W911WN-16-T-8009
New Cumberland Locks and Dam Saw Cutting for Floating Mooring Bitt Concrete Removal, Phase 4
Ohio River Jefferson County, OH
Technical Specifications
Certified Final Documents
New Cumberland Saw Cutting Phase 4
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SPECIFICATIONS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1 QC Review - W911WN-16-T-8009
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SPECIFICATIONS
PART 1 GENERAL REQUIREMENTS
1.1 GENERAL
1.2 CONCRETE SAW CUTTING
1.2.1 Alternative Cutting Methods
1.3 STEEL CUTTING
1.4 MISCELLANEOUS STEEL AND REINFORCEMENT
1.5 MEASUREMENT AND PAYMENT
1.5.1 Saw Cutting Concrete
1.5.2 Saw Cutting Exposed Metal
1.6 SAFETY
1.7 PROJECT SUBMITTALS
1.7.1 Sawcutting Work Plan
1.7.2 Environmental Protection Plan
1.8 COORDINATION MEETING AND POINTS OF CONTACT
1.9 VERIFICATION OF FIELD CONDITIONS
1.10 PROJECT/SITE CONDITIONS
1.10.1 Work Areas
1.10.2 Storage Areas
1.10.3 Utilities
1.10.4 Time of Performance
1.10.5 Lock Operation
1.11 DUST CONTROL
1.12 ENVIRONMENTAL PROTECTION
1.13 PROTECTION OF GOVERNMENT PROPERTY
1.14 PROTECTION OF PERSONNEL
1.15 IDENTIFICATION OF EMPLOYEES
1.16 SECURITY REQUIREMENTS
1.16.1 Contract for Work on Government Property (No Access to
Critical Infrastructure)
1.16.2 Contracts for Work at Federally Controlled Facilities (Access to Critical Infrastructure)
1.16.3 Background investigations are defined in two parts as
described below:
1.16.4 Changes in Security Requirements
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL
3.2 EQUIPMENT
3.3 CUTTING CONCRETE
3.3.1 Embedded Materials
3.3.2 General
3.3.3 Cutting
3.3.4 Control of Debris
3.4 CLEAN UP
SECTION 01 11 00 Page 1
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SPECIFICATIONS
PART 1 GENERAL REQUIREMENTS
1.1 GENERAL
The work is located at New Cumberland Island Locks and Dam, Ohio River, near Stratton, Ohio. The work is located on the Middle Wall at the Auxiliary Chamber (landward). The Auxiliary Chamber is in Jefferson County, Ohio. The site of the work may be reached from state and local roads and streets as indicated on the attached Directions to New Cumberland Locks and Dam.
The general description of the work is to furnish all equipment, labor, layout of work, and supervision to saw cut concrete at the Auxiliary Chamber (landward chamber) floating mooring bitts (FMBs) in accordance with the following specifications.
This work includes saw cutting of concrete and embedded items to the lines indicated below and on the attached drawings. Removal and disposal of the concrete and associated metal items will not be required. The floating mooring bitts will be removed by others prior to commencement of work by the Contractor.
All work, including cleanup of the premises, shall be completed as follows no later than January 9, 2017.
1.2 CONCRETE SAW CUTTING
All concrete saw cutting work will be performed in the small 110-FT by 600-FT landward lock chamber, specifically at the following landward facingfloating mooring bitts on the Middle Wall:
Middle Wall Sta. 1+96.0B (3rd FMB downstream of Upper Miter Gate)
Middle Wall Sta. 3+50.0B (4th FMB downstream of Upper Miter Gate)
Middle Wall Sta. 5+06.0B (5th FMB downstream of Upper Miter Gate)
Middle Wall Sta. 5+56.0B (6th FMB downstream of Upper Miter Gate)
The work will involve both vertical and horizontal saw cutting of concrete. The approximate dimensions to be saw cut are shown on the attached sketches.
The existing mooring bitt anchorages and embedded items are shown on the attached Reference Drawings O-LNC-20/19.3 and O-LNC-20/35.3. The floating mooring bitts will be removed by others.
The anchorage will remain in place. Upon completion of saw cutting, the concrete/mooring bitt anchorage will be anchored by others.
SECTION 01 11 00 Page 3
1.2.1 Alternative Cutting Methods
At the Contractor's option, and subject to the approval by the Contracting Officer, only the back and bottom cuts may be made by methods other than saw cutting. If alternative cutting methods are used, the tolerances specified shall apply to the centerline of the cutting for the back cut, and maximum concrete removal shall not exceed 1-1/2 inches beyond the indicated removal line. For the bottom cut, the tolerances shall apply to the extreme edge of the cut area, and concrete removal shall not exceed past the 5'-2" depth. All requirements for containment and disposal of debris, waste water, and other materials shall apply as specified.
1.3 STEEL CUTTING
Cutting of existing corner protection and wall armor on the chamber face of the lock wall shall be cut at the locations of the proposed concrete sawing and in a matter that facilitates the concrete sawing.
1.4 MISCELLANEOUS STEEL AND REINFORCEMENT
All concrete that is to be cut shall be assumed to have typical steel reinforcement. The guide channels and angle bracing shall be cut with the bottom concrete cut (see attached reference drawings).
1.5 MEASUREMENT AND PAYMENT
1.5.1 Saw Cutting Concrete
- Payment shall constitute full compensation for all labor, equipment, materials and supply costs for performing all concrete cutting.
- Measurement will be made of the number of locations that saw cutting is performed for replacement of mooring bitt anchorages as specified.
- Payment Items: SAW CUT CONCRETE FOR FLOATING MOORING BITT ANCHORAGE
REPLACEMENT
1.5.2 Saw Cutting Exposed Metal
- Payment shall constitute full compensation for all labor, equipment, materials and supply costs for performing all metal cutting.
- Measurement will be made of the number of locations that saw cutting is performed of corner protection and wall armor for floating mooring bitts.
- Payment Items: SAW CUT EXPOSED WALL ARMOR AND CORNER PROTECTION
1.6 SAFETY
All work shall be performed in accordance with the Corps of Engineers Safety Manual EM385-1-1. Latest version includes updates 1 through 15 and is available online at:
http://www.usace.army.mil/CESO/pages/home.aspx.
The Contractor shall complete and submit an Accident Prevention Plan. A template/example of an Accident Prevention Plan is included in this specification as a separate attachment. The Contractor shall modify and/or
SECTION 01 11 00 Page 4 of work.
Safety features shall include, but not be limited to:
- Safety Shoes: All employees engaged in construction operations shall wear safety shoes meeting the requirements of EM 385-1-1, Section 05.E.
- Protective Eyewear: All workers on the site shall wear, as a minimum, protective eyewear meeting the requirements of EM 385-1-1, Section 05.A. Additional eye protection may be required in accordance with EM 385-1-1, Section 05.B.
- Hearing Protection: Hearing protection shall be provided for workers in accordance with EM 385-1-1, Section 05.C.
- Protective Headgear: All workers on the site shall wear protective headgear in accordance with EM 385-1-1, Section 05.D.
- Personal Flotation Devices: Personal flotation devices (PFD's) shall be worn by all personnel when working beyond the lock esplanade, including but not limited to, crossing the land Wall, miter gates, or Middle Wall; and working on the River Wall, or any time a drowning hazard may exist.
- Employee Acknowledgement: All personnel used during this contract, including those of subcontractors, shall sign a formal written notice supplied by the Contractor, attesting that they have been provided and will utilize the above required safety equipment. Copies of these signed acknowledgements shall be furnished to the Contracting Officer.
- Fall Protection: The upstream lock pool is approximately 9.5-FT below the top of the lock wall and the downstream lock pool is approximately 30-FT below the top of the lock wall. The use of fall protection for this work is required. The Contractor shall design and implement fall protection measures in accordance with EM 385-1-1, Section 21.
- Safe Access: Safe access shall be continuously provided for project personnel and personnel of the Contracting Officer. Access shall be provided and maintained during every phase of the operations.
1.7 PROJECT SUBMITTALS
The Contractor shall provide submittals for Government review. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications.
1.7.1 Sawcutting Work Plan
The Contractor shall submit proposed methods and procedures for the saw cutting work for the Government's review. The proposed procedures and Environmental Protection Plan shall provide for safe conduct of the work, protection of property, equipment and machinery which is to remain undisturbed, protection and support of existing features, and coordination with lock operating requirements. The Sawcutting Plan shall include a detailed description of the proposed method(s) and equipment to be used for the saw cutting operation, including access to the work area, and the
SECTION 01 11 00 Page 5 sequence of each operation. No saw cutting work shall commence until the Contractor has received the Contracting Officer's approval of the proposed plan in writing.
1.7.2 Environmental Protection Plan
The Contractor shall submit and Environmental Protection Plan for review.
The Environmental Protection Plan shall include procedures to provide for safe conduct of the work, protection of property, equipment and machinery which is to remain undisturbed, protection and support of existing features, and coordination with lock operating requirements. The plan shall include a detailed description of the proposed method(s) and equipment to be used to control the saw cutting slurry, waste water, and dust from the saw cutting operation. No saw cutting work shall commence until the Contractor has received the Contracting Officer's approval of the proposed plan in writing.
1.8 COORDINATION MEETING AND POINTS OF CONTACT
Prior to commencement of any work being performed on site, the Contractor shall participate in the teleconference with the Administrative Contracting Officer (ACO) and the Lockmaster.
New Cumberland L/D Lockmaster:
Mr. Willie J. Maynard 740-537-2571
ACO:
Mr. Kirk McWilliams Resident Engineer Lower Mon Area Office 1811 Schoomaker Road, Monesen, PA 15062 724-684-7462
1.9 VERIFICATION OF FIELD CONDITIONS
The Contractor shall verify all dimensions and condition in the field and shall advise the Contracting Officer of any discrepancy before performing any work.
1.10 PROJECT/SITE CONDITIONS
1.10.1 Work Areas
Work areas will be limited to the lock walls in the vicinity of the floating mooring bitts and a limited area on the esplanade. Access for Government personnel shall be maintained along all lock walls at all times. The Contractor will be permitted to cross the miter gates to access the Middle Wall. Construction loads on the miter gate walkways shall not exceed 500 pounds.
1.10.2 Storage Areas
A storage area for materials and equipment will be provided on the esplanade at a location designated by the Contracting Officer. Use of the storage area shall not interfere with Government personnel in the operation of the project.
SECTION 01 11 00 Page 6
1.10.3 Utilities
Electric power will be made available at no cost to the Contractor at existing outlets in the tainter valve machinery pits on the Middle Wall and River Wall. The power supply is 440 volt, 90 Amp service, with Hubbell receptacles. The Contractor shall be responsible for providing connections compatible with the Hubbell receptacles.
1.10.4 Time of Performance
The Contractor shall confine all operations at the work site between 7:30 AM and 4:00 PM, Monday through Friday, unless otherwise approved. Work will not be permitted on weekends or Federal Holidays unless otherwise approved.
1.10.5 Lock Operation
The Auxiliary Chamber will be undergoing maintenance by the Government and will remain closed to Navigation traffic for the duration of the Contract.
1.11 DUST CONTROL
Dust resulting from saw cutting shall be controlled to prevent the spread of dust to avoid creation of a nuisance in the surrounding area. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding, and pollution.
1.12 ENVIRONMENTAL PROTECTION
Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction and associated activities. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
Minimize environmental pollution and damage that may occur as the result of construction operations. The environmental resources within the project boundaries and those affected outside the limits of permanent work must be protected during the entire duration of this contract. Comply with all applicable environmental Federal, State, and local laws and regulations.
Any delays resulting from failure to comply with environmental laws and regulations will be the Contractor's responsibility.
Waste water from construction activities will not be allowed to enter waterways or to be discharged prior to being treated to remove pollutants.
Dispose of the construction related waste water off-Government property in accordance with Federal, State, Regional and Local laws and regulations.
Secondary containment will be required if debris or waste water enters the lock chamber to contain it and prevent it from going downriver. Spill containment and cleanup supplies shall be furnished by the Contractor and kept onsite.
No debris, waste water from saw cutting, or other materials shall be permitted to enter the lock chamber or other waters.
Any spills or releases of debris into the water or other environmental violations shall be immediately reported to the Contracting Officer.
SECTION 01 11 00 Page 7
To limit noise pollution, all work shall be performed between the hours of 7:30 AM and 4:00 PM, Monday through Friday, unless otherwise approved.
1.13 PROTECTION OF GOVERNMENT PROPERTY
The Contractor shall protect all Government property during the performance of this contract. All damage to existing Government property as a result of Contractor's work shall be repaired or replaced to the satisfaction of the Contracting Officer. Work area shall be cleaned by the Contractor daily as needed and after construction is complete. Before beginning any concrete saw cutting work, carefully survey the structure to determine the extent of the work. Take all necessary precautions to insure against damage to existing concrete or other structures to remain in place, and repair or replace any damage to such items as approved by the Contracting Officer at no additional cost to the Government.
1.14 PROTECTION OF PERSONNEL
Insure that adequate measures are in place to protect workers, facility operation personnel, navigation vessel personnel, and the public from injury due to operations being performed. All protective measures shall be in accordance with EM 385-1-1.
1.15 IDENTIFICATION OF EMPLOYEES
The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working onsite and for requiring each employee engaged on the work to display identification.
Identification shall consist of name tags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government issued photo identification card is required for positive identification.
1.16 SECURITY REQUIREMENTS
This paragraph contains information for security requirements for work on Government property. The purpose of these security requirements is to ensure that all Contractor and subcontractor employees working on this contract have received proper clearance for access to Government property.
Identification of critical infrastructure and submission of required employee identification will be discussed at the Preconstruction Meeting.
Required employee information shall be submitted to the Contracting Officer or Pittsburgh Office of Security and Law Enforcement, as applicable, at least 15 calendar days prior to required employee access to the project.
1.16.1 Contract for Work on Government Property (No Access to Critical Infrastructure)
This paragraph applies to Government facilities not defined as critical infrastructure by the USACE Pittsburgh District.
All Contractor and subcontractor employees working on this contract who require access to non-critical infrastructures, as defined in the scope of this contract, on Pittsburgh District facilities (i.e. flood control dams, navigation locks, etc.), in areas that are available to the general public are required to have a favorable background check in accordance with "Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD-12).
SECTION 01 11 00 Page 8
The Contractor shall provide the information required by the attached E-Quip Information Needed for Contractors to the Contracting Officer for performance of the background check. This background check shall be conducted by the local or state police agency where the employee resides at the Contractor's expense. The results of these checks will be presented to the Administrative Contracting Officer (ACO) prior to the employee starting work on the contract. The ACO will make a determination of suitability based on the results of the checks. Any employee found not to be within the suitability standards will not be granted access to the project.
Employee information submitted to the Contracting Officer and results from investigations will be retained in a secure location until 90 calendar days after completion of the contract. The records will be destroyed at the end of this period.
Only those individual Contractor employees that were specifically identified and approved will be cleared to work on Government property.
The Contractor shall report any change(s) in person prior to the individual(s) arriving onsite. The Contractor shall follow the same requirements as listed above for any new employees who will require access to site.
1.16.2 Contracts for Work at Federally Controlled Facilities (Access to Critical Infrastructure)
This paragraph applies to Government facilities defined as critical infrastructure by the USACE Pittsburgh District (i.e. construction contracts or those requiring Contractor access to secure areas such as dams, locks or limited access facilities).
All Contractor and subcontractor employees working on this contract who require access to Pittsburgh District critical infrastructures, as defined by the USACE are required to have a favorable background check in accordance with "Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors"
(HSPD-12).
This background investigation shall be completed by the Pittsburgh Office of Security and Law Enforcement, who will make the final determination on an employee's suitability for work on Government property, and who shall have the right to deny a Contractor or subcontractor employee from working on a contract based on results of the background investigation.
1.16.3 Background investigations are defined in two parts as described below:
- Prior to any Contractor's employee accessing the work site, an initial background check (LEXUS/NEXUS) shall be completed. To accomplish this, the prime contractor shall submit a complete list of employees who will be working on Government property (prime contractor employees and any subcontractor employee) to include: name, social security number, date of birth, and place of birth. This list shall be submitted to the Pittsburgh Office of Security and Law Enforcement who will conduct this initial check based on the information provided. The Pittsburgh Office of Security and Law Enforcement will notify the Contracting Officer of the results within 5 working days of receiving the information. If no issues are found, approval to begin work will be provided in writing by the Contracting Officer or the Contracting
SECTION 01 11 00 Page 9
Officer's Representative to the Contractor upon receipt of the results from the Pittsburgh Office of Security and Law Enforcement. At that time, Contractor employees receiving a favorable background check will be permitted access to the work site.
- In addition to the requirements of the above subparagraph, those contractors who are awarded contracts that are sensitive or require access to USACE computer network shall also submit an investigation package for each Contractor and subcontractor employee requiring such access. This investigation package shall include:
SF-85, Questionnaire for Non-Sensitive Positions (See E-Quip form attached).
FD-258, Contractor Fingerprint Card (1 card for digital prints, 2 for ink prints). (Note: Prints must be taken by a trained/qualified individual; ORI block on FD-258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by contacting the Pittsburgh Office of Security and Law Enforcement).
At the conclusion of this in-depth background investigation, results will be provided by the Contracting Officer or the Contracting Officer's Representative to the Contractor. Contractor employees permitted access to Government property shall be limited to those individuals that have been specifically identified and approved. The Contractor shall report any change(s) in personnel at least 5 working days prior to individual(s) needing access to site. The Contractor shall provide the same information as listed above for any new employees.
Employee information submitted to the Pittsburgh Office of Security and Law Enforcement and results from investigations will be retained in a secure location until 90 calendar days after completion of the contract. The records will be destroyed at the end of this period.
1.16.4 Changes in Security Requirements
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, US Army Force Protection Measures, regulation or policy changes, etc. Changes to any security requirements shall be added to the contract by modification.
The Pittsburgh District Office of Security and Law Enforcement may be contacted by phone or e-mail at the following number/address:
Steve Davidson Phone: 412-395-7504 E-mail: stephen.davidson@usace.army.mil
Paul Surace Phone: 412-395-7162 E-mail: paul.m.surace@usace.army.mi
E-Quip Information Needed for Contractors
Information Needed for Contractors
Full Name
SECTION 01 11 00 Page 10
Date of Birth
City of Birth
Social Security Number
Country of Birth
Are they a US Citizen
E-mail Address
Phone Number (Primary and Secondary)
Supervisor Full Name
Supervisor E-mail Address
Supervisor Phone Number
Government POC Full Name
Government POC E-mail Address
Government POC Phone Number
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL
The Contractor shall provide all equipment and materials necessary to complete the work as shown and as specified. The Contractor shall verify dimensions and clearances in the field before beginning of work.
3.2 EQUIPMENT
The Contractor shall furnish sufficient equipment that is dependable, appropriate, and adequate to accomplish the work specified. Machines, tools, and equipment used in the performance of the work shall be approved before the work is started and shall be maintained in satisfactory condition at all times. The equipment shall be maintained in good working conditions. Anchor holes for mounting equipment shall be patched upon completion of work.
3.3 CUTTING CONCRETE
3.3.1 Embedded Materials
The attached drawing do not constitute a complete description of all metal parts and other materials that may be encountered, but represent the best information available to the Government. Other items, or different locations for items shown, may exist. Care shall be exercised to avoid cutting through functional embedded items intended to remain in service.
The Contractor's selection of equipment and methods shall consider the presence of such materials, and the Government will not be responsible in any way for the effect of such items on the Contractor's equipment or progress.
SECTION 01 11 00 Page 11
3.3.2 General
Saw cut the existing concrete to limits indicated. Saw cut concrete with care to avoid damage to adjacent structures, concrete, and embedded metal.
Mark on the surface the limits of concrete removal for approval by Contracting Officer prior to any removal. Notify the Contracting Officer at least 24 hours prior to the time such approval is required. Do not remove metal and other embedded items exposed during the concrete saw cutting without authorization of the Contracting Officer. All equipment and removal methods shall comply with applicable sections of EM 385-1-1.
3.3.3 Cutting
Wire sawing or other precision cutting methods which are capable of cutting concrete to the precise lines indicated may be utilized for cutting of concrete and embedded metals. In areas where such cutting is not feasible, cutting may be performed by line drilling or other approved methods.
Adequate safety measures shall be provided to protect workers, equipment, and structures in the vicinity of the work. All equipment shall be subject to the review and approval of the Contracting Officer.
- Tolerances for Concrete Cutting: Concrete shall be removed to the lines of removal indicated on the drawings. Tolerances for cuts shall be as shown on the drawings. The bottom width of the cutout block shall be less than the top width, and the back width of the cut shall be less than the chamber face width so that the block can be lifted out.
3.3.4 Control of Debris
Debris shall not be allowed to drop into the river or on vessels using the lock chamber. Debris shall be collected and retained near to its point of removal. The Contractor's method of debris control and removal shall be described in his saw cutting plan and must meet the approval of the Contracting Officer. Debris shall be disposed at a commercially available, properly permitted facility in a manner consistent with Federal, state and local regulations.
3.4 CLEAN UP
Clean all surfaces of concrete and adjacent facilities which are stained by dirt, oil, grease, fuel, or other byproducts that are created by the construction operations with detergent and pressure wash. Products used for cleanup shall be environmentally friendly. Waste water and debris from cleanup shall not be permitted to enter the water.
-- End of Section --
SECTION 01 11 00 Page 12
| COVER |
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 11 00 - SPECIFICATIONS |
| 01 11 00 - SPECIFICATIONS |
| PART 1 GENERAL REQUIREMENTS |
| 1.1 GENERAL |
| 1.2 CONCRETE SAW CUTTING |
| 1.2.1 Alternative Cutting Methods |
| 1.3 STEEL CUTTING |
| 1.4 MISCELLANEOUS STEEL AND REINFORCEMENT |
| 1.5 MEASUREMENT AND PAYMENT |
| 1.5.1 Saw Cutting Concrete |
| 1.5.2 Saw Cutting Exposed Metal |
| 1.6 SAFETY |
| 1.7 PROJECT SUBMITTALS |
| 1.7.1 Sawcutting Work Plan |
| 1.7.2 Environmental Protection Plan |
| 1.8 COORDINATION MEETING AND POINTS OF CONTACT |
| 1.9 VERIFICATION OF FIELD CONDITIONS |
| 1.10 PROJECT/SITE CONDITIONS |
| 1.10.1 Work Areas |
| 1.10.2 Storage Areas |
| 1.10.3 Utilities |
| 1.10.4 Time of Performance |
| 1.11 DUST CONTROL |
| 1.12 ENVIRONMENTAL PROTECTION |
| 1.13 PROTECTION OF GOVERNMENT PROPERTY |
| 1.14 PROTECTION OF PERSONNEL |
| 1.15 IDENTIFICATION OF EMPLOYEES |
| 1.16 SECURITY REQUIREMENTS |
| 1.16.1 Contract for Work on Government Property No Access to Critical |
| 1.16.2 Contracts for Work at Federally Controlled Facilities Access to |
| 1.16.3 Background investigations are defined in two parts as described |
| 1.16.4 Changes in Security Requirements |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 GENERAL |
| 3.2 EQUIPMENT |
| 3.3 CUTTING CONCRETE |
| 3.3.1 Embedded Materials |
| 3.3.2 General |
| 3.3.3 Cutting |
| 3.3.4 Control of Debris |
3.4 CLEAN UP