" clause of this contract. The period of such suspension, delay, SECTION 01 14 00 Page 11 or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof. The term "environmental litigation" means, a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
1.15 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historic, and archaeological data, including relics and specimens that might otherwise be lost as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historic, or archaeological data, the Contractor shall immediately cease work at that location, and notify the Contracting Officer, giving the location and nature of the findings.
Contractor shall clearly photograph any suspected resources if pieces are found in the draghead or hopper. Photographs shall be taken from all angles when feasible and provided to the Contracting Officer's Representative.
The Contractor shall retain any suspected resource, or piece of a suspected resource, recovered in the draghead so long as it is safe to do so The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contracting Officer shall notify the districts' Archaeologist, Environmental Manager, and the State Historic Preservation Office if any resources are discovered. USACE will coordinate with VDHR to determine the final disposition of any suspected resource.
The Contractor shall exercise care so as not to disturb or damage shipwrecks, artifacts or fossils uncovered during excavation, dredging and material placement operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without written permission, injures, destroys, excavates, appropriates, moves or removes any historic or prehistoric artifact, object of antiquity, or archaeological resource is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in accordance with the applicable clauses of the contract.
1.15.1 Avoidance of Historic Resources
Not less than thirty calendar days from the start of dredging operations, the Contractor shall perform a marine remote sensing survey at the site(s) of any booster(s) or Scott's buoy/anchored pumpout buoy locations to ensure that potential historic resources are not located within his work area. If potential resources are identified during the survey, Contractor shall immediately notify the Contracting Officer's Representative, giving the location and nature of the findings. Contractor shall relocate his construction areas and establish a 100-ft buffer around the discovery. Do not anchor or spud in any such historic-resource, buffer zone nor disturb the buffer area in any way.
The proposed revised buoy site or booster location shall be surveyed to
SECTION 01 14 00 Page 12 ensure no historic resources are within any revised work area.
A list of Archaeological Avoidance Areas, including location and minimum avoidance radius, is included as an attachment to the project specifications.
1.16 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
(a) Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractors, or to limit work performed by any trade.
(b) Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
(c) The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.
(d) The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.17 SEAGOING BARGE ACT
All dredges, barges, and vessels used for the transport of dredged material shall meet the applicable requirements of the Seagoing Barge Act (46 U.S.C. et seq). To document compliance with this act, the Contractor shall submit with his bid copies of U.S. Coast Guard Certificate of Inspection for each item of plant. Certification shall also be furnished to the Contracting Officer if additional plant is engaged during the course of the work.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 13
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 3: 02/23
PART 1 GENERAL
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-1005 (2007) Control and Topographic Surveying
EM 1110-2-1003 (2013) Hydrographic Surveying
1.2 SUBMITTALS
NOT USED.
1.3 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3.1 Base Bid Payment Item No. 0001 Mobilization and Demobilization
All costs connected with the mobilization and demobilization, inclusive of additional remobilizations and demobilizations for seasonal restriction windows, of the Contractor's plant and equipment for dredging Sandbridge Shoal Borrow Area A and placement on Sandbridge Beach are included in this bid item. Sixty percent of the lump sum price will be paid to the Contractor upon completion of his mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer
SECTION 01 20 00 Page 1 may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.
All dredging costs are to be incidental to the cost for beach placement.
No separate payment will be made for the dredging work performed
1.3.1.1 Mobilization
Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging and beach fill placement operations. This shall include transfer of dredge and attendant plant, booster pumps and pump out buoys, bulldozers and other like equipment and machinery including pipelines associated with beach fill placement operations, preparation of the Contractor's staging area and any long term staging area(s) used for off beach equipment and material storage, and any other associated work that is necessary in advance of the actual dredging and beach fill placement operations.
1.3.1.2 Demobilization
Demobilization shall include general preparation for transfer of dredging and beach fill plant as described in Paragraph "Mobilization" above to its home base, cleanup of the Contractor's long term staging area, and transfer of the dredging and beach fill plant to its home base.
1.4 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.4.1 Base Bid Payment Item No. 0002 Live Sea Turtle Response with Traumatic Fatal Injuries (Level One)
Payment to be made for this item includes all costs for the collection, handling, transportation, and delivery of a live sea turtle to the Virginia Aquarium & Marine Science Center Stranding Response Team (VAQS)(mailing address: 717 General Booth Blvd, Virginia Beach, Virginia 23451), the payment of the VAQS fee as defined below for their response and rehabilitation, and all other associated costs.
Level One is defined as a live sea turtle that is transferred to the VAQS and is euthanized or dies within 48 hours due to the severity of the injuries resulting from the dredge interaction. The government has negotiated the fee for this item at $1,502.00 and includes the predetermined costs incurred by the VAQS for live response and rehabilitation of a live sea turtle with traumatic fatal injuries (level one).
Live Sea Turtle dredge takes are categorized into one of three fee levels
SECTION 01 20 00 Page 2
(1, 2, or 3) and this Payment Item is specific to fee level one. The fee levels will be determined by the VAQS based on the severity of the injury resulting from the dredge interaction. These fees have been negotiated between the Government and VAQS. Once VAQS assesses the turtle and determines the severity of the injury, the Contractor shall be responsible for paying VAQS directly for the predetermined fee associated with the response and care of live sea turtle dredge takes. The Contractor shall submit the invoice from VAQS to the Contracting Officer within 7 days of receipt. Within 30 days of receiving the invoice, the Contractor shall submit payment to VAQS. The Contractor shall submit to the Contracting Officer the Contractor's proof of payment from VAQS along with the Contractor's Invoice for this Payment Item.
The Contractor shall include the level one fee to VAQS for this Payment Item in their bid for this item.
1.4.2 Base Bid Payment Item No. 0003 Live Sea Turtle Response and Rehabilitation with Mild to Moderate Traumatic Injuries (Level Two)
Payment to be made for this item includes all costs for the collection, handling, transportation, and delivery of a live sea turtle to VAQS, the payment of the VAQS fee as defined below for…