W911XK21Q0004 0003.pdf

PDF 602 KB Posted

Attached to
Detroit Area Office Debris Pile Removal
Solicitation number
W911XK21Q0004
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Detroit Area Office Debris Pile Removal

This amendment is issued to:

1. Provide an additional site visit for interested contractors to be conducted on March 18, 2021 at 2:00 PM EST. Onsite person of contact to sign up for the site visit is located in the revised performance w ork statement below .

2. All terms, conditions, requirements and clauses remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK21Q0004

X 9B. DATED (SEE ITEM 11)

08-Mar-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0003

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Mar-2021

CODE

U.S.ARMY ENGINEER DISTRICT, DETROIT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

W911XK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK21Q0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT FOR REMOVING DEBRIS PILE

US Army Corps of Engineers – Detroit Area Office

1. LOCATION:

Detroit Area Office Facilities located at Historic Fort Wayne. 6309 W. Jefferson, Detroit, MI 48209.

2. DESCRIPTION OF WORK:

The work area for this contract is behind building No. 404. All material in the pile; concrete, asphalt (bituminous pavement pieces) and dirt shall be removed from Detroit Area Office facility. This project consists of providing all labor, equipment, and materials for:

Provide dump trucks to haul away the debris pile: The work consists of trucking the pile of debris on government property offsite, to a disposal of the Contractor’s choosing. The Corps of Engineers will provide an excavator with an Operator to load the Contractor’s trucks. Jefferson Street is the entry to the government property where the pile is located. Contractor may use either the front entrance of Historical Fort Wayne or the easement service drive along the adjacent property. Both entrances allow for a width of twelve (12) feet to clear the security booth and metal fence. No damage to curb and gutter nor fence shall be allowed. If damage occurs to entry gate or roadway it is the responsibility of the Contractor to replace damaged items back to their original condition. All vehicles transporting debris material must be legal on the road following Michigan DOT guidelines as: coved load and adhering to weight restrictions. All vehicles on government property must have back-up alarms as a safety requirement. Government shall furnish the heavy equipment with operators to load the contracted vehicles. Prior to hauling the material offsite, the Contractor must notify the Government a few days before scheduling their trucks to coordinate excavating pile with their trucking hauling. The responsibility of the destination of the disposal of the debris pile is the Contractor’s. Lab work on the debris pile characteristics have been taken and is available on request. This waste is subject to corrective action under USEPA 40CFR280.

Cleanup of the project site where the debris pile was placed is required: The work consists of removing the debris pile to the existing grade or the asphalt pavement beneath the pile. Only the debris pile is to be removed and no other area surrounding the pile. The quantity of material may be more or less than the estimated quantity of 4,000 cubic yards. There is no variations of estimated quantity granted. It is suggested that scheduling a site visit ensures the Contractor with the amount and type of debris to be removed.

These sections describe the method of required work for the removing the debris waste pile from USACE property:

Concrete Removal: Remove all the pieces of concrete including parking blocks. There are some concrete pieces with metal reinforcement attached to the concrete; that must be removed.

Asphalt Removal: Broken pieces of bituminous are in the debris pile and must be removed. There is an asphalt pavement beneath the pile in disrepair; if excavated this pavement shall be removed as well. The contract requirement is to remove all evidence of debris removed from the site.

Miscellaneous debris: Stones and dirt make-up a large portion of the debris pile. The following are items in the pile that must be removed: Fence posts encased in concrete footings; Grass growing on the pile;

Chain-link cyclone fence pieces that are attached to fence posts, not sheets of chain-link fence; must be removed. There are no steel cables in the pile. There are no appliances or machinery in the pile. If an item in the pile is questioned, a USACE representative will note the item and discuss it with the Contracting Officer; to determine if the item conforms to the materials described in the contract. The item must fall into the categories discussed in this document, otherwise the Contractor is not liable to remove it. Only inert material and items mentioned are to be removed.

Vegetation: Vegetation consists of trees, brush, and growing grass. All roots, trees and vegetation in the pile must be removed.

3. SAFETY:

The Contractor shall ensure that all activities of the Contractor and/or their sub-contractors meet or exceed the COE Safety and Health Requirements Manual EM 385-1-1 dated 30 November 2014 and any applicable OSHA regulations.

4. SECURITY:

All personnel employed by the contractor in the performance of the services specified in this contract or any representative of the contractor entering the work area shall conform and comply with all applicable U.S. Army Corps of Engineers, facility access, security policies and procedures (provided by government representative).

Pre-screening of contractor candidates via E-verify Program: The contractor must pre-screen candidates using the E-verify Program (http://www.dhs.gov/E-verify) website to meet the established employment eligibility requirements.

The vendor must ensure that all contractors working on the site have two valid forms of Government issued identification prior to entering the information in E-verify. The vendor must ensure the correct information is entered into the E-verify system. A verification sheet for each verified/eligible contractor candiadate must be provided to the COR no later than 3 business days after the initial contract award. (The purpose of using E-verify is to ensure all contractors are U.S. citizens or documented foreign citizens with authority to work in the United States of America). The COR will forward the verification sheets to the USACE, Detroit District Security Office for validation.

Security Checks - all employees must carry pictured identification at all times. They must show I.D. upon request by the Government personnel. The contractor's employees will be subject to such additional checks as may be deemed necessary to ensure that no violation of security rules has occurred.

5. SITE VISIT:

A site visit to the Detroit Area Office is recommended but not required. The site visit will be held on 15 MAR 2021 at 2:00 PM EST. Contractors who decide to attend the site visit need to have the following personal protective equipment: steel toed boots, high visibility safety vest and eye protection. Any contractors interested in attending the site visit needs to reach out to the onsite person of contact Rich Sallans by either phone or email: (313) 938-1892 or Rich.Sallans@usace.army.mil.

An additional site visit will be held on 18 March 2021 at 2:00 PM EST for any other contractors that would like to see the debris pile. Contractors who decide to attend the additional site visit need to have the following personal protective equipment: steel toed boots, high visibility safety vest and eye protection. Any contractors interested in attending the site visit needs to reach out to the onsite person of contact Rich Sallans by either phone or email: (313) 938-1892 or Rich.Sallans@usace.army.mil.

END of Performance Work Statement

(End of Summary of Changes)