Question and Answer Replace failed section of DAO perimeter security fence

W911XK19T0003

Question: I was planning to attend the prebid walk through next week for the Fort Wayne perimeter hardening project in Detroit. Please let me know if there is any form or sign in procedure I need to perform.

Answer: The only requirement from the DAO is all potential bidders must report to the Office of the Area Engineer in Building 414 prior to the walk-through. Any sign-in, etc. will be performed from there. Any questions asked and any answers provided during the site visit will be noted and distributed to all potential bidders.