Ontonagon, Port Wing, and Cornucopia Maintenance Dredging Federal contract opportunity
Solicitation number
W911XK26BA021
Issued by
Department of the Army Corps of Engineers Engineering District Detroit

About this file

This is an Abstract of Bids for a construction solicitation issued by the US Army Corps of Engineers, Contracting Branch, Detroit District.

The solicitation W911XK26BA021 covers dredging services at three locations: Ontonagon, Port Wing, and Cornucopia, Michigan. The contract was issued on March 17, 2026, with bids opened on April 21, 2026. The work is structured as a base contract plus five options. Each work location includes mobilization/demobilization costs and dredging tasks with tiered cubic yard (CY) pricing—pricing decreases per CY for quantities exceeding specified thresholds. Base dredging at Port Wing includes 11,600 CY total; Ontonagon includes 10,400 CY; and Cornucopia (Outer) includes 5,500 CY. Options include additional dredging at Ontonagon (5,100 CY), Cornucopia (Inner) with 3,200 CY, and Port Wing (4,800 CY). Six offerors submitted bids: Viking Marine Construction, LLC; Dean Marine and Excavating, Inc.; King Co., Inc.; Jones Fish Hatcheries & Distributors, LLC; Walsh Service Solutions, LLC; and Stimulant Marine Construction, LLC. All offerors provided bid security of 20% of their total bid amounts and acknowledged one amendment. Bid totals for base and all options ranged from approximately $1.64 million to $3.39 million. Per the solicitation, price evaluation was conducted on the base contract only, in accordance with IAW FAR 52.217-3.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES

03/17/2026 4/21/2026 1 1

9. OFFERS

0001 Mobilization & Demobilization 1 JA $ 572,962.00 $ 572,962.00 $ 532,003.50 $ 532,003.50 $ 814,740.35 $ 814,740.35 $ 850,000.00 $ 850,000.00 $ 1,315,505.10 $ 1,315,505.10 $ 1,381,275.58 $ 1,381,275.58 $ 395,000.00 $ 395,000.00

0002AA FIRST 4,500 CY 4,500 CY $ 23.10 $ 103,950.00 $ 17.27 $ 77,715.00 $ 16.17 $ 72,765.00 $ 19.00 $ 85,500.00 $ 15.76 $ 70,920.00 $ 35.73 $ 160,785.00 $ 26.00 $ 117,000.00 0002AB OVER 4,500 CY 7,100 CY $ 15.03 $ 106,713.00 $ 16.11 $ 114,381.00 $ 16.17 $ 114,807.00 $ 19.00 $ 134,900.00 $ 15.76 $ 111,896.00 $ 31.45 $ 223,295.00 $ 22.00 $ 156,200.00

0003AA FIRST 5,500 CY 5,500 CY $ 16.63 $ 91,465.00 $ 17.27 $ 94,985.00 $ 16.17 $ 88,935.00 $ 19.50 $ 107,250.00 $ 16.68 $ 91,740.00 $ 27.20 $ 149,600.00 $ 25.00 $ 137,500.00 0003AB OVER 5,500 CY 4,900 CY $ 11.85 $ 58,065.00 $ 16.11 $ 78,939.00 $ 16.17 $ 79,233.00 $ 19.50 $ 95,550.00 $ 16.68 $ 81,732.00 $ 36.46 $ 178,654.00 $ 20.00 $ 98,000.00

0004AA FIRST 2,500 CY 2,500 CY $ 28.38 $ 70,950.00 $ 17.27 $ 43,175.00 $ 16.17 $ 40,425.00 $ 23.50 $ 58,750.00 $ 33.37 $ 83,425.00 $ 40.20 $ 100,500.00 $ 26.00 $ 65,000.00 0004AB OVER 2,500 CY 3,650 CY $ 18.76 $ 68,474.00 $ 16.11 $ 58,801.50 $ 16.17 $ 59,020.50 $ 23.50 $ 85,775.00 $ 33.37 $ 121,800.50 $ 48.95 $ 178,667.50 $ 22.00 $ 80,300.00

$ 1,072,579.00 $ 1,000,000.00 $ 1,269,925.85 $ 1,417,725.00 $ 1,877,018.60 $ 2,372,777.08 $ 1,049,000.00

0005AA FIRST 1,300 CY 1,300 CY $ 23.97 $ 31,161.00 $ 17.27 $ 22,451.00 $ 16.17 $ 21,021.00 $ 11.00 $ 14,300.00 $ 15.76 $ 20,488.00 $ 75.58 $ 98,254.00 $ 23.00 $ 29,900.00 0005AB OVER 1,300 CY 4,400 CY $ 12.55 $ 55,220.00 $ 16.11 $ 70,884.00 $ 16.17 $ 71,148.00 $ 11.00 $ 48,400.00 $ 15.76 $ 69,344.00 $ 33.50 $ 147,400.00 $ 20.00 $ 88,000.00

$ 86,381.00 $ 93,335.00 $ 92,169.00 $ 62,700.00 $ 89,832.00 $ 245,654.00 $ 117,900.00

0006AA FIRST 2,800 CY 2,800 CY $ 15.25 $ 42,700.00 $ 17.27 $ 48,356.00 $ 16.17 $ 45,276.00 $ 12.00 $ 33,600.00 $ 16.68 $ 46,704.00 $ 17.55 $ 49,140.00 $ 20.00 $ 56,000.00 0006AB OVER 2,800 CY 2,500 CY $ 10.87 $ 27,175.00 $ 16.11 $ 40,275.00 $ 16.17 $ 40,425.00 $ 12.00 $ 30,000.00 $ 16.68 $ 41,700.00 $ 39.30 $ 98,250.00 $ 18.00 $ 45,000.00

$ 69,875.00 $ 88,631.00 $ 85,701.00 $ 63,600.00 $ 88,404.00 $ 147,390.00 $ 101,000.00

Option 3 Mobilization & Demobilization:

Cornucopia (Inner)

1 JA $ 329,543.00 $ 329,543.00 $125,000.00 $ 125,000.00 $ 308,626.20 $ 308,626.20 $ 100,000.00 $ 100,000.00 $ 362,045.03 $ 362,045.03 $ 210,000.00 $ 210,000.00 $ 52,000.00 $ 52,000.00

0008AA FIRST 1,000 CY 1,000 CY $ 123.77 $ 123,770.00 $57.00 $ 57,000.00 $ 16.17 $ 16,170.00 $ 68.00 $ 68,000.00 $ 40.10 $ 40,100.00 $ 46.88 $ 46,880.00 $ 26.00 $ 26,000.00 0008AB OVER 1,000 CY 2,200 CY $ 75.35 $ 165,770.00 $50.00 $ 110,000.00 $ 16.17 $ 35,574.00 $ 68.00 $ 149,600.00 $ 40.10 $ 88,220.00 $ 46.88 $ 103,136.00 $ 25.00 $ 55,000.00

$ 619,083.00 $ 292,000.00 $ 360,370.20 $ 317,600.00 $ 490,365.03 $ 360,016.00 $ 133,000.00

0009AA FIRST 1,200 CY 1,200 CY $ 20.52 $ 24,624.00 $17.27 $ 20,724.00 $ 16.17 $ 19,404.00 $ 11.00 $ 13,200.00 $ 15.76 $ 18,912.00 $ 37.22 $ 44,664.00 $ 23.00 $ 27,600.00 0009AB OVER 1,200 CY 3,900 CY $ 10.90 $ 42,510.00 $16.11 $ 62,829.00 $ 16.17 $ 63,063.00 $ 11.00 $ 42,900.00 $ 15.76 $ 61,464.00 $ 22.90 $ 89,310.00 $ 20.00 $ 78,000.00

$ 67,134.00 $ 83,553.00 $ 82,467.00 $ 56,100.00 $ 80,376.00 $ 133,974.00 $ 105,600.00

0010AA FIRST 2,600 CY 2,600 CY $ 16.71 $ 43,446.00 $17.27 $ 44,902.00 $ 16.17 $ 42,042.00 $ 12.00 $ 31,200.00 $ 16.68 $ 43,368.00 $ 37.79 $ 98,254.00 $ 20.00 $ 52,000.00 0010AB OVER 2,600 CY 2,200 CY $ 12.00 $ 26,400.00 $16.11 $ 35,442.00 $ 16.17 $ 35,574.00 $ 12.00 $ 26,400.00 $ 16.68 $ 36,696.00 $ 22.33 $ 49,126.00 $ 18.00 $ 39,600.00

$ 69,846.00 $ 80,344.00 $ 77,616.00 $ 57,600.00 $ 80,064.00 $ 133,974.00 $ 91,600.00 $ 912,319.00 $ 637,863.00 $ 698,323.20 $ 557,600.00 $ 829,041.03 $ 1,021,008.00 $ 549,100.00 $ 1,984,898.00 $ 1,637,863.00 $ 1,968,249.05 $ 1,975,325.00 $ 2,706,059.63 $ 3,393,785.08 $ 1,598,100.00

NO. 3

A. OFFEROR:

King Co., Inc.

B. BID SECURITY (TYPE AND AMOUNT)

20%

TOTAL AMOUNT OF ALL OPTIONS

TOTAL AMOUNT OF BASE AND ALL OPTIONS

E. UNIT PRICE

F. ESTIMATED

AMOUNT

Option 2 Dredging: Port Wing

Base Dredging: Ontonagon

TOTAL AMOUNT OF OPTION 1

Option 1 Dredging: Ontonagon

TOTAL AMOUNT OF BASE:

Option 3 Dredging: Cornucopia (Inner)

TOTAL AMOUNT OF OPTION 2

TOTAL AMOUNT OF OPTION 3

7A. ITEM

NO

Base Dredging: Port Wing

7C. EST.

QUANTITY

Base Dredging: Cornucopia (Outer)

5. PROJECT TITLE

US Army Corp of Engineers Contracting Branch, Detroit District

Ontonagon, Port Wing, and Cornucopia MD

X

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

8. GOVERNMENT ESTIMATE

NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)

Matthew Mcduffie, Contracting Officer

SIGNATURE DATE SIGNED

ABSTRACT OF BIDS - Construction

1. SOLICITATION NUMBER

W911XK26BA021

4. ISSUING OFFICE

NO. 1 NO. 2

A. OFFEROR:

C.Reasonable Contract (With Profit)

B. Reasonable Contract (Without Profit)

Dean Marine and Excavating, Inc.Viking Marine Construction, LLC

B. BID SECURITY (TYPE AND AMOUNT)

20%

C. AMENDMENTS ACKNOWLEDGED

20%

YES YES

B. BID SECURITY (TYPE AND AMOUNT)

C. AMENDMENTS ACKNOWLEDGED

A. Hired Labor

TOTAL AMOUNT OF OPTION 5

6. Number of Amendments Issued

A. OFFEROR:

D. UNIT PRICE

E. ESTIMATED

AMOUNT

D. UNIT PRICE

E. ESTIMATED

AMOUNT7B. DESCRIPTION OF OFFERED ITEM

D. UNIT

B. BID SECURITY (TYPE AND AMOUNT)

20%

Option 4 Dredging: Ontonagon

TOTAL AMOUNT OF OPTION 4

Option 5 Dredging: Port Wing

C. AMENDMENTS ACKNOWLEDGED

YES

D. UNIT PRICE

E. ESTIMATED

AMOUNT

C. AMENDMENTS ACKNOWLEDGED

YES

D. UNIT PRICE

E. ESTIMATED

AMOUNT

NO. 5

A. OFFEROR:

Walsh Service Solutions, LLC

B. BID SECURITY (TYPE AND AMOUNT)

20%

C. AMENDMENTS ACKNOWLEDGED

YES

D. UNIT PRICE

E. ESTIMATED

AMOUNT

NO. 4

A. OFFEROR:

Jones Fish Hatcheries & Distributors, LLC

C. AMENDMENTS ACKNOWLEDGED

YES

D. UNIT PRICE

E. ESTIMATED

AMOUNT

NO. 6

A. OFFEROR:

Summerset Marine Construction, LLC

B. BID SECURITY (TYPE AND AMOUNT)

20%