Abstract_W911XK18B0012.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
FY18 Maintenance Dredging Channels of Lake St. Clair, MI
Solicitation number
W911XK18B0012
Issued by

About this file

BID ABSTRACT W911XK18B0012 6 SEP 2018

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ABSTRACT OF OFFERS - CONSTRUCTION1. SOLICITATION NUMBER2. DATE ISSUED3. DATE OPENEDPAGEOF PAGES
W911XK18B00128/2/189/6/1811
4. ISSUING OFFICEI CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
US Army Corps of Engineers
Detroit DistrictBruce M. Walrad, Contracting Officer
SIGNATUREDATE SIGNED
5. PROJECT TITLE8. GOVERNMENT ESTIMATE9. OFFERS
FY17 Maintenance Dredging Channels of Lake St. Clair(Check A, B, or C and complete D, E, and F)NO. 1NO. 2
A. HIRED LABORA. OFFEROR:A. OFFEROR:
Ryba Marine ConstructionLuedtke Engineering
XB. REASONABLE CONTRACT (Without Profit)B. BID SECURITY (Type and Amount)B. BID SECURITY (Type and Amount)
N/AN/A
6. NUMBER OF AMENDMENTS ISSUEDC. REASONABLE CONTRACT (Including Profit)C. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
011
7A.
ITEM NO7B. DESCRIPTION OF OFFERED ITEM7C. QUANTITYD. UNITE. UNIT PRICEF. ESTIMATED AMOUNTD. UNIT PRICEE. ESTIMATED AMOUNTD. UNIT PRICEE. ESTIMATED AMOUNT
BASE CONTRACT
0001Mob & DeMob1JOB$242,072.00$242,072.00$156,000.00$156,000.00$190,000.00190,000.00
0002Required Dredging between STA. 711+00 to STA.

672+50 to 27.5 ft. below L.W.D.

0002AAFirst 12,500 Cubic Yards12,500CY$17.85$223,125.00$13.50$168,750.00$18.50231,250.00
0002ABOver 12,500 Cubic Yards18,300CY$12.83$234,789.00$12.00$219,600.00$17.00311,100.00
TOTAL AMOUNT OF BASE$699,986.00$544,350.00$732,350.00
OPTION ONE (1)
0003OPTION 1 - Dredging between STA. 672+50 to STA.

660+00 to 27.5 ft. below L.W.D.

0003AAFirst 4,700 Cubic Yards4,700CY$17.2681,122.0013.5063,450.00$11.00$51,700.00
0003ABOver4,700 Cubic Yards6,500CY$12.45$80,925.00$11.00$71,500.00$11.00$71,500.00
TOTAL AMOUNT OF OPTION ONE (1)$162,047.00$134,950.00$123,200.00
OPTION TWO (2)
0004OPTION 2 - Dredging between STA. 660+00 to STA.

649+00 to 27.5 ft. below L.W.D.

0004AAFirst 4,900 Cubic Yards4,900CY$17.1183,839.0013.5066,150.00$11.00$53,900.00
0004ABOver 4,900 Cubic Yards6,200CY$12.51$77,562.00$11.00$68,200.00$11.00$68,200.00
TOTAL AMOUNT OF OPTION TWO (2)$161,401.00$134,350.00$122,100.00

TOTAL AMOUNT OF BASE PLUS OPTION (ALL ITEMS) $1,023,434.00 $813,650.00 $977,650.00