811-FY17SB4_100__SPECIFICATIONS.pdf
PDF 25 MB Posted
- Attached to
- Craney Island Spillbox #4, Portsmouth, Virginia
- Solicitation number
- W91236-18-B-0007
About this file
W91236-18-B-0007, Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W91236-18-B-0007-0001.pdf | ||
| A.07.14_Site_Visit_Roster.pdf | ||
| A.07.23_W91236-18-B-0007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
FOR
CRANEY ISLAND
SPILLBOX # 4 REPLACEMENT
PORTSMOUTH, VIRGINIA
PREPARED
AND
ISSUED BY
DEPARTMENT OF THE ARMY
NORFOLK DISTRICT, CORPS OF ENGINEERS
WATERFIELD BUILDING
803 FRONT STREET
NORFOLK, VIRGINIA 23510-1096
NOVEMBER 2017
This page was intentionally left blank for duplex printing.
Craney Island - Spillbox #4 Replacement (FY17) CISB4FY17
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 31 29 MARINE CONCRETE
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 09 - FINISHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DIVISION 31 - EARTHWORK
31 00 01 EXCAVATION, FILLING AND BACKFILLING FOR SPILLBOX STRUCTURE
31 00 02 EXCAVATION, TRENCHING, AND BACKFILLING FOR OUTFALL PIPES
31 05 19 GEOTEXTILE USED FOR STABILIZATION
31 05 21 GEOGRID SOIL REINFORCEMENT
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 19 HYDROSEEDING
DIVISION 33 - UTILITIES
PROJECT TABLE OF CONTENTS Page 1
33 40 00 STORM DRAINAGE PIPE
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR
STRUCTURES
35 42 35 POLYMERIC MARINE FILTER MATTRESS
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 23.19 HOIST
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
APPENDICES
APPENDIX A - A SUBSURFACE EXPLORATION REPORT, BORING LOGS AND DMT
DATA
APPENDIX B - COMMANDER'S POLICY MEMORANDUM NUMBER WRD-01
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 DESCRIPTION OF CRANEY ISLAND DREDGE MATERIAL MAMANAGEMENT AREA
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 General
1.2.2 Project Description
1.2.3 Order of Work
1.2.3.1 Removal of the Existing Outfall Pipes
1.2.3.2 Partial Demolition of the Existing Spillbox #4
1.2.3.3 Installation of New Outfall Pipes for Spillbox #4
1.2.3.4 Construction of a New Free-Standing Spillbox #4
1.2.3.5 Construction of a Permanent Access Road
1.2.4 Location
1.2.5 Safety Requirements
1.3 TRANSPORTATION FACILITIES
1.3.1 Use of Roads
1.3.2 Tracked Vehicles
1.4 SPECIAL CONTRACTOR REQUIREMENTS
1.4.1 Coordination in Work Areas
1.4.1.1 Sharing of Roadways and Work Areas
1.4.1.2 Dike Raising Project
1.4.1.3 Work Hours Restrictions
1.4.1.4 Existing Utility Location
1.4.1.5 Digging Permits
1.4.1.6 Notification Prior to Excavation
1.5 TIME EXTENSION FOR UNUSUALLY SEVERE WEATHER
1.5.1 Schedule
1.5.2 Adverse Weather Records
1.5.3 Impacted Days
1.6 COORDINATION WITH THE USING AGENCY AND OTHER CONTRACTORS
1.7 HISTORICAL AND ARCHAEOLOGICAL FINDS
1.8 SUBCONTRACTS AND WORK COORDINATION
1.9 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
1.10 PROFIT
1.10.1 Weighted Guidelines
1.10.2 Weighted Values
1.10.2.1 Degree of Risk
1.10.2.2 Relative Difficulty of Work
1.10.2.3 Size of Job
1.10.2.4 Periods of Performance
1.10.2.5 Contractor's Investment
1.10.2.6 Assistance by Government
1.10.2.7 Subcontracting
1.11 BLASTING AND FIRES
1.12 CONTRACTOR QUALITY CONTROL RESPONSIBILITY
1.13 LIQUIDATED DAMAGES
SECTION 01 11 00 Page 1
1.14 PERFORMANCE BOND
1.15 DAMAGE TO THE WORK
1.16 PROTECTION OF EXISTING CONDITIONS AND NEW WORK
1.17 PRE-BID SITE VISIT
1.18 WARRANTY
1.19 LAYOUT OF WORK
1.19.1 Established Project Controls
1.19.2 Layout
1.19.3 Survey
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 DESCRIPTION OF CRANEY ISLAND DREDGE MATERIAL MAMANAGEMENT AREA
The Craney Island Dredged Material Management Area (CIDMMA) is a 2,500 acre confined dredged material disposal site located at the north end of the town of Portsmouth near Norfolk, Virginia. CIDMMA serves as a long-term disposal site for material dredged from the rivers, channels and ports in the Norfolk Harbor area. By 2010, the site had received over 253 million cubic yards of dredged material. The heights of the dikes are being raised to increase the site's storage capacity. The site is divided into three large storage cells that are contained by compacted soil dikes that average 30 to 40 feet high. The top of the dikes serve as roadways and are interconnected. The site is a peninsula that is approximately 2 miles wide times 2 miles long that extends into the Norfolk Harbor. The south end includes access roads, the USACE office, and the Contractor's laydown yard.
Access to the site is limited and must be approved by the site's USACE office. A permanent crew of USACE personnel maintains the roads, dikes and associated structures. The island is a known nesting area for protected birds during the March 1 through August 15 period which may cause delays and relocation of work.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 General
The Contractor shall provide construction services, including personnel, transportation, mobilization/demobilization, equipment, and materials required in connection with the services described in this Scope of Work.
The services shall be performed in accordance with the technical and special provisions contained herein. Services not specifically described herein are nevertheless required if they can be identified as an item commonly a part of normally expected and/or professional grade work of a comparable nature. The work shall be performed in accordance with the Contract, manufacturer's recommendations, and state building codes.
1.2.2 Project Description
The six spillboxes found on or near the west side dikes are used to drain clarified water from the three holding cells down to an outfall structure that drains into the Norfolk Bay using four 36-inch CMP pipes. A mix of water and dredge material is pumped into the cells from the east side dikes which then slowly deposits sediments as it drains east-to-west across the cells where clarified surface water can be drained from the cells though the spillboxes. There are two main designs for the existing spillboxes:
1) the older concrete and steel structures embedded in the dike walls facing the interior cells; and 2) the newer free standing steel structures installed in the sediment cells to permit drainage through all four spillbox sides. This contract includes: 1) the partial demolition of the existing spillbox and its four outfall pipelines; and 2) the construction of a new free-standing spillbox in the sediment cell and its four outfall pipelines.
SECTION 01 11 00 Page 3
There are two separate construction areas: 1) partial demolition of the existing Spillbox #4 which is embedded in the dike wall on the interior cell side and associated outfall pipelines in the north-west corner of the center cell; and 2) construction of a new free-standing Spillbox #4 just south of the existing spillbox and approximately 300' east from the main dike into the cell; this includes four new HDPE outfall pipes and a riprap outfall structure supported by marine filter mattresses. See Section 31 00 01 EXCAVATION, FILLING AND BACKFILLING FOR SPILLBOX STRUCTURES for information on construction of the new free-standing spillbox. See Section 31 00 02 EXCAVATION, TRENCHING AND BACKFILLING FOR OUTFALL PIPES for both the removal of the existing spillbox's outfall pipes and the installation of the new spillbox's outfall pipes.
Two Borrow Sites found at the north-east and south-east corners of Craney contain layers of material from different dredging operations near the Norfolk Harbor which the Government has been mixing into blended mixtures that will be used for construction. The top of the material is around the same elevation as the adjoining dikes' roadways. The Contractor is to excavate and haul material from this site that is deemed satisfactory impervious fill or select fill for placement on the dike. Impervious fill will be used as backfill material for the dike center core at both sites:
site of removal of the existing Spillbox #4 pipelines and site of placement of the new Spillbox #4 pipelines. Select fill will be used for construction of an acces road ot the new Spillbox #4. Sufficient dredge materials are available at the borrow areas to complete construction.
1.2.3 Order of Work
The partial demolition of the existing spillbox and its outfall pipelines may be performed concurrently with the construction of the new spillbox and its new outfall pipelines.
The general work requirements for this project are listed below in no particular order and are not inclusive of all work included in this contract and that may be incidental to meeting contract requirements.
1.2.3.1 Removal of the Existing Outfall Pipes
The four existing 36" CMT pipelines extend from the bay side of the dike and through the dike where they connect into the existing spillbox located on the interior dike wall and facing the pond.
a. Clear and grub the dike area that will be excavated to remove the existing pipelines;
b. Excavate to expose the four existing 36" CMT pipelines by either sloping back the dike material and/or using sheeting/shoring as per approved Excavation plan;
c. Remove and dispose of the existing four 36" CMT pipes. The rock that surrounded the pipelines may be left in place and mixed back into the dike material.
d. Remove any remaining pipe connections into the concrete spillbox wall and prepare for future plugging of the holes with concrete.
e. Backfill the entire excavated area to match existing contours including the area where the pipes were removed with impervious material at
SECTION 01 11 00 Page 4 the dike core.
f. Rebuild portions of perimeter roads that were removed during excavation as per drawings.
g. Hydroseed the disturbed areas on dike slopes but not where the roadways exist.
1.2.3.2 Partial Demolition of the Existing Spillbox #4
a. Prepare the area around the existing spillbox's concrete wall and the interior cell side metal framework to provide access to the wall's four pipe openings, including installing the weir boards to above the water level in the cell.
b. Install concrete plugs in the four pipe wall openings and associated work as shown in the drawings.
c. Remove the horizontal steel walkways and associated handrails on the pond side of the spillbox .
c. Backfill the exterior dike side of the concrete wall during dike reconstruction.
d. Backfill the interior cell side of the concrete wall between the weir boards and the wall as shown in the drawings.
1.2.3.3 Installation of New Outfall Pipes for Spillbox #4
Four new 36" HDPE pipelines will extend from the bay, through the dike, and then will be embedded in the Government constructed temporary access road between the interior dike slope to the new spillbox and then through the spillbox wall. As placement of the pipe in the temporary road will affect construction work for the spillbox structure, Contractor is to schedule this work to meet construction requirements.
a. Clear and grub the dike area that will be excavated to install four new pipelines;
b. Excavate to expose the dike area required for the placement of four new 36" HDPE pipelines by either sloping back the dike material and/or using sheeting/shoring as per approved Excavation plan;
c. Install four new 36" HDPE pipelines as shown in the drawings.
d. Backfill to match existing contours across the dike area with either compacted structural fill or impervious fill as per the drawings.
e. Construct riprap outfall structure at the end of new pipeline as shown in the drawings.
f. Rebuild portions of perimeter road that were removed during excavation as per drawings.
g. Hydroseed disturbed areas of the dike except where roadways exist.
1.2.3.4 Construction of a New Free-Standing Spillbox #4
The free-standing spillbox will be built in the center cell approximately
SECTION 01 11 00 Page 5
300 feet from the interior edge of the perimeter dike. The Government has built a temporary access road to this site from the dike edge using on-site fill material which ends in a temporary pad at the spillbox site. In order to install new outfall pipes this temporary access road shall be excavated and then backfilled upon completion of pipe installation. The Contractor is responsible for scheduling his work to meet construction requirements.
a. Excavate and stabilize the sides of a pit that extends 20 feet beyond the edge of the new concrete foundation pad as per approved Excavation Plan
b. Install reinforced foundation materials to the edges of the pit as shown in drawings
c. Construct concrete foundation pad
d. Build steel frame spillbox as per drawings
e. Install steel access gangway from the north side of the spillbox to the newly constructed access road dike.
f. Install wood slats (weir boards) into the appropriate slots on all four sides of the spillbox up to the current water/sediment level
g. Partially remove sediment/cofferdam walls used to control water access into the spillbox area during construction as per agreement with Contracting Officer.
1.2.3.5 Construction of a Permanent Access Road
New permanent access road is to provide Government personnel an access to the new spillbox. The road extends from the interior edge of the dike to the north side of the spillbox where a steel gangway provides an access to the spillbox. The access road is constructed on top of dredge sediment.
a. Construct a permanent access road using select fill that has been excavated from the Borrow Sites and hauled to the work site as per drawings
b. Hydroseed the slopes but not the roadway area.
1.2.4 Location
The work is located at the Craney Island Dredged Material Management Area which is located at the north end of the town of Portsmouth, Virginia on a peninsula extending into the Norfolk Harbor. Craney Island is directly west of downtown Norfolk, VA. The exact location is shown on the plans.
The USACE office is at the south-east corner of the site at: 4599 River Shore Road, Portsmouth, VA 23703 and can be contacted at 757-201-7605.
Access to the site is limited by fencing and access gates and requires USACE approval.
1.2.5 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1. Use of appropriate safety equipment is mandatory and not limited to hard hats, safety vests, and safety-toed boots. Contractor is responsible for daily clean up and restoration of the work and office trailer areas once the contract is complete.
SECTION 01 11 00 Page 6
1.3 TRANSPORTATION FACILITIES
The Facility is served by a secondary unpaved roads around the perimeter with two connecting cross roads. Road(s) within the Facility that the Contractor proposes to be used shall be subject to prior approval of the Facility authorities. Haul and connecting roads used by Contractor shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be deemed necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition before demobilization from the site.
All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor. The condition of the construction access route roadways shall be documented in writing and supplemented with pictures and video. The report shall be submitted to the Contracting Officer prior to starting the construction. Any existing roads, structures, or utilities damaged by moving equipment and materials to the construction site and during construction shall be repaired and/or replaced by the Contractor at no additional cost to the government.
1.3.1 Use of Roads
Hard-surfaced paved and unpaved roads from major and primary municipal roads serve the exterior side of the site. The movement of all vehicles shall be confined to the roads designated and shall comply with traffic regulations. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations.
The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights.
Speed limits and traffic controls shall be observed.
1.3.2 Tracked Vehicles
Tracked vehicles shall not be allowed on Craney Island service roads except for the immediate work site where they are to be used for construction.
1.4 SPECIAL CONTRACTOR REQUIREMENTS
1.4.1 Coordination in Work Areas
1.4.1.1 Sharing of Roadways and Work Areas
During the period of this contract, in addition to Government personnel and equipment working at the site, other contractors may be on the island for the construction of other features of work that is on or adjacent to the site being accomplished under this contract. This work includes the pumping of new dredge material into the storage cells using pipelines from the bay; and dike, borrow area and road work. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other Contractors.
Should there be any conflict between these limits, it shall be brought to the attention of the Contracting Officer (CO) and the CO's decision shall be final.
SECTION 01 11 00 Page 7
1.4.1.2 Dike Raising Project
The dikes surrounding the three sediment containment cells at Craney Island Dredged Materials Management Area (CIDMMA) are slowly being raised to increase the site's dredged material storage capacity. Currently, the three containment areas (also known as "ponds") are slowly approaching maximum capacity. The dikes are slowly being raised under a separate contract which may require coordination with this spillbox contract.
1.4.1.3 Work Hours Restrictions
The Contractor shall limit work hours and activities to normal construction work hours and shall adhere and comply with local ordinances. Work occurring on Sunday or outside these prescribed hours is not allowed without prior written approval from the Contracting Officer. At least 2 days prior notice to the desired day is required. There is very limited existing lighting of the dike roadways and work areas and any work after sunset will require Contractor supplied light plants.
1.4.1.4 Existing Utility Location
Existing utilities must be located before doing any digging work on Facility. The Contractor shall be responsible to contact Miss Utility, obtain all necessary existing utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of his work. It shall be the responsibility of the Contractor to contact Miss Utilities at 1-800-552-7001 for locating commercial utilities 48 hours prior to digging operations.
1.4.1.5 Digging Permits
As the Government manages this site, they are responsible for obtaining all digging and/or site permits, including associated locating and marking services, in accordance with local and The Commonwealth of Virginia's requirements. The Contractor is not required to obtain additional permits for the work included in this contract.
1.4.1.6 Notification Prior to Excavation
Notify the Contracting Officer at least five days prior to starting excavation work at each of the main construction sites. Contractor is responsible for marking all utilities.
1.5 TIME EXTENSION FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
SECTION 01 11 00 Page 8
c. All awards or extensions for time shall be at the sole discretion of the Contraction Officer or their representative.
1.5.1 Schedule
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays as part of all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON A FIVE (5) DAY
WORK WEEK
JAN FEB MAR APR MAY JUNE JUL AUG SEP OCT NOV DEC
CRANEY 10 9 9 6 6 7 8 7 5 7 9 9
1.5.2 Adverse Weather Records
Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
1.5.3 Impacted Days
The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month); shall be calculated chronologically from the first to the last day in each month; and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, as listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)" of Section 00 72 00 Contract Clauses.
1.6 COORDINATION WITH THE USING AGENCY AND OTHER CONTRACTORS
During the period of this contract, in addition to Government personnel working at the site, other contractors may be in force for the construction of other features of work on or adjacent to the site being accomplished under this contract. This work includes the pumping of new dredge material into the storage cells using pipelines from the bay; and dike, borrow area and road work. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other Contractors. Should there be any conflict between these limits, it shall be brought to the attention of the Contracting Officer (CO) and the CO's decision shall be final. Also, prior to the completion of work under this contract, members of the Using Agency may be performing work or occupying facilities on or adjacent to the area, including working at the Government Office and Equipment Yard. The Contractor shall arrange his plant and shall schedule and perform this work so as to effectively cooperate with all other contractors and Government agencies.
SECTION 01 11 00 Page 9
1.7 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the applicable clauses of the contract.
1.8 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.
b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.
d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.9 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.
1.10 PROFIT
For modifications to this Craney Dike Construction contract, profit must be calculated using the Weighted Guidelines method.
SECTION 01 11 00 Page 10
1.10.1 Weighted Guidelines
Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value
Degree of Risk 20% Relative difficulty of work 15% Size of Job 15% Period of performance 15% Contractor's investment 05% Assistance by Government 05% Subcontracting 25% Total 100%
1.10.2 Weighted Values
Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
1.10.2.1 Degree of Risk
Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, the amount of labor included in costs, and whether the negotiation is before or after performance of work.
1.10.2.2 Relative Difficulty of Work
If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
1.10.2.3 Size of Job
All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
1.10.2.4 Periods of Performance
Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs
SECTION 01 11 00 Page 11 not to exceed 30 days. No weight where additional time not required.
1.10.2.5 Contractor's Investment
To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
1.10.2.6 Assistance by Government
To be weighted from .12 to .03 on the basis of average to above average.
Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.
1.10.2.7 Subcontracting
To be weighted inversely proportional to the amount of subcontracting.
Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.11 BLASTING AND FIRES
Blasting and fires will not be permitted for this project.
1.12 CONTRACTOR QUALITY CONTROL RESPONSIBILITY
The Contractor is fully responsible for the management and supervision associated with Quality Control of all construction work included in this contract. The Government is responsible for Quality Assurance by reviewing all Contractor documentation and work has been completed to meet contract requirements.
1.13 LIQUIDATED DAMAGES
Refer to contract clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) in Section 00 72 00 General Conditions.
1.14 PERFORMANCE BOND
The Contractor's Performance Bond shall remain effective throughout the construction period.
a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.
c. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner.
Written verification will follow oral instructions. Failure of the
SECTION 01 11 00 Page 12
Contractor to respond will be cause for the Contracting Officer to proceed against the Contractor.
d. Refer to contract Clause 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (FAR 52.228-15 in Section 00 72 00 General Conditions.
1.15 DAMAGE TO THE WORK
The responsibility for damage to any part of the permanent work shall be as set forth in contract Clause PERMITS AND RESPONSIBILITIES of Section 00 72 00 CONTRACT CLAUSES in Volume 1. However, if, in the judgement of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES in Section 00 72 00 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as noted herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
Refer to contract Clause 52.236-7 PERMITS AND RESPONSIBILITIES (FAR 52.236-7 in Section 00 72 00 General Conditions.
1.16 PROTECTION OF EXISTING CONDITIONS AND NEW WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements," the Contractor shall:
a. Perform excavation, transportation, and construction operations in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Perform excavation, transportation, and construction operations in such a manner to prevent injury and damage to new work. Repair or replace portions of new work which have been altered during construction operations, at no additional cost to the government.
c. Repair or replace portions of existing conditions which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing surfaces and vegetation adjacent to the new work shall be in a condition equal to or better than that which existed before new work started.
1.17 PRE-BID SITE VISIT
Prior to the submission of bids, bidders are highly encouraged to visit the project site location to become familiar with the project requirements.
This contract includes a Government led site visit during the solicitation period. Failure to visit the project site will not disqualify a bid;
SECTION 01 11 00 Page 13 however, the bidder is required to comply with the terms and conditions of the resultant Contract by reason of such failure. A failure to inspect the site shall not constitute grounds for a claim after Contract award.
1.18 WARRANTY
The Contractor shall provide a minimum of one-year warranty on the materials and workmanship from the date of the Government's acceptance of the work.
1.19 LAYOUT OF WORK
Read this paragraph in conjunction with contract Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00 72 00 CONTRACT CLAUSES.
1.19.1 Established Project Controls
The Government has established monuments around the work site(s). Each monument is represented in the contract drawings by a designated number.
1.19.2 Layout
From the monuments, control data and elevations established by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modification to the contract work.
1.19.3 Survey
The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and materials, all labor as may be required in laying out any part of the work from the monuments, control data and elevations established by the Government. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks established by the Contracting Officer until authorized by remove them, and if such marks are destroyed by the Contractor or through their negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 14
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONTRACTOR WORK REQUIREMENTS
1.3.1 Personnel Restrictions
1.3.2 Transportation Restrictions
1.3.3 Methane Gas Hazard
1.3.4 Security and Public Safety of Work Areas
1.3.5 Noise Control and Abatement
1.4 PHYSICAL DATA
1.4.1 Physical Conditions Information
1.4.2 Site Related Weather Conditions
1.5 INSPECTION
1.5.1 General Insection Requirements
1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.6.1 Costs
1.6.2 Rentals
1.6.3 Data
1.7 ENVIRONMENTAL LITIGATION
1.8 PARTNERING
1.9 CONTRACTOR ACCESS AND USE OF PREMISES
1.9.1 Activity Regulations
1.9.1.1 Subcontractors and Personnel Contacts
1.9.2 Working Hours
1.9.3 Work Outside Regular Hours
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
Safety And Lighting Plan; G
For evening/night work, Contractor must submit and have a pre-approved safety and lighting plan specific to the planned work.
1.3 CONTRACTOR WORK REQUIREMENTS
All activities at Craney Island Dredged Material Management Area shall be conducted in accordance with Norfolk District Regulation DR 1130-2-4 that is available for review at the Craney Island Reservation Office. Point of contact for review of the Regulation or to visit the site is Carlos Quinones , telephone (757) 484-1021.
1.3.1 Personnel Restrictions
Personnel working at Craney Island are limited to the immediate site areas where work is to be performed and shall not enter buildings or facilities not involved in the work. All employees of the Contractor will be subject to all rules and regulations of the Craney Island Dredged Material Management Area which pertain to personnel.
1.3.2 Transportation Restrictions
Roads within the Craney Island reservation, if proposed to be used by the Contractor, shall be subject to prior approval of the Facility Manager and such roads, if used, shall be maintained throughout construction and restored to as good condition as existed prior to their use. Other roads
SECTION 01 14 00 Page 2 may be used only with the approval of the Facility Manager. The Contractor shall keep all roads free of mud and other foreign materials resulting from his operations. All temporary construction shall be removed and the affected areas restored to their original condition. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles and vehicles with flashing lights. Craney Island speed limits and traffic controls shall be observed. All costs for the use of existing transportation facilities, and for the removal of temporary construction and subsequent restoration, shall be borne by the Contractor.
1.3.3 Methane Gas Hazard
Low pressure subterranean methane gas is continuously present at Craney Island. Open-flame, including smoking, and operation of spark producing devices will not be allowed within 50 feet of earthwork operations.
1.3.4 Security and Public Safety of Work Areas
The work areas are not accessible to the general public; however, the Contractor is informed the Government will not undertake to exclude the public or restrict public access to the work areas during the work. The Contractor shall be solely responsible for protection of the public at all times for the duration of the contract and fully comply with the provisions of OSHA safe working practices and the Safety and Accident Prevention requirements of these specifications.
1.3.5 Noise Control and Abatement
The Contractor shall employ the use of properly installed and maintained mufflers, silencers, and manufacturer's recommended sound suppressors on all plant, machinery, and equipment used on this work. The use of sound signals such as whistles, horns, or bells shall not be used if two-way radio communication can accomplish the required function.
1.4 PHYSICAL DATA
1.4.1 Physical Conditions Information
The physical conditions indicated on the drawings and in the specifications are the result of site investigations and surveys. Information and data furnished or referred to below is furnished for the Contractor's information; however, it shall be expressly understood that the Government will not be responsible for any interpretation or conclusion drawn from this information or data by the Contractor.
1.4.2 Site Related Weather Conditions
Complete weather forecasts, records and reports may be obtained from the National Weather Service in Wakefield, Virginia, telephone (757) 899-4200, Menu selection service or operator assisted as applicable. The Contractor shall satisfy himself as to the hazards likely to arise from the weather conditions during the contract period.
1.5 INSPECTION
1.5.1 General Insection Requirements
The presence of the construction representative shall not relieve the
SECTION 01 14 00 Page 3
Contractor of responsibility for the proper execution of the work in accordance with the specifications.
1.6 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.6.1 Costs
Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule", Region II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.
1.6.2 Rentals
Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36 substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase or sale-leaseback arrangements will be determined using the schedule except that rental costs leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.
1.6.3 Data
When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet". By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.
1.7 ENVIRONMENTAL LITIGATION
If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall
SECTION 01 14 00 Page 4 be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the "Suspension of Work" clause of this contract. The period of such suspension, delay, or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof. The term "environmental litigation" means, a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
1.8 PARTNERING
In order to most effectively accomplish this contract, the Government is willing to form a cohesive partnership with the Contractor. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done correctly, within budget, and on time. This partnership would be bilateral in make-up and partnership will be totally voluntary. Any cost associated with effectuating this partnership will be agreed to by all parties and will be shared equally with no change in contract price.
1.9 CONTRACTOR ACCESS AND USE OF PREMISES
1.9.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.9.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.9.2 Working Hours
Regular working hours are between 6.00 a.m. and 6.00 p.m., Monday through Friday, excluding Government holidays.
1.9.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer and in accordance with the requirements of EM 385-1-1. For evening/night work, Contractor must submit and have a pre-approved safety and lighting plan specific to the planned work.
SECTION 01 14 00 Page 5
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 6
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
08/15
PART 1 GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 LUMP SUM PAYMENT ITEMS
1.3.1 Payment for Line Item No. 0001 - Full Mobilization and
Demobilization
1.3.1.1 Full Mobilization
1.3.1.2 Full Demobilization
1.3.1.3 Unit of Measure
1.3.2 Payment for Line Item No. 0002 - Partial Demolition of Existing
Spillbox #4
1.3.2.1 Unit of Measure
1.3.3 Payment for Line Item No. 0003 - Construction of New Spillbox #4
1.3.3.1 Unit of Measure
1.4 UNIT PRICE PAYMENT ITEMS
1.4.1 Line Item No. 0004 - Purchase and Install 36" HDPE Pipe
1.4.1.1 Payment
1.4.1.2 Measurement
1.4.1.3 Unit of Measure
1.4.2 Stone by Unit Cost Line Items
1.4.2.1 Line Item No. 0005 - Purchase and Place VDOT #3 Aggregate.
1.4.2.1.1 Payment
1.4.2.1.2 Measurement
1.4.2.1.3 Unit of measure
1.4.2.2 Line Item No. 0006 - Purchase and Place VDOT Class II
Riprap.
1.4.2.2.1 Payment
1.4.2.2.2 Measurement
1.4.2.2.3 Unit of Measure
1.4.2.3 Line Item No. 0007 - Purchase and Place VDOT #57 Stone.
1.4.2.3.1 Payment
1.4.2.3.2 Measurement
1.4.2.3.3 Unit of Measure
1.4.2.4 Line Item No. 0008 - Purchase and Place VDOT #21A Dense
Graded Aggregate
1.4.2.4.1 Payment
1.4.2.4.2 Measurement
1.4.2.4.3 Unit of Measure
1.4.3 Line Item No. 0009 - Purchase and Place Structural Fill
1.4.3.1 Payment
1.4.3.2 Measurement
1.4.3.3 Unit of Measure
1.5 MISPLACED MATERIAL
1.6 MONTHLY PARTIAL PAYMENTS
SECTION 01 22 00.00 10 Page 1
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00.00 10 Page 2
SECTION 01 22 00.00 10