W56MES52817843
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY 16 M/D Ludington & Manistee Outer Harbors
This amendment is being issued to make changes to the bid schedule and specifications as outlined in the Amendment 1 summary of changes. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Mar-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK-16-B-0004
X 9B. DATED (SEE ITEM 11)
25-Feb-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Mar-2016
CODE
CONTRACTING BRANCH
USACE DETROIT DISTRICT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK-16-B-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 1
Amendment 1 FY16 Maintenance Dredging of Ludington & Manistee Harbors, Michigan
1. CHANGES TO BID SCHEDULE
A. ADD: Add line item TOTAL AMOUNT OF OPTION 6 $__________
2. CHANGES TO THE SPECIFICATIONS
A. 35 20 23 DREDGING, PARAGRAPH 1.14 ALLOWABLE PAY OVERDEPTH AND
SIDESLOPES
DELETE: Ludington Harbor - Option 3 Overdepth 2,000,000 cy.
REPLACE: Ludington Harbor - Option 3 Overdepth 2,000 cy.
Revised specifications will not be issued with this amendment.
END OF AMENDMENT
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been modified:
BID SCHEDULE
BID SCHEDULE
ITEM SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE TOTAL
0001 Mobilization & Demobilization 1 JA $ $
0002 Required Dredging Ludington Harbor Outer, MI to 28 ft. below L.W.D. between C.S. 28+00.1W and C.S. 7+36.9E
0002AA First 30,000 CY 30,000 CY $ $
0002AB Over 30,000 CY 18,000 CY $ $
TOTAL AMOUNT FOR LUDINGTON BASE $
0003 Required Dredging Manistee Harbor Outer, MI to 25 ft. below L.W.D. between C.S. 24+83.6W and C.S. 8+61.8W and to 23 ft. below L.W.D. between C.S. 8+61.8W and C.S. 0+00
0003AA First 20,000 CY 20,000 CY $ $
0003AB Over 20,000CY 21,000 CY $ $
TOTAL AMOUNT FOR MANISTEE BASE $
TOTAL AMOUNT OF LUDINGTON AND MANISTEE (BASE BID) $
Option 1
Dredging Ludington Harbor Outer, MI to 29 ft. below L.W.D. between C.S. 28+00.1W and C.S.
9+50W
0004AA First 8,000 CY 8,000 CY $ $
0004AB Over 8,000 CY 5,000 CY $ $
TOTAL AMOUNT OF OPTION 1 $
Option 2
Dredging Ludington Harbor Outer, MI to 30 ft. below L.W.D. between C.S. 28+00.1W and C.S.
9+50W
0005AA First 8,000 CY 8,000 CY $ $
0005AB Over 8,000 CY 5,000 CY $ $
TOTAL AMOUNT FOR OPTION 2 $
Option 3
Dredging Ludington Harbor Outer, MI to 31 ft. below L.W.D. between C.S. 28+00.1W and C.S.
9+50W
0006AA First 8,000 CY 8,000 CY $ $
0007AB Over 8,000 CY 5,000 CY $ $
TOTAL AMOUNT OF OPTION 3 $
Option 4
Dredging Manistee Harbor Outer, MI to 26 ft. below L.W.D. between C.S. 8+61.8W to C.S.
24+83.6W
0007AA First 8,000 CY 8,000 CY $ $
0007AB Over 8,000 CY 5,000 CY $ $
TOTAL AMOUNT OF OPTION 4 $
Option 5
Dredging Manistee Harbor Outer, MI to 27 ft. below L.W.D. between C.S. 8+61.8W to C.S.
24+83.6W
0008AA First 8,000 CY 8,000 CY $ $
0008AB Over 8,000 CY 5,000 CY $ $
TOTAL AMOUNT OF OPTION 5 $
Option 6
Install steel safety guardrail at Manistee Harbor revetment including ladders (2) with grab rails
(2) and swing gates (2).
1 JA $ $
TOTAL AMOUNT OF OPTION 6 $
TOTAL AMOUNT OF All OPTIONS $
TOTAL AMOUNT OF All ITEMS $
JA = Job
(End of Summary of Changes)