Abstract of Bids - W911XK25BA013 Duluth Superior Harbor Maintenance Dredging (FINAL).pdf
PDF 671 KB Posted
- Attached to
- Duluth Superior Harbor Maintenance Dredging
- Solicitation number
- W911XK25BA013
About this file
This document is an Abstract of Bids for the Duluth Superior Harbor Maintenance Dredging project (Solicitation W911XK25BA013) issued by the US Army Corps of Engineers Detroit District. The bid abstract shows Roen Salvage as the offeror, with a comprehensive pricing breakdown for dredging services across multiple areas and options. The base bid and six additional options cover dredging in different locations, including Wisconsin Point and Erie Pier Confined Disposal Facility (CDF) placement areas, with quantities ranging from 500 to 23,100 cubic yards (CY) per area.
The total pricing demonstrates significant cost variations, with the base bid totaling $3,713,265 and the government estimate at $7,945,200. The bid includes a mobilization and demobilization line item of $778,040, and pricing structures that differentiate between first quantities and quantities over specified thresholds for each dredging area. The solicitation was issued on 25 April 2025, opened on 29 May 2025, and includes three amendments. The total combined base and option pricing reaches $10,933,000, representing a comprehensive dredging maintenance project for the Duluth-Superior Federal navigation channel.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE OF PAGES
1 1
DATE SIGNED
7A. ITEM
NO
7B. DESCRIPTION OF OFFERED
ITEM
7C. EST.
QUANTIT
Y
D.
UNIT
E. UNIT PRICE F. ESTIMATED AMOUNT E. UNIT PRICE
F. ESTIMATED
AMOUNT
E. UNIT PRICE
F. ESTIMATED
AMOUNT
BASE
0001 Mobilization and Demobilization 1 Job $778,040.00 $778,040.00 $2,808,900.00 $2,808,900.00
0002AA First 8,000 CY 8,000 CY $33.65 $269,200.00 $84.00 $672,000.00
0002AB Over 8,000 CY 16,800 CY $30.20 $507,360.00 $57.00 $957,600.00
0003AA First 1,800 CY 1,800 CY $25.85 $46,530.00 $45.00 $81,000.00
0003AB Over 1,800 CY 3,900 CY $23.05 $89,895.00 $45.00 $175,500.00
0004AA First 11,900 CY 11,900 CY $24.40 $290,360.00 $28.00 $333,200.00
0004AB Over 11,900CY 18,200 CY $23.00 $418,600.00 $28.00 $509,600.00
0005AA First 1,900CY 1,900 CY $27.50 $52,250.00 $37.00 $70,300.00
0005AB Over 1,900CY 5,500 CY $23.30 $128,150.00 $37.00 $203,500.00
0006AA First 23,100CY 23,100 CY $28.90 $667,590.00 $61.00 $1,409,100.00
0006AB Over 23,100CY 16,100 CY $28.90 $465,290.00 $45.00 $724,500.00
$3,713,265 $7,945,200.00
Option 1
0007AA First 7,400CY 7,400 CY $24.65 $182,410.00 $27.00 $199,800.00
0007AB Over 7,400 CY 12,200 CY $23.00 $280,600.00 $27.00 $329,400.00
$463,010.00 $529,200.00
Option 2
0008AA First 13,200CY 13,200 CY $24.30 $320,760.00 $41.00 $541,200.00
0008AB Over 13,200 CY 19,900 CY $22.95 $456,705.00 $41.00 $815,900.00
$777,465.00 $1,357,100.00
Option 3
0009AA First 500 CY 500 CY $29.95 $14,975.00 $44.00 $22,000.00
0009AB Over 500 CY 2,000 CY $23.70 $47,400.00 $44.00 $88,000.00
$62,375.00 $110,000.00
Option 4
0010AA First 5,800 CY 5,800 CY $26.80 $155,440.00 $27.00 $156,600.00
0010AB Over 5,800 CY 14,700 CY $23.30 $342,510.00 $27.00 $396,900.00
$497,950.00 $553,500.00
Option 5
0011AA First 1,800 CY 1,800 CY $28.90 $52,020.00 $36.00 $64,800.00
Over 1,800 CY 6,700 CY $23.25 $155,775.00 $36.00 $241,200.00
$207,795.00 $306,000.00
Option 6
0012AA First 900 CY 900 CY $26.20 $23,580.00 $44.00 $39,600.00
0012AB Over 900 CY 2,100 CY $23.10 $48,510.00 $44.00 $92,400.00
$72,090.00 $132,000.00
Total of Base plus All Options $5,793,950.00 $10,933,000.00
Total Amount for Option 6
Required Dredging - Dredge Area 4 (Erie Pier CDF Placement)
Total Amount for Option 4
Total Amount for Option 3
Option 4 Dredging - Dredge Area 11 (Erie Pier CDF Placement)
Option 5 Dredging - Dredge Area 23 (Erie Pier CDF Placement)
Option 6 Dredging - Dredge Area 26 (Erie Pier CDF Placement)
Total Amount for Option 5
Total Amount for Option 1
Option 1 Dredging - Dredge Area 3B (Erie Pier CDF Placement)
Option 2 Dredging - Dredge Area 3C (Erie Pier CDF Placement)
Option 3 Dredging - Dredge Area 8 (Erie Pier CDF Placement)
Total Amount for Option 2
Required Dredging - Dredge Area 1 (Wisconsin Point Placement)
Required Dredging - Dredge Area 2 (Erie Pier CDF Placement)
Required Dredging - Dredge Area 3A (Erie Pier CDF Placement)
Required Dredging - Dredge Area 6 (Wisconsin Point Placemant)
Total Amount of Base
Yes
6. NUMBER OF AMENDMENTS ISSUED
C. REASONABLE CONTRACT (Including Profit) C. Amendments Acknowledged C. Amendments Acknowledged
3 Yes
A. HIRED LABOR
A. OFFEROR: A. OFFEROR:
Roen Salvage
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
Duluth Superior Harbor Maintenance Dredging
(Check A, B, or C and complete D, E, and F) NO. 1 NO. 2 x B. REASONABLE CONTRACT (Without Profit) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount)
4. ISSUING OFFICE I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
US Army Corps of Engineers Detroit District
Michelle Barr, Contracting Officer
SIGNATURE
ABSTRACT OF BIDS - IFB
1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED
W911XK25BA013 25 April 2025 29 May 2025
| 2025-05-30T13:59:18-0400 | |
| BARR.MICHELLE.LEE.1232355901 |
File details come from the government source that posted it. Updated .