Text version
W26GLG00228044
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ) CONTRACT FOR MAINTENANCE DREDGING AT VARIOUS LOCATIONS, JAMES RIVER, VIRGINIA is amended as follow s.
1. The Bid Schedule is clarif ied as show n on attached.
2. Specif ications are amended as show n on attached.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-May-2010
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91236-10-B-0011
X 9B. DATED (SEE ITEM 11)
16-Apr-2010
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-May-2010
CODE
USA ENGINEER DISTRICT, NORFOLK
CONTRACTING OFFICE
803 FRONT STREET
NORFOLK VA 23510-1096
W91236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91236-10-B-0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SECTION 00 11 00 - SOLICITATION, OFFER & AWARD
BID SCHEDULE
BID SCHEDULE - AMENDMENT
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 1 Lump Sum
SCHEDULE I - BASE BID
FFP
FOB: Destination
MILSTRIP: W26GLG00228044
PURCHASE REQUEST NUMBER: W26GLG00228044
TOTAL (Items 0001 through 0011)
UNIT UNIT PRICE MAX AMOUNT
0002 1 Lump
OPTION SCHEDULE II - OPTION YEAR 1
FOB: Destination
TOTAL (Items 1001 through 1011)
UNIT UNIT PRICE MAX AMOUNT
0003 1 Lump
OPTION SCHEDULE III - OPTION YEAR 2
FOB: Destination
TOTAL (Items 2001 through 2011)
TOTAL BASE AND ALL OPTION YEARS $______________________________
BID SCHEDULE ADDENDUM
BASE YEAR
ITEM DESCRIPTION QUANTITY UNIT U/P AMOUNT
0001 Mobilization and
Demobilization 1 JB ___LS___
0002 Mobilization and Demobilization of Additional Pipeline 1 JB ___LS___ _______
0003 Dredging – Lower and Middle James River Shoals 400,000 CY
0004 Dredging Upper James River Shoals, Richmond Deepwater Terminal 50,000 CY
0005 Dredging Upper James River Shoals, Richmond Deepwater Terminal to Hopewell 30,000 CY
0006 Dredging Upper James River Shoals, Richmond Harbor to Richmond
Deepwater Terminal 100,000 CY
0007 Transportation of Plant and Equipment from Designated Mobilization Point to First Dredging Area and Subsequent Areas 100 RIV MI ___ _ __________
0008 Installation and Removal of Additional Pipeline 12,000 LF ___ __________
0009 Dredging – Upper James River Shoals at Pipeline
Lengths Exceeding 7,500 linear feet 25,000 CY ________ __________
0010 Dredging – Lower James
Lengths exceeding 10,000 linear feet 150,000 CY ________ __________
0011 Contracting Officer Directed
Standby Time 1 DAY ___LS___ __________
TOTAL ESTIMATED BID AMOUNT – BASE YEAR $_________
OPTION YEAR 1
ITEM DESCRIPTION QUANTITY UNIT U/P AMOUNT
1001 Mobilization and
1002 Mobilization and of Additional Pipeline 1 JB ___LS___ __________ 1003 Dredging – Lower and Middle James River Shoals 400,000 CY
1004 Dredging Upper James River Shoals, Richmond Deepwater Terminal 50,000 CY
1005 Dredging Upper James River Shoals, Richmond Deepwater Terminal to Hopewell 30,000 CY
1006 Dredging Upper James River Shoals, Richmond Harbor to Richmond Deepwater Terminal 100,000 CY
1007 Transportation of Plant and Equipment from Designated Mobilization Point to First Dredging Area and Subsequent Areas 100 RIV MI ___ __________
1008 Installation and Removal of
1009 Dredging – Upper James
7,500 linear feet 25,000 CY ________ __________
1010 Dredging – Lower James
10,000 linear feet 150,000 CY ________ __________
1011 Contracting Officer
Standby Time 1 DAY ___LS___ __________
TOTAL ESTIMATED BID AMOUNT – OPTION YEAR 1 ___________
OPTION YEAR 2
ITEM DESCRIPTION QUANTITY UNIT U/P AMOUNT
2001 Mobilization and
2002 Mobilization and of Additional Pipeline 1 JB ___LS___ ____________
2003 Dredging – Lower and Middle James River Shoals 400,000 CY ___
2004 Dredging Upper James River Shoals, Richmond Deepwater Terminal 50,000 CY ___
2005 Dredging Upper James River Shoals, Richmond Deepwater Terminal to Hopewell 30,000 CY
2006 Dredging Upper James River Shoals, Richmond Harbor to Richmond
Deepwater Terminal 100,000 CY
2007 Transportation of Plant and Equipment from Designated Mobilization Point to First Dredging Area and Subsequent Areas 100 RIV MI ______ ___________
2008 Installation and
Removal of
2009 Dredging – Upper James River Shoals at Pipeline
7,500 linear feet 25,000 CY ________ _________
2010 Dredging – Lower James
10,000 linear feet 150,000 CY ________ _________
2011 Contracting Officer
Standby Time 1 DAY ___LS___ _________
TOTAL ESTIMATED BID AMOUNT – OPTION YEAR 2 $__________
TOTAL ESTIMATED BID AMOUNT –
BASE + ALL OPTION YEARS $ ____
SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS
AMENDED SPECIFICATIONS
TECHNICAL SPECIFICATIONS:
1. TECHNICAL SPECIFICATIONS, second page, Table of Contents:
a. Change title of SECTION 35 20 40 to read “HISTORIC BANK HEIGHT
INFORMATION FROM PREVIOUS JAMES RIVER TASK ORDER
DREDGING CONTRACTS”
2. SECTION 01 14 00, SPECIAL WORK CONDITIONS:
a. Page 7, paragraph 1.5.4, second sentence, delete the word “within” and insert “a minimum of” in its place.
b. Page 9, paragraph 1.6.7, delete the third sentence and replace with “The boundary points shall be physically located with 1 inch diameter steel pipe and marked with orange flagging or orange buoys, as directed by the Contracting Officer, prior to dredging operations.”
3. SECTION 01 22 00, MEASUREMENT AND PAYMENT:
a. Page 4, paragraph 1.2.3, change title of paragraph to read “Payment Item No.
0004, 1004 and 2004 Dredging Upper James River Shoal, Richmond Deepwater Terminal”
b. Page 4, paragraph 1.2.3, change title of paragraph to read “Payment Item No.
0005, 1005 and 2005 Dredging Upper James River Shoals, Richmond Deepwater Terminal to Hopewell”
c. Page 5, paragraph 1.2.4, change title of paragraph to read “Payment Item No.
0006, 1006 and 2006 Dredging Upper James River, Richmond Harbor to Richmond Deepwater Terminal”
4. SECTION 01 35 00, GOVERNMENTAL SAFETY REQUIREMENTS:
a. Page 5, delete paragraph 1.5.1.2 in its entirety.
5. SECTION 01 35 26, GOVERNMENTAL SAFETY REQUIREMENTS:
a. Page 8, SECTION 1.12, delete the word “PLAN” from the title.
6. SECTION 35 20 40, HISTORIC BANK HEIGHT INFORMATION FROM
PREVIOUS JAMES RIVER TASK ORDER DREDGING CONTRACTS AND MAPS
OF CHANNELS ON JAMES RIVER:
a. Page 1, change title of SECTION to read “HISTORIC BANK HEIGHT
INFORMATION FROM PREVIOUS JAMES RIVER TASK ORDER
DREDGING CONTRACTS”
b. Page 1, Section Table of Contents, PART 1 GENERAL, change title of contents of 1.1 to read “Historic Bank Height Information and Payment Clarification”
c. Page 2, paragraph 1.1, change title of paragraph to read “Historic Bank
Height Information and Payment Clarification”
d. Page 2, paragraph 1.1, delete the fifth sentence in its entirety.
7. SECTION 35 20 23, DREDGING:
a. Page 4, paragraph 3.1.2, delete the third sentence and replace with “The markings shall be physically located with minimum 1 inch diameter steel pipe marked with orange flagging or other appropriate markings, as approved by the Contracting Officer, prior to dredging operations, placed in the immediate work areas only, and promptly removed as the work areas are accepted by the Government.”