Attachment_2_(Statement_of_Work).pdf

PDF 25 KB Posted

Attached to
Trailer Mounted Concrete Pump with Operator, Ohio River (Emsworth L/D) Federal contract opportunity
Solicitation number
W911WN-16-Q-2571
Issued by
Department of the Army Corps of Engineers Engineering District Pittsburgh

View the file

Other files for this federal contract opportunity

Other files attached to Trailer Mounted Concrete Pump with Operator, Ohio River (Emsworth L/D), newest first.
File Type Posted
Attachment_4_(Sketch_for_Trailer_Mounted_Pump).pdf PDF
Attachment_1_(Bid_Schedule).docx DOCX document
Attachment_5_(Wage_Determinations).docx DOCX document
Attachment_3_(Concrete_Specifications).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Concrete Pumping General Requirements

Emsworth L/D, Ohio River Concrete Pumping Rental General Requirements

1.0 TRAILER MOUNTED CONCRETE PUMP REQUIREMENTS.

a. The Trailer Mounted Concrete Pump will be provided with an operator on days of actual concrete placement. If it is requested by the Government to have the Trailer Mounted Concrete Pump, heavy-duty flexible hoses, and assemblies be delivered to the site several days in advance of the concrete placement, an operator may not be required on these days.

b. The Trailer Mounted Concrete Pump shall be capable of placing the underwater concrete vertically down 41 ft and 110 ft horizontally (across the bottom of the lock chamber).

Another potential placement configuration is setting the pumper trailer onto a Government barge which will minimize the length of pumping hose. See attached sketch.

c. The distance to be pumped shall not exceed the limits recommended by the Trailer Mounted Concrete Pump manufacture.

d. The pumping equipment shall be piston or squeeze pressure type. Pneumatic placing equipment shall not be used.

e. The pipeline shall be heavy-duty flexible hose specifically designed and/or manufactured for concrete pumping. Aluminum pipe shall not be used.

f. The maximum inside diameter of the heavy-duty flexible hose shall be 4 inches. The maximum size aggregate in the Underwater Concrete Design Mix will be #67.

g. The heavy-duty flexible hose shall be primed/greased utilizing a plug ("pig", "ball") by the Trailer Mounted Concrete Pump operator prior to pumping the Underwater Concrete.

Portland Cement, Type 1 (2 each 94 lb. bags) will be provided by the government to prime the lines.

h. Literature. All quotes submitted must be accompanied by descriptive literature of the Trailer Mounted Concrete Pump proposed. This literature shall include dimensions and capacities of the Trailer Mounted Concrete Pump in the form of general dimension drawings; all the above information must be clearly marked within the literature. Additional information in regards to the heavy-duty flexible hose, connections, weights, etc. should also be provided.

i. Specifications. The Trailer Mounted Concrete Pump shall be equal to or better than the Reed C70 Series. Approximate size and weight: L=184”, W=71”, H=83”, and weight = 8600 pounds.

2.0 GENERAL INFORMATION

2.1 Underwater Concrete.

a. The Government will be placing Underwater Concrete in formwork that is submerged approximately 14 ft in water. Government divers will position and control the end of the heavy-duty flexible hose from the Trailer Mounted Concrete Pump to place the underwater concrete in the forms. The placement will continue until it reaches the required elevation.

b. The anticipated design mix of the Underwater Concrete is attached; this underwater mix design was used by the Pittsburgh District in 2014 and 2015 with good results.

3.0 PUMPING SCHEDULE

3.1 Underwater Concrete Pumping

a. The actual amount of Underwater Concrete pumped will be between 10 and 20 cubic yards depending on the underwater conditions and formwork requirements. Each concrete placement will be a Minimum of 2 cubic yards. A total of 1 – 6 days rental of the Trailer Mounted Concrete Pump may be required to complete the entire Underwater Concrete Pumping Operation, some days requiring an operator and some days on standby without an operator. If more than 1 day is required to complete the Underwater Concrete Pumping, the operations will most likely occur on consecutive days. It is anticipated that the Trailer Mounted Concrete Pump, heavy-duty flexible hoses, and assemblies be delivered to the site 1 – 3 days prior to the actual Underwater Concrete placement in order for the Government to determine the best location for the Trailer Mounted Concrete Pump, to assemble the hoses and possibly perform a “dry-run” moving the heavy-duty flexible hose assembly utilizing a crane (It is anticipated that the operator will not be needed on the setup day).

b. The concrete pumping operations will occur sometime between 25 July and 12 August 2016 during the weekdays. It is not anticipated that concrete will be placed on any weekends.

c. The contractor will be notified at least 2-5 days prior to start of the pumping operation.

Multiple times may be requested.

d. Job site address: Emsworth L/D, Ohio River

0 Western Avenue Pittsburgh, PA 15202-1708 412-766-6213

4.0 SECURITY REQUIREMENTS

4.1 Access and General Protection and Security Policy and Procedures:

The contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the USACE Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The contractor must submit the full name, Social Security Number, Date of Birth, and Place of Birth for all associated contractor or subcontractor employees to the USACE Security Specialist Paul M. Surace, 412-395-7162, paul.m.surace@usace.army.mil or Stephen Davidson, 412-395-7504, stephen.davidson@usace.army.mil. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.

4.2 Escort Requirements:

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

4.3 Pre-Screen Candidates using “E-Verify” Program:

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

- - End of Section - -mailto:paul.m.surace@usace.army.mil mailto:stephen.davidson@usace.army.mil http://www.uscis.gov/e-verify http://www.uscis.gov/e-verify