Bid_Abstract_By_Line_Item,_E.Branch,_GOM.pdf

PDF 140 KB Posted

Attached to
Replace Gate Operating Machinery, East Branch Clarion River Lake, Elk County, PA
Solicitation number
W911WN19B8009
Issued by

About this file

Bid Abstract on Bids Received from 9/6/19 Bid Opening (One "Responsive" Bid Received)

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9/6/2019

ITEM NO. LINE ITEM DESCRIPTION QTY U/M Unit Price Total Cost Unit Price Total Cost

0001 Reimbursement for Actual Performance and Payment Bonds Premiums 1 JOB $28,229.50 $28,229.50 $12,000.00 $12,000.00

0002 Digital Progress Images 10 SETS $686.28 $4,803.96 $650.00 $6,500.00 0003 Mobilization and Demobilization 1 JOB $256,715.26 $256,715.26 $580,000.00 $580,000.00 0004 Temporary Work Platform 1 JOB $259,000.27 $259,000.27 $145,000.00 $145,000.00 0005 Furnish and Install Roof Hatch 1 JOB $87,173.44 $87,173.44 $108,000.00 $108,000.00 0006 Replace Roofing, Center Control Tower 1 JOB

$51,755.72 $51,755.72 $67,700.00 $67,700.00 0007 Replace Gate No. 4 Operating

Machinery

1 JOB

$1,831,446.57 $1,831,446.57 $1,267,000.00 $1,267,000.00

TOTAL, BASE CONTRACT, ITEMS

0001 THROUGH 0007 $2,519,124.72 $2,186,200.00

1001 Reimbursement for Actual Performance and Payment Bonds Premiums 1 JOB $21,726.60 $21,726.60 $8,000.00 $8,000.00

1002 Digital Progress Images 1 SET $894.63 $894.63 $650.00 $650.00 1003 Replace Gate No. 3 Operating

Machinery 1 JOB $1,831,446.57 $1,831,446.57 $1,158,180.00 $1,158,180.00

TOTAL, AWARDABLE OPTION 1

ITEMS 1001 THROUGH 1003 $1,854,067.80 $1,166,830.00

AWARDABLE OPTION 1

IGE

Solicitation Number W911WN19B8009

Replace Gate Operating Machinery East Branch Dam

Alltech Engineering Corp

2001 Reimbursement for Actual Performance and Payment Bonds Premiums 1 JOB $21,678.20 $21,678.20 $8,000.00 $8,000.00

2002 Digital Progress Images 1 SET $894.63 $894.63 $650.00 $650.00 2003 Replace Emergency Gate Operating

Machinery 1 JOB $1,831,446.57 $1,831,446.57 $1,164,520.00 $1,164,520.00

TOTAL, AWARDABLE OPTION 2

ITEMS 2001 THROUGH 2003 $1,854,019.40 $1,173,170.00

3001 Reimbursement for Actual Performance and Payment Bonds Premiums 1 JOB $629.25 $629.25 $500.00 $500.00

3002 Removal of Temporary Work Platform and Site Restoration 1 JOB $25,295.83 $25,295.83 $64,000.00 $64,000.00

TOTAL, AWARDABLE OPTION 3

ITEMS 3001 AND 3002 $25,925.08 $64,500.00

TOTAL OF BASE CONTRACT AND

AWARDABLE OPTIONS 1,2,3

$6,253,137.00 $4,590,700.00

AWARDABLE OPTION 2

AWARDABLE OPTION 3

Sheet1