DATE SIGNED
7A. ITEM
NO 7B. DESCRIPTION OF OFFERED ITEM 7C. EST.
QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
0001 Mob & DeMob 1 JOB $240,993.00 $240,993.00 $133,000.00 $133,000.00 $415,600.00 $415,600.00
Base Dredging - Area 1 to 29.5' below L.W.D. between CS 24+00 to CS 27+88
0002AA First 20,000 Cubic Yards 20000.00 CY $30.17 $603,400.00 $28.95 $579,000.00 $26.50 $530,000.00
0002AB Over 20,000 Cubic Yards 39000.00 CY $20.56 $801,840.00 $28.95 $1,129,050.00 $22.75 $887,250.00
Base Dredging - Area 2 to 29.5 below L.W.D. between CS 217+00 (Course 5) to CS 16+73 (Course 6)
0003AA First 8,000 Cubic Yards 8,000 CY $38.89 $311,120.00 $28.95 $231,600.00 $33.60 $268,800.00
0003AB Over 8,000 Cubic Yards 24,000 CY $23.92 $574,080.00 $28.95 $694,800.00 $25.60 $614,400.00
TOTAL AMOUNT OF BASE BID $2,531,433.00 $2,767,450.00 $2,716,050.00
Option 1 Dredging to 29.5 below L.W.D. between CS 24+00 to CS 0+00
0004AA First 8,000 Cubic Yards 8,000 CY $25.04 $200,320.00 $27.75 $222,000.00 $18.35 $146,800.00
0004AB Over 8,000 Cubic Yards 16,000 CY $16.99 $271,840.00 $27.75 $444,000.00 $17.35 $277,600.00
TOTAL AMOUNT OF OPTION 1
BID
$472,160.00 $666,000.00 $424,400.00
Option 2 Dredging to 29.5 below L.W.D. between CS 0+00 to CS 27+88
0005AA First 8,000 Cubic Yards 8,000 CY $27.42 $219,360.00 $27.75 $222,000.00 $18.35 $146,800.00
0005AB Over 8,000 Cubic Yards 16,000 CY $18.63 $298,080.00 $27.75 $444,000.00 $17.35 $277,600.00
TOTAL AMOUNT OF OPTION 2
BID
$517,440.00 $666,000.00 $424,400.00
TOTAL AMOUNT OF ALL
OPTIONS $989,600.00 $1,322,000.00 $848,800.00
SUM TOTAL OF BID $3,521,033.00 $4,099,450.00 $3,564,850.00
B. REASONABLE CONTRACT (Without Profit)
C. REASONABLE CONTRACT (Including Profit)
B. BID SECURITY (Type and Amount) 20%
C. AMENDMENTS ACKNOWLEDGED
6. NUMBER OF AMENDMENTS ISSUED
FY15 Maintenance Dredging St. Mary's River
X dba Ryba Marine Construction Company
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
B. BID SECURITY (Type and Amount) 20%
C. AMENDMENTS ACKNOWLEDGED
A. HIRED LABOR
A. OFFEROR: MCM Marine Inc. A. OFFEROR: Morrish-Wallace Constructin Inc.
Robert W. Austin, Contractng Officer I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE
(Check A, B, or C and complete D, E, and F)
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER
W911XK-15-B-0005
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
NO. 1 NO. 2
US Army Corps of Engineers Detroit District
PAGE OF PAGES
2 2
A. ITEM
NO B. ESTIMATED QUANTITY C. UNIT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
0001 Mob & DeMob 1 $250,000.00 $250,000.00 $295,000.00 $295,000.00 $419,845.00 $419,845.00
Base Dredging - Area 1 to 29.5' below L.W.D. between CS 24+00 to CS 27+88
0002AA First 20,000 Cubic Yards 20000.00 $21.50 $430,000.00 $18.75 $375,000.00 $38.40 $768,000.00
0002AB Over 20,000 Cubic Yards 39000.00 $20.50 $799,500.00 $17.75 $692,250.00 $27.29 $1,064,310.00
0003 Base Dredging - Area 2 to 29.5 below L.W.D. between CS 217+00 (Course 5)
0003AA First 8,000 Cubic Yards 8,000 $23.50 $188,000.00 $25.25 $202,000.00 $51.12 $408,960.00
0003AB Over 8,000 Cubic Yards 24,000 $22.50 $540,000.00 $24.25 $582,000.00 $35.60 $854,400.00
TOTAL AMOUNT OF BASE BID $2,207,500.00 $2,146,250.00 $3,515,515.00
0004 Option 1 Dredging to 29.5 below L.W.D. between CS 24+00 to CS 0+00
0004AA First 8,000 Cubic Yards 8,000 $20.20 $161,600.00 $18.75 $150,000.00 $38.40 $307,200.00
0004AB Over 8,000 Cubic Yards 16,000 $20.20 $323,200.00 $17.75 $284,000.00 $27.05 $432,800.00
TOTAL AMOUNT OF OPTION 1 BID $484,800.00 $434,000.00 $740,000.00
0005 Option 2 Dredging to 29.5 below L.W.D. between CS 0+00 to CS 27+88
0005AA First 8,000 Cubic Yards 8,000 $20.20 $161,600.00 $18.75 $150,000.00 $38.40 $307,200.00
0005AB Over 8,000 Cubic Yards 16,000 $20.20 $323,200.00 $17.75 $284,000.00 $26.17 $418,720.00
TOTAL AMOUNT OF OPTION 2 BID $484,800.00 $434,000.00 $725,920.00
TOTAL AMOUNT OF ALL OPTIONS $969,600.00 $868,000.00 $1,465,920.00
SUM TOTAL OF BID $3,177,100.00 $3,014,250.00 $4,981,435.00
INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF
1419s for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
1. SOLICITATION NUMBER
W911XK-15-B-0005
4. OFFERS (Continued)
20% 20%
A. OFFEROR: White Lake Dock & Dredge Inc.
NO. 5NO. 3 NO. 4FY15 Maintenance Dredging St. Mary's River
B. BID SECURITY (Type and Amount)
20%
3. CONTRACT ITEMS
ABSTRACT OF OFFERS - CONSTRUCTION CONTINUATION
SHEET
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR: Luedtke Engineering Company
2. PROJECT TITLE
B. BID SECURITY (Type and Amount)
A. OFFEROR: Great Lakes Dock & Materials, LLC.
1 1
B. BID SECURITY (Type and Amount)
C. AMENDMENTS ACKNOWLEDGED
| Sheet1 |
| Sheet2 |
| 2015-03-11T11:02:54-0400 | |
| AUSTIN.ROBERT.WAYNE.JR.1186713296 |
File details come from the government source that posted it. Updated .