Amend_0001.pdf

PDF 145 KB Posted

Attached to
Shenango River Lake Fresh and Waste Water Treatment
Solicitation number
W911WN18T3001
Issued by

About this file

Amend 0001, Responses to Questions

View the file

Other files

File Type Posted
Site_Visit,_Sign-In_Sheet.pdf PDF
Price_Schedule.xls XLS spreadsheet
WD_15-4261_(Rev._-5)_01102018.pdf PDF
PWS_Atch_1_-_8.pdf PDF
W911WN18T3001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

RE: Fresh and Waste Water Treatment Services, Shenango River Lake

The purpose of this amendment is provide responses to questions submitted on the solicitation, as w ell as from the site visit.

See Summary of Changes for details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Mar-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN18T3001

X 9B. DATED (SEE ITEM 11)

01-Mar-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Mar-2018

CODE

U.S. ARMY ENGINEER DISTRICT, PITTSBURGH

ATTN CELRP-RC-P

W S MOORHEAD FEDERAL BUILDING

1000 LIBERTY AVENUE ROOM 2203

PITTSBURGH PA 15222-4186

W911WN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911WN18T3001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Answers to Questions received, Total of 6 Questions

Question 1: Section 2, Item 2.1.2 of the Performance Work Statement indicates that the Sewer treatment plant operator shall possess a Class F Type 1 license from the PADEP. No similar license requirement appears under the Section 1 Freshwater System portion of the Work Statement. What is the freshwater operator licensing requirements?

Answer: Department of Environmental Protection (DEP) certification for Water Systems, Class A and Class E, Water Subclasses 1-14

Question 2: Please advise if freshwater and sewage treatment operators carrying an Ohio EPA Class 1 license are acceptable via reciprocation of licensing thru the PADEP.

Answer: The PA State Board for Certification of Water and Wastewater Systems Operators may issue a Pennsylvania certification to an applicant holding a valid water and/or wastewater operator certification from another state, territory, the District of Columbia, or Board-approved registry. For more information, go to:

http://www.dep.pa.gov/Business/Water/BureauSafeDrinkingWater/OperatorCertification/Operators/Pages/Reciproci ty.aspx

Question 3: Please confirm that the well pits are designated confined spaces and will require OSHA confined space entry safety requirements.

Answer: The well pits meet the definition of a confined space and as such require the use of Occupational Safety and Health Administration (OSHA) procedures for safe entry.

Question 4: Please advise if there are any other locations designated as confined spaces that will require OSHA confined space safety standards.

Answer: The only other location would be the aeration tanks at the sewage treatment plant, which wouldn’t need to be entered on a routine basis. They may need to be entered for unforeseen maintenance, such as plugged aerator diffusers.

Question 5: Section 2.2.6 of the Performance Work Statement notes the following on the sewage collection lines:

“Periodic cleaning of the sewage lines (approx. every 2-3 years) is necessary to remove grit, sand debris and other deposits that constrict the free flow of sewage.” For bidding purposes, can you determine an exact number of times that line cleaning will be required over the 5-year (including options) contract period?

Answer: The blockage of sewage lines cannot be predicted. For proposal pricing on the Cleaning of Sewage Collection Lines identified as the third requirement for the base period and on each of the respective four (4) option periods, a sewage line total of 1,125 linear feet is being placed on Item No. 0003 (Base period), 1003 (Option Period 1), 2003 (Option Period 2), 3003 (Option Period 3), and 4003 (Option Period 4) to account for this service.

The Government’s main concern is to have some clearing immediately available in case the lines end up blocked.

Question 6: Is the inspection and testing at the wwtp 365 days a year?

Answer: In accordance to the Performance Work Statement Section 2.1.1, “the Contractor shall be responsible for the operation of the Shenango River Lake Sewage Treatment Plant (STP), lift stations, and other parts of the treatment system and appurtenant equipment seven days a week, 24 hours a day while the plant is in operation, including daily testing requirements. Daily testing shall occur on Federal holidays.”

W911WN18T3001

In accordance to the Performance Work Statement Section 2.5.2, “the Contractor shall conduct daily and bimonthly tests on effluent to ensure compliance with standards set forth in the NPDES Permit for the facility.” If the daily testing requirement of the National Pollutant Discharge Elimination System (NPDES) permit were to be amended during the period of performance on the contract, due to low or no discharge when the campground is not opened, the contract award would be modified.

(End of Summary of Changes)