W91236-17-B-0015-0001.pdf
PDF 88 KB Posted
- Solicitation number
- W91236-17-R-0027
About this file
Amendment 0001
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Craney Island Eastw ard Expansion, Main Dike, Dredging and Debris Removal located in Portsmouth, Virginia is amended as follow s: (SEE
CONTINUATION PAGES)
NOTE: Offeror must acknow ledge receipt of ALL amendment(s) by the date specif ied in the proposal (or as amended). FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS
(FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123617B0015
X 9B. DATED (SEE ITEM 11)
01-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Aug-2017
CODE
USA ENGINEER DISTRICT, NORFOLK
803 FRONT STREET
NORFOLK VA 23510-1096
W91236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123617B0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION 00 11 00 - SF 1442 AND CLIN SCHEDULE
SUMMARY OF CHANGES
SECTION 00 21 00 - INSTRUCTIONS, CONDITIONS & NOTICES TO OFFERORS
The following Delivery Schedule item for CLIN 0004 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
150 dys. ADC 27,000 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616 FOB: Destination
E4L8W20
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
164 dys. ADC 27,000 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0005 has been changed from:
CAGE
150 dys. ADC 720 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
164 dys. ADC 720 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0006 has been changed from:
CAGE
150 dys. ADC 30,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
178 dys. ADC 30,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0007 has been changed from:
150 dys. ADC 810 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
178 dys. ADC 810 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0008 has been changed from:
CAGE
150 dys. ADC 31,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
192 dys. ADC 31,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0009 has been changed from:
CAGE
150 dys. ADC 840 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
192 dys. ADC 840 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0010 has been changed from:
CAGE
150 dys. ADC 31,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
206 dys. ADC 31,500 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following Delivery Schedule item for CLIN 0011 has been changed from:
CAGE
150 dys. ADC 840 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
CAGE
206 dys. ADC 840 GEOSPATIAL SERVICES SECTION
GREGGORY WILLIAMS
US ARMY ENGR DIST NORFOLK ATTN:
CENAO-TS-OG 8
TREET
NORFOLK VA 23510-1096
(757) 201-7616
The following have been modified:
1. PROJECT DESCRIPTION
Craney Island Eastward Expansion, Main Dike, Dredging and Debris Removal located in Portsmouth, Virginia The Craney Island Eastward Expansion, Main Dike, Dredging and Debris Removal Project will consist of mechanical dredging of the top layer of soil material, including debris, to a depth of 4 feet below the mudline within a portion of the footprint of the future main dike of the Craney Island Eastward Expansion project. The contractor shall separate the debris using screens as the material is loaded into scows. The contractor shall deposit the dredged material hydraulically within the Craney Island Dredged Material Management Area (CIDMMA). The contractor shall dispose the debris off-site at a location as determined by the contractor that meets local, state and federal regulations. Within the base bid work area the estimated volume to be removed is 284,000 cubic yards and the estimated weight of debris is 7,825 tons. The work potentially could include up to 4 optional areas, each estimated at a volume of 31,500 cubic yards and weight of debris of 840 tons.
For the base contract bid items, begin performance within 15 calendar days and complete all work within 150 calendar days of receipt of Notice to Proceed (NTP). If optional items are awarded, the period of performance will include an additional 14 calendar days for each optional item.
Should the total quantity of material to be paid for and actually removed from the dredging site under this contract exceed the quantity from the bidding schedule, additional time will be allowed at the rate of one day for each 2,500 cubic yards in excess of the estimated quantity.
The Contractor shall comply with the provisions of EM 385-1-1. If the Contractor is a currently accepted participant in the Dredging Contractors of America (DCA)/United States Army Corps of Engineers (USACE) Dredging Safety Management Program (DSMP), as determined by the DCA/USACE Joint Committee, and holds a current valid Certificate of Compliance for both the Contractor Program and the Dredge(s) to be used to perform the work under this contract, the Contractor may, in lieu of the submission of an Accident Prevention Plan (APP),
(1) make available for review, upon request, the Contractor’s current Safety Management System (SMS) documentation,
(2) submit to the Contracting Officer the current valid Company Certificate of Compliance for it’s SMS,
(3) submit the current dredge(s) Certificate of Compliance based on third party audit, and submit for review and acceptance, site-specific addenda to the SMS as specified in the solicitation.
The full text of EM 385-1-1 can be accessed at:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
2. BIDDER QUESTIONS AND COMMENTS
All questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than COB August 17, 2017, in order that they may be given consideration or actions taken prior to receipt of offers.
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W91236-17-B-0015 The Bidder Inquiry Key is: 9M7V6G-AB7HKN
The Bidder Inquiry System will be unavailable for new inquires 7 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.projnet.org/projnet
3. BID EVALUATION AND AWARD
The Government will evaluate bids in response to this solicitation based upon the Total Evaluated Price without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government considering only price and the price-related factors specified elsewhere in the solicitation. The Government may reject any or all bids and/or waive informalities or minor irregularities in bids received.
The Government will evaluate offers for award purposes by adding the total price for all optional items to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the optional items. Optional items, if exercised, will be awarded in accordance with clause 52.217-7.
4. AWARD TO RESPONSIBLE OFFEROR
To be determined responsible, a bidder must –
a) Have adequate financial resources to perform the contract, or the ability to obtain them;
b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;
c) Have a satisfactory performance record. A prospective contractor shall not be determined responsible or non-responsible solely on the basis of a lack of relevant performance history;
d) Have a satisfactory record of integrity and business ethics;
e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors);
f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations
In accordance with FAR Part 9.1, responsibility will be determined, prior to award, by the Contracting Officer through the performance of a pre-award survey or utilizing information from a previous pre-award survey and/or any performance data available. The apparent low bidder may be required to show that he has the necessary capital, experience, and owns or can procure the necessary plant or other resources to commence the work at the time prescribed in the specifications and thereafter to prosecute and complete the work safely and satisfactorily within the time specified. The below information will be requested of the apparent low offeror. This information is not required to be responsive to the invitation for bid.
a) Banking Information to include Branch/Location, Point of Contact and Telephone Number.
Please insure the Bank is prepared to provide necessary information regarding average balances in your operating accounts, lines of credit and credit history.
b) Current commitments and expected dates of completion
5. EVIDENCE OF AUTHORITY TO SIGN OFFERS
Evidence of the authority of individuals signing offers to submit firm offers on behalf of the offeror is required except where the offer is signed, and shows that it is so signed, by: the President, Vice-President, or Secretary of an incorporated offeror; a partner in the case of a partnership; or the owner in the case of a sole proprietorship. Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.
6. PREAWARD SAFETY CONFERENCE
a. Where an apparent low bidder, in performance of contracts during the previous three-year period, incurred one or more accidents, or where, in the opinion of the Contracting Officer, there is any question regarding this compliance with any safety or accident prevention requirement, such bidder, on request of the Contracting Officer prior to any award under this solicitation, shall attend a conference with representatives of the Contracting Officer to discuss any such accidents or non-compliance, the reason for their occurrence, and measures which will be taken to preclude any recurrence thereof.
b. Information elicited at this conference will be used by the Contracting Officer, in conjunction with other information obtained in a preaward survey, in determining the bidder's responsibility.
c. The items discussed, the preventive measures considered, and any conclusions reached in this conference shall be recorded in minutes of the meeting, which shall be authenticated by the signatures of representatives of the bidder and the Contracting Officer, and any procedures noted therein as agreed upon shall become an obligation of the bidder, along with all other safety and accident prevention requirements of the contract, if award is made to him.
7. INSPECTION OF THE SITE
Prospective bidders are invited to visit the site of the work in order to acquaint themselves as to site conditions and other problems incident to the prosecution of the work. Arrangements for inspection of the site shall be made through the Office the Area Engineer identified in the clause 52.236-27, entitled "SITE VISIT
(CONSTRUCTION)."
8. SUBCONTRACTING PLAN (CONSTRUCTION)
If the offeror is a large business and the offer amount exceeds $1,000,000.00, he shall submit a subcontracting plan within three (3) working days of being notified (either verbally or in writing) that he is the apparent low bidder or is otherwise in line for award. The subcontracting plan shall be reviewed and approved by the Contracting Officer prior to award.
9. INCURRING COSTS
The Government is not liable for any costs incurred by the offeror submitting an offer in response to this solicitation.
10. AGENTS
Offers signed by an Agent must be made in the name of the Principal and must be accompanied by evidence of said Agent’s authority to act on behalf of its Principal.
11. UNBALANCED BIDS
Any offer which is materially unbalanced as to prices for the Base Items and the Optional Items may be rejected as non-responsive or otherwise not considered for award. An unbalanced offer is one which is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
12. UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The contractor shall not accept instructions issued by any person, employed by the U.S. Government or otherwise, other than the Contracting Officer or the Authorized Representative of the Contracting Officer acting within the limits of his/her authority as defined in the Designation of Authority letter. A copy of the Designation of Authority letter will be furnished to the contractor at time of contract award.
SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
The purpose of Amendment 0001 is to:
1. The following Bidder Inquiries and corresponding answers are hereby incorporated:
Inquiry ID: 7110491:
Q: We request an extension to the bidder questions deadline in order to more thoroughly examine the provided plans and specifications.
A: Bid Opening remains 31 August 2017 at 2:00 PM EST.
Inquiry ID: 7110770:
Q: Please provide geotechnical data in Appendices D, E, F, G & H as they are not included in the posted documents.
A: Please see the attached Appendices D, E, F, G & H.
2. The delivery Schedules for CLINs 0004, 0005, 0006, 0007, 0008, 0009, 0010, and 0011 have changed. Please see summary of changes for full details.
3. Section 00 21 00 – Instructions, Conditions & Notices to Offerors:
3a. Insert “Calendar” after 14 in Project Description. The last sentence in the first paragraph of item 1.
PROJECT DESCRIPTON now reads, “If optional items are awarded, the period of performance will include an additional 14 calendar days for each optional item.”
3b. 2.500 cubic yards is replaced with 2,500 cubic yards in the second paragraph of item 1. PROJECT
DESCRIPTION.
4. Please note that the Bid Opening remains 31 August 2017 at 2:00 PM EST. Offeror must acknowledge receipt of ALL amendment(s) by the date specified in the proposal (or as amended). FAILURE TO ACKNOWLEDGE
AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER
IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF
PROPOSALS (FAR 15.208).
5. Document “CIEE_Stage_1A, _FINAL_Specification, _7-6-17” deleted in its entirety and replaced with document “CIEE Stage 1A, FINAL Specifications, 7-12-17”
SECTION 00 73 10 - SUPPLEMENTAL CONTRACT REQUIREMENTS
CLIN 0004
The CLIN description has changed from Mech. Removal of First 4 Ft. Option 1 to Mech. Removal of First 4 Ft. Option 1A.
CLIN 0005
The CLIN description has changed from Mech. Removal of Debris Option 2 to Mech. Removal of Debris Option 1B.
CLIN 0006
The CLIN description has changed from Mech. Removal of First 4 Ft. Option 3 to Mech. Removal of First 4 Ft. Option 2A.
CLIN 0007
The CLIN description has changed from Mech. Removal of Debris Option 4 to Mech. Removal of Debris Option 2B.
CLIN 0008
The CLIN description has changed from Mech. Removal of First 4 ft. Option 5 to Mech. Removal of First 4 ft. Option 3A.
CLIN 0009
The CLIN description has changed from Mech. Removal of Debris Option 6 to Mech. Removal of Debris Option 3B.
CLIN 0010
The CLIN description has changed from Mech. Removal of First 4 Ft. Option 7 to Mech. Removal of First 4 Ft. Option 4A.
CLIN 0011
The CLIN description has changed from Mech. Removal of Debris Option 8 to Mech. Removal of Debris Option 4B.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .