BidAbstract.xlsx

XLSX spreadsheet 38 KB Posted

Attached to
Charleroi Locks, River Chamber Completion, Monoliths M-22 to M-27
Solicitation number
W911WN14B0001
Issued by

About this file

Bid Abstract

View the file

Other files

File Type Posted
W911WN-15-B-0005-0003.pdf PDF
BIDRESULTS.docx DOCX document
Charleroi_M22-M27_Video.wmv WMV file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BidItems

Charleroi Locks and Dam
River Chamber Completion
Monoliths M-22 to M-27
W911WN-14-B-0001

July 23, 2014

IGEBid # 1 - Joseph B. Fay Co.Bid # 2 - Kokosing Construction Company, Inc.Bid #3 - Mahan - Lane A Joint VentureBid #4 Trumbull Corporation & Brayman Construction Company
ITEM NO.DESCRIPTIONQTYUNITUNIT
PRICEAMOUNTUNIT
PRICEAMOUNTUNIT
PRICEAMOUNTUNIT
PRICEAMOUNTUNIT
PRICEAMOUNT
0001REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BONDS PREMIUMS1JOB$617,540.00$617,540.00$409,067.51$409,067.51$525,000.00$525,000.00$416,300.00$416,300.00$471,000.00$471,000.00
0002DIGITAL PROGRESS IMAGES, MONTHLY45SET$718.00$32,310.00$650.00$29,250.00$500.00$22,500.00$700.00$31,500.00$400.00$18,000.00
0003DIGITAL AERIAL PROGRESS IMAGES, QUARTERLY16SET$1,570.00$25,120.00$650.00$10,400.00$550.00$8,800.00$800.00$12,800.00$450.00$7,200.00
0004ENVIRONMENTAL COMPLIANCE MEASUREMENTS, SAMPLING, TESTING AND REPORTING, CONCRETE BATCH PLANT45MONTHS$15,560.00$700,200.00$6,900.00$310,500.00$11,000.00$495,000.00$7,200.00$324,000.00$6,900.00$310,500.00
0005CLEANING OF SEDIMENT BASIN NO. 1, CONCRETE BATCH PLANT6EACH$48,650.00$291,900.00$25,000.00$150,000.00$15,000.00$90,000.00$21,615.00$129,690.00$15,000.00$90,000.00
0006CLEANING OF SEDIMENT BASIN NO. 2, CONCRETE BATCH PLANT6EACH$40,540.00$243,240.00$22,500.00$135,000.00$18,000.00$108,000.00$6,368.00$38,208.00$17,500.00$105,000.00
0007CLEAN SEEP, CONCRETE BATCH PLANT9EACH$4,865.00$43,785.00$3,500.00$31,500.00$15,000.00$135,000.00$3,050.00$27,450.00$12,750.00$114,750.00
0008MOBILIZATION AND DEMOBILIZATION1JOB$451,200.00$451,200.00$880,000.00$880,000.00$4,333,000.00$4,333,000.00$2,508,000.00$2,508,000.00$600,000.00$600,000.00
0009MAINTAIN CONCRETE TESTING LAB45MONTHS$16,920.00$761,400.00$4,000.00$180,000.00$20,000.00$900,000.00$6,000.00$270,000.00$3,900.00$175,500.00
0010FURNISH NEW ROTATING CONVEYOR UNIT FOR CONVEYOR SYSTEM1JOB$1,090,000.00$1,090,000.00$881,600.00$881,600.00$1,850,000.00$1,850,000.00$1,050,000.00$1,050,000.00$832,100.00$832,100.00
0011RELOCATE PORTABLE CONVEYORS5EACH$5,700.00$28,500.00$8,500.00$42,500.00$50,000.00$250,000.00$6,000.00$30,000.00$7,150.00$35,750.00
0012INITIAL BATCH PLANT AND PH TREATMENT SYSTEM SETUP AND TRIAL OPERATION1JOB$103,450.00$103,450.00$75,000.00$75,000.00$350,000.00$350,000.00$179,000.00$179,000.00$320,000.00$320,000.00
0013MONTHLY MAINTENANCE OF BATCH PLANT AND CONVEYOR SYSTEMS45MONTHS$1,770.00$79,650.00$135,000.00$6,075,000.00$14,000.00$630,000.00$95,600.00$4,302,000.00$150,000.00$6,750,000.00
0014REIMBURSEMENT FOR REPAIR OF BATCH PLANT AND CONVEYOR EQUIPMENT1JOB$50,000.00$50,000.00$50,000.00$50,000.00$50,000.00$50,000.00$5,000.00$50,000.00$50,000.00$50,000.00
0015SHUTDOWN AND MOTHBALLING OF BATCH PLANT AND PHE TREATMENT FACILITY AT END OF CONSTRUCTION1JOB$60,000.00$60,000.00$20,000.00$20,000.00$125,000.00$125,000.00$100,000.00$100,000.00$79,000.00$79,000.00
0016MAINTAIN GOVERNMENT FIELD OFFICES35MONTHS$4,820.00$168,700.00$3,500.00$122,500.00$6,000.00$210,000.00$10,000.00$350,000.00$15,000.00$525,000.00
0017PROVIDE TEMPORARY POWER AND CONTROLS FOR DAM1JOB$491,200.00$491,200.00$600,000.00$600,000.00$1,000,000.00$1,000,000.00$300,000.00$300,000.00$400,000.00$400,000.00
0018REIMBURSEMENT FOR POWER COMPANY SERVICES1JOB$15,000.00$15,000.00$10,000.00$10,000.00$10,000.00$10,000.00$10,000.00$10,000.00$10,000.00$10,000.00
0019CONSTRUCT DOWNSTREAM PROTECTION CELL1JOB$1,374,000.00$1,374,000.00$875,000.00$875,000.00$1,300,000.00$1,300,000.00$1,000,000.00$1,000,000.00$1,545,000.00$1,545,000.00
0020TEMPORARY RAISE EXISTING RIVER WALL MONOLITHS R-26 THROUGH R-281JOB$13,550.00$13,550.00$45,000.00$45,000.00$25,000.00$25,000.00$38,000.00$38,000.00$50,000.00$50,000.00
0021CONCRETE CLOSURE WEDGE, DOWNSTREAM CLOSURE1JOB$461,600.00$461,600.00$1,082,000.00$1,082,000.00$900,000.00$900,000.00$1,000,000.00$1,000,000.00$750,000.00$750,000.00
0022COFFER WALL, DOWNSTREAM CLOSURE1JOB$420,800.00$420,800.00$745,000.00$745,000.00$1,000,000.00$1,000,000.00$1,000,000.00$1,000,000.00$600,000.00$600,000.00
0023MODIFY EXISTING STABILITY CELL, DOWNSTREAM CLOSURE1JOB$283,400.00$283,400.00$400,000.00$400,000.00$450,000.00$450,000.00$1,000,000.00$1,000,000.00$500,000.00$500,000.00
0024GRANULAR BERM MATERIAL, DOWNSTREAM CLOSURE2105CUBIC YARDS$68.30$143,771.50$150.00$315,750.00$100.00$210,500.00$76.00$159,980.00$110.00$231,550.00
0025HANDRAIL, GOVERNMENT ACCESS TO LOCK AND DAM FACILITIES710LINEAR FEET$108.00$76,680.00$50.00$35,500.00$100.00$71,000.00$200.00$142,000.00$120.00$85,200.00
0026GANGWAYS, GOVERNMENT ACCESS TO LOCK AND DAM FACILITIES4Each$7,330.00$29,320.00$5,000.00$20,000.00$8,000.00$32,000.00$7,500.00$30,000.00$15,000.00$60,000.00
0027METAL STAIRS, GOVERNMENT ACCESS TO LOCK AND DAM FACILITIES2Each$5,170.00$10,340.00$15,000.00$30,000.00$7,000.00$14,000.00$15,000.00$30,000.00$20,000.00$40,000.00
0028TREMIE CONCRETE STRUT, LOCK WALL STABILIZATION340CUBIC YARDS$891.40$303,076.00$280.00$95,200.00$650.00$221,000.00$650.00$221,000.00$380.00$129,200.00
0029GRANULAR BERM MATERIAL, TREMIE CONCRETE STRUT, LOCK WALL STABILIZATION145CUBIC YARDS$132.60$19,227.00$300.00$43,500.00$225.00$32,625.00$155.00$22,475.00$200.00$29,000.00
0030LOWER LEVEL STABILIZATION STRUT, LOCK WALL STABILIZATION2EACH$142,850.00$285,700.00$95,000.00$190,000.00$130,000.00$260,000.00$229,000.00$458,000.00$180,000.00$360,000.00
0031UPPER LEVEL STABILIZATION STRUT, LOCK WALL STABILIZATION2EACH$55,000.00$110,000.00$54,000.00$108,000.00$50,000.00$100,000.00$139,000.00$278,000.00$100,000.00$200,000.00
0032UPPER LEVEL REPLACEMENT STABILIZATION STRUTS, LOCK WALL STABILIZATION4EACH$24,600.00$98,400.00$26,500.00$106,000.00$25,000.00$100,000.00$38,000.00$152,000.00$45,000.00$180,000.00
0033FIELD DEMONSTRATION, TREMIE ENDS OF THE LOWER LEVEL STABILIZATION STRUTS1JOB$105,200.00$105,200.00$120,000.00$120,000.00$160,000.00$160,000.00$176,000.00$176,000.00$375,000.00$375,000.00
0034TREMIE ENDS OF THE LOWER LEVEL STABILIZATION STRUTS, LOCK WALL STABILIZATION2EACH$24,180.00$48,360.00$60,000.00$120,000.00$60,000.00$120,000.00$85,000.00$170,000.00$60,000.00$120,000.00
0035GROUT LOWER MIDDLE WALL STABILIZATION STRUTS, LOCK WALL STABILIZATION2EACH$18,010.00$36,020.00$30,000.00$60,000.00$9,000.00$18,000.00$7,500.00$15,000.00$6,500.00$13,000.00
0036COLD JOINT ANCHORS, LOCK WALL STABILIZATION2EACH$12,170.00$24,340.00$25,000.00$50,000.00$14,000.00$28,000.00$16,000.00$32,000.00$20,000.00$40,000.00
0037REMOVE FOOTBRIDGE SPAN1JOB$56,850.00$56,850.00$75,000.00$75,000.00$90,000.00$90,000.00$225,000.00$225,000.00$125,000.00$125,000.00
0038DEMOLITION OF ORIGINAL RIVER WALL AND FIXED WEIR TO EL 7341JOB$519,400.00$519,400.00$1,332,000.00$1,332,000.00$3,000,000.00$3,000,000.00$1,095,000.00$1,095,000.00$1,250,000.00$1,250,000.00
0039DEMOLITION OF ORIGINAL LOWER GUARD WALL1JOB$166,500.00$166,500.00$850,000.00$850,000.00$1,000,000.00$1,000,000.00$676,000.00$676,000.00$500,000.00$500,000.00
0040REMOVE DOWNSTREAM RIVER CHAMBER CLOSURE CELL1JOB$473,750.00$473,750.00$275,000.00$275,000.00$800,000.00$800,000.00$479,000.00$479,000.00$500,000.00$500,000.00
0041FURNISH AND INSTALL SHEET PILING, COFFERBOX MONOLITHS M-22 TO M-2713,810LINEAR FEET$79.50$1,097,895.00$120.00$1,657,200.00$135.00$1,864,350.00$140.00$1,933,400.00$110.00$1,519,100.00
0042FURNISH AND INSTALL KING PILES, COFFERBOX MONOLITHS M-22 TO M-277,730LINEAR FEET$616.40$4,764,772.00$500.00$3,865,000.00$645.00$4,985,850.00$760.00$5,874,800.00$725.00$5,604,250.00
0043FIELD DEMONSTRATION, SOCKETED KING PILES1JOB$263,600.00$263,600.00$450,000.00$450,000.00$600,000.00$600,000.00$429,000.00$429,000.00$1,350,000.00$1,350,000.00
0044FURNISH AND INSTALL SOCKETED KING PILES, MONOLITHS M-24 TO M-2614EACH$93,430.00$1,308,020.00$92,000.00$1,288,000.00$155,000.00$2,170,000.00$98,000.00$1,372,000.00$125,000.00$1,750,000.00
0045DYNAMIC PILE TESTING, COFFERBOX MONOLITHS M-22 TO M-275EACH$1,605.00$8,025.00$2,500.00$12,500.00$6,000.00$30,000.00$4,500.00$22,500.00$3,600.00$18,000.00
0046FURNISH AND INSTALL STRUCTURAL STEEL, COFFERBOX MONOLITHS M-22 TO M-27585,000POUNDS$9.55$5,586,750.00$4.50$2,632,500.00$5.75$3,363,750.00$7.00$4,095,000.00$8.50$4,972,500.00
0047REMOVE SHEET PILING, COFFERBOX MONOLITHS M-22 TO M-277,345LINEAR FEET$36.75$269,928.75$35.00$257,075.00$16.00$117,520.00$1.00$7,345.00$55.00$403,975.00
0048REMOVE KING PILES, COFFERBOX MONOLITHS M-22 TO M-274,400LINEAR FEET$38.25$168,300.00$60.00$264,000.00$45.00$198,000.00$10.00$44,000.00$134.00$589,600.00
0049REMOVE STRUCTURAL STEEL, COFFERBOX MONOLITHS M-22 TO M-27555,000POUNDS$0.35$194,250.00$0.66$366,300.00$0.50$277,500.00$0.25$138,750.00$1.00$550,000.00
0050UNDERWATER ALLUVIUM EXCAVATION INSIDE COFFERBOX MONOLITHS M-22 TO M-277,220CUBIC YARDS$240.00$1,732,800.00$185.00$1,335,700.00$175.00$1,263,500.00$225.00$1,624,500.00$225.00$1,624,500.00
0051COFFERBOX DEWATERING MONOLITH M-221JOB$75,500.00$75,500.00$250,000.00$250,000.00$60,000.00$60,000.00$140,000.00$140,000.00$350,000.00$350,000.00
0052COFFERBOX DEWATERING MONOLITH M-271JOB$56,000.00$56,000.00$290,000.00$290,000.00$60,000.00$60,000.00$125,000.00$125,000.00$175,000.00$175,000.00
0053COFFERBOX DEWATERING MONOLITHS M-23 TO M-261JOB$71,000.00$71,000.00$350,000.00$350,000.00$80,000.00$80,000.00$150,000.00$150,000.00$250,000.00$250,000.00
0054DEWATER BETWEEN MIDDLE WALL M-22 AND DOWNSTREAM RIVER CHAMBER CLOSURE1JOB$8,050.00$8,050.00$55,000.00$55,000.00$20,000.00$20,000.00$115,000.00$115,000.00$50,000.00$50,000.00
0055COMPENSATION FOR FLOODING AND EVACUATION, COFFERBOXES M-22 OR M-272EACH$100,000.00$200,000.00$100,000.00$200,000.00$100,000.00$200,000.00$100,000.00$200,000.00$100,000.00$200,000.00
0056COMPENSATION FOR FLOODING AND EVACUATION, COFFERBOX M-23 TO M-261EACH$200,000.00$100,000.00$200,000.00$200,000.00$200,000.00$200,000.00$200,000.00$200,000.00$200,000.00$200,000.00
0057COMPENSATION FOR GOVERNMENT-DIRECTED EVACUATION WITHOUT FLOODING, COFFERBOXES M-22 TO M-271EACH$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00$40,000.00
0058CONSTRUCT PORT CLOSURE SEALS AT ORIGINAL MONOLITH OM-271JOB$34,000.00$34,000.00$55,000.00$55,000.00$100,000.00$100,000.00$80,000.00$80,000.00$29,000.00$29,000.00
0059CONSTRUCT DOWNSTREAM CLOSURE SEALS AT MONOLITH M-221JOB$360,000.00$360,000.00$555,000.00$555,000.00$1,150,000.00$1,150,000.00$990,000.00$990,000.00$600,000.00$600,000.00
0060SEEPAGE CONTROL GROUT,ORIGINAL LOWER GUARD WALL CLOSURE SEAL AT MONOLITH M-2274CUBIC YARDS$1,785.00$124,950.00$7,500.00$555,000.00$6,000.00$444,000.00$3,000.00$222,000.00$4,000.00$296,000.00
0061PRE-EXCAVATION MIDDLE WALL DOWNSTREAM2,400CUBIC YARDS$70.00$168,000.00$75.00$180,000.00$50.00$120,000.00$56.00$134,400.00$40.00$96,000.00
0062FIELD DEMONSTRATION, MIDDLE WALL FOUNDATION DRILLED SHAFTS1JOB$421,600.00$421,600.00$400,000.00$400,000.00$1,100,000.00$1,100,000.00$998,000.00$998,000.00$1,550,000.00$1,550,000.00
006354" DIA. PERMANENT CASING, 48-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITH M-22263LINEAR FEET$2,255.00$593,065.00$1,950.00$512,850.00$8,500.00$2,235,500.00$4,800.00$1,262,400.00$1,175.00$309,025.00
0064SOIL EXCAVATION, 48-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITH M-22315LINEAR FEET$367.50$115,762.50$400.00$126,000.00$250.00$78,750.00$715.00$225,225.00$130.00$40,950.00
0065ROCK EXCAVATION, 48-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITH M-22600LINEAR FEET$948.00$568,800.00$1,025.00$615,000.00$750.00$450,000.00$960.00$576,000.00$525.00$315,000.00
006678" DIA. PERMANENT CASING, 72-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-23 TO M-27465LINEAR FEET$2,615.00$1,215,975.00$2,100.00$976,500.00$9,000.00$4,185,000.00$5,700.00$2,650,500.00$1,630.00$757,950.00
0067SOIL EXCAVATION, 72-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-23 TO M-27630LINEAR FEET$361.10$227,493.00$580.00$365,400.00$250.00$157,500.00$760.00$478,800.00$180.00$113,400.00
0068ROCK EXCAVATION, 72-INCH DIA. MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-23 TO M-271,200LINEAR FEET$2,573.50$3,088,200.00$1,855.00$2,226,000.00$800.00$960,000.00$930.00$1,116,000.00$820.00$984,000.00
0069REINFORCING STEEL, MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-22 TO M-271,687,900POUNDS$3.50$5,907,650.00$2.05$3,460,195.00$1.90$3,207,010.00$1.80$3,038,220.00$1.50$2,531,850.00
0070ACCESS TUBES, CROSSHOLE SONIC LOGGING, MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-22 TO M-2713,320LINEAR FEET$14.25$189,810.00$8.70$115,884.00$20.00$266,400.00$40.00$532,800.00$15.00$199,800.00
0071CONCRETE, MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-22 TO M-272,240CUBIC YARDS$406.50$910,560.00$715.00$1,601,600.00$750.00$1,680,000.00$400.00$896,000.00$400.00$896,000.00
0072CROSSHOLE SONIC LOGGING (CSL) MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-22 TO M-2745EACH$2,655.00$119,475.00$3,000.00$135,000.00$1,600.00$72,000.00$1,650.00$74,250.00$775.00$34,875.00
0073CORING OF MW FOUNDATION DRILLED SHAFTS, MONOLITHS M-22 TO M-27460LINEAR FEET$147.50$67,850.00$300.00$138,000.00$260.00$119,600.00$410.00$188,600.00$170.00$78,200.00
0074PORTLAND CEMENT, MONOLITHS M-22 TO M-271,884TONS$260.30$490,405.20$160.27$301,948.68$250.00$471,000.00$225.00$423,900.00$350.00$659,400.00
0075POZZOLAN, MONOLITHS M-22 TO M-271,245TONS$85.10$105,949.50$68.45$85,220.25$115.66$143,175.00$75.00$93,375.00$130.00$161,850.00
0076GROUND GRANULATED BLAST FURNACE SLAG, MONOLITHS M-22 TO M-271,511TONS$180.50$272,735.50$160.27$242,167.97$200.00$302,200.00$165.00$249,315.00$225.00$339,975.00
0077SILICA FUME, MONOLITHS M-22 TO M-2790TONS$1,307.00$117,630.00$771.31$69,417.90$1,200.00$108,000.00$1,015.00$91,350.00$1,400.00$126,000.00
0078ANTI-WASHOUT ADMIXTURE, MONOLITHS M-22 TO M-275,240GALLONS$44.10$231,084.00$29.74$155,837.60$40.00$209,600.00$38.00$199,120.00$55.00$288,200.00
0079LIMESTONE POWDER, MONOLITHS M-22 TO M-27820TONS$91.20$74,784.00$65.22$53,480.40$100.00$82,000.00$75.00$61,500.00$235.00$192,700.00
0080DELIVER AND INSTALL DOWNSTREAM MITER GATE EMBEDDED GUDGEON ANCHORAGES4EACH$16,900.00$67,600.00$15,000.00$60,000.00$25,000.00$100,000.00$27,500.00$110,000.00$35,000.00$140,000.00
0081FURNISH AND INSTALL DOWNSTREAM BULKHEAD RECESS FILLERS1JOB$326,100.00$326,100.00$93,000.00$93,000.00$150,000.00$150,000.00$110,000.00$110,000.00$300,000.00$300,000.00
0082FIELD DEMONSTRATION, TREMIE FOUNDATION PLACEMENT1JOB$1,237,000.00$1,237,000.00$900,000.00$900,000.00$3,250,000.00$3,250,000.00$1,675,000.00$1,675,000.00$2,600,000.00$2,600,000.00
0083FURNISH AND INSTALL TREMIE CONCRETE PARTITIONS82,214POUNDS$2.85$234,309.90$4.00$328,856.00$5.50$452,177.00$3.60$295,970.40$7.50$616,605.00
0084TREMIE CONCRETE, MONOLITHS M-22 TO M-275,300CUBIC YARDS$133.30$706,490.00$130.00$689,000.00$330.00$1,749,000.00$175.00$927,500.00$110.00$583,000.00
0085CAST-IN-PLACE CONCRETE, MIDDLE WALL, MONOLITHS M-22 TO M-2713,740CUBIC YARDS$330.30$4,538,322.00$497.00$6,828,780.00$580.00$7,969,200.00$245.00$3,366,300.00$375.50$5,159,370.00
0086PVC WATERSTOPS, MONOLITHS M-22 TO M-27508LINEAR FEET$27.30$13,868.40$66.00$33,528.00$70.00$35,560.00$25.00$12,700.00$35.00$17,780.00
0087COPPER WATERSTOPS, MONOLITHS M-22 TO M-27200LINEAR FEET$83.20$16,640.00$110.00$22,000.00$90.00$18,000.00$80.00$16,000.00$60.00$12,000.00
0088FURNISH AND INSTALL PRECAST CONCRETE CULVERTS1JOB$2,706,000.00$2,706,000.00$500,000.00$500,000.00$1,820,000.00$1,820,000.00$2,550,000.00$2,550,000.00$1,250,000.00$1,250,000.00
0089REINFORCING STEEL, TREMIE CONCRETE, MIDDLE WALL, MONOLITHS M-22, M-34 AND M-24113,940POUNDS$3.35$381,699.00$3.60$410,184.00$1.50$170,910.00$4.80$546,912.00$4.00$455,760.00
0090REINFORCING STEEL, MIDDLE WALL, MONOLITHS M-22 TO M-27508,650POUNDS$2.35$1,195,327.50$3.60$1,831,140.00$1.50$762,975.00$2.50$1,271,625.00$5.00$2,543,250.00
0091FLOATING MOORING BITTS, MONOLITH M-222EACH$47,300.00$94,600.00$50,000.00$100,000.00$40,000.00$80,000.00$33,000.00$66,000.00$20,000.00$40,000.00
0092FURNISH AND INSTALL LINE HOOKS AND GUARDS, MONOLITH M-2210EACH$5,750.00$57,500.00$10,000.00$100,000.00$7,000.00$70,000.00$7,300.00$73,000.00$7,000.00$70,000.00
0093FURNISH AND INSTALL CHECK POSTS, MONOLITHs M-22 AND M-273EACH$6,650.00$19,950.00$8,000.00$24,000.00$7,500.00$22,500.00$6,250.00$18,750.00$12,000.00$36,000.00
0094LOCK LADDER RECESSES, MONOLITH M-251,330POUNDS$14.10$18,753.00$23.50$31,255.00$13.00$17,290.00$18.00$23,940.00$10.00$13,300.00
0095ALUMINUM RABBET ANGLES, MONOLITHS M-22 TO M-27386LINEAR FEET$38.50$14,861.00$60.00$23,160.00$60.00$23,160.00$42.00$16,212.00$98.00$37,828.00
0096ALUMINUM PLANKING838SQUARE FEET$96.20$80,615.60$48.00$40,224.00$60.00$50,280.00$45.00$37,710.00$32.00$26,816.00
0097ALUMINUM PLATE WELDED TO ALUMINUM GRATING64SQUARE FEET$146.00$9,344.00$95.00$6,080.00$100.00$6,400.00$97.00$6,208.00$86.00$5,504.00
0098ALUMINUM GRATING30SQUARE FEET$300.00$9,000.00$132.00$3,960.00$350.00$10,500.00$77.00$2,310.00$300.00$9,000.00
0099CORNER CASTINGS, MONOLITHS M-22 TO M-2718EACH$1,447.00$26,046.00$4,000.00$72,000.00$1,100.00$19,800.00$935.00$16,830.00$3,800.00$68,400.00
0100CORNER PROTECTION, MONOLITHS M-22 TO M-27843LINEAR FEET$278.50$234,775.50$230.00$193,890.00$300.00$252,900.00$163.00$137,409.00$250.00$210,750.00
0101WALL ARMOR, MONOLITHS M-22 TO M-274,940LINEAR FEET$213.00$1,052,220.00$156.00$770,640.00$205.00$1,012,700.00$125.00$617,500.00$290.00$1,432,600.00
0102EMBEDDED PINS FOR REMOVABLE HANDRAIL24EACH$195.00$4,680.00$500.00$12,000.00$300.00$7,200.00$155.00$3,720.00$500.00$12,000.00
0103FURNISH AND INSTALL EMBEDDED METALS, DOWNSTREAM MITER GATE1JOB$52,000.00$52,000.00$140,000.00$140,000.00$250,000.00$250,000.00$145,000.00$145,000.00$70,000.00$70,000.00
0104FURNISH AND INSTALL EMBEDDED METALS, DOWNSTREAM BULKHEAD RECESSES1JOB$155,300.00$155,300.00$145,000.00$145,000.00$100,000.00$100,000.00$175,000.00$175,000.00$165,000.00$165,000.00
0105INSTRUMENTATION1JOB$375,000.00$375,000.00$260,000.00$260,000.00$400,000.00$400,000.00$125,000.00$125,000.00$91,000.00$91,000.00
0106INSTRUMENTATION MONITORING PROGRAM45MONTHS$21,040.00$946,800.00$13,500.00$607,500.00$17,000.00$765,000.00$12,000.00$540,000.00$12,500.00$562,500.00
0107ELECTRICAL AND MECHANICAL SYSTEMS EMBEDDED ITEMS1JOB$372,000.00$372,000.00$200,000.00$200,000.00$350,000.00$350,000.00$158,000.00$158,000.00$150,000.00$150,000.00
0108ENVIRONMENTAL COMPLIANCE MEASUREMENTS, SAMPLING, TESTING AND REPORTING, VICTORY HOLLOW SITE35MONTHS$9,055.00$316,925.00$7,350.00$257,250.00$12,000.00$420,000.00$7,500.00$262,500.00$7,500.00$262,500.00
0109CLEANING OF SEDIMENT BASIN NO. 1, VICTORY HOLLOW SITE6EACH$19,530.00$117,180.00$20,000.00$120,000.00$14,000.00$84,000.00$18,201.00$109,206.00$11,750.00$70,500.00
0110CLEANING OF SEDIMENT BASIN NO. 2, VICTORY HOLLOW SITE6EACH$19,900.00$119,400.00$20,000.00$120,000.00$14,000.00$84,000.00$22,909.00$137,454.00$11,750.00$70,500.00
0111CLEARING, VICTORY HOLLOW SITE5ACRE$8,865.00$44,325.00$3,500.00$17,500.00$6,000.00$30,000.00$1,701.00$8,505.00$4,000.00$20,000.00
0112SILT FENCE, VICTORY HOLLOW SITE500LINEAR FEET$5.80$2,900.00$19.80$9,900.00$7.00$3,500.00$5.20$2,600.00$7.00$3,500.00
0113WEIGHTED SEDIMENT FILTER LOG, (12-IN. DIA.), VICTORY HOLLOW SITE600LINEAR FEET$11.30$6,780.00$9.00$5,400.00$5.00$3,000.00$9.20$5,520.00$13.00$7,800.00
0114TEMPORARY SEEDING, VICTORY HOLLOW SITE10ACRE$21,380.00$213,800.00$2,500.00$25,000.00$2,300.00$23,000.00$2,835.00$28,350.00$1,500.00$15,000.00
0115PERMANENT SEEDING, VICTORY HOLLOW SITE5ACRE$11,410.00$57,050.00$3,500.00$17,500.00$10,000.00$50,000.00$4,410.00$22,050.00$1,750.00$8,750.00
0116AAPDT NO. 2A SURFACE COURSE, FIRST 400 CUBIC YARDS, VICTORY HOLLOW SITE400CUBIC YARDS$59.25$23,700.00$40.00$16,000.00$125.00$50,000.00$52.00$20,800.00$100.00$40,000.00
0116ABPDT NO. 2A SURFACE COURSE, ALL OVER 400 CUBIC YARDS, VICTORY HOLLOW SITE200CUBIC YARDS$59.25$11,850.00$40.00$8,000.00$115.00$23,000.00$78.00$15,600.00$60.00$12,000.00
0117TRAFFIC CONTROL, VICTORY HOLLOW SITE1JOB$60,000.00$60,000.00$5,000.00$5,000.00$20,000.00$20,000.00$14,263.00$14,263.00$35,000.00$35,000.00
0118MOVE EXISTING MATERIAL AT VICTORY HOLLOW SITE AND STOCKPILE AREA 300017,300CUBIC YARDS$23.00$397,900.00$6.50$112,450.00$15.00$259,500.00$7.20$124,560.00$18.00$311,400.00
0119RELOCATE ROCK PILES AT VICTORY HOLLOW SITE, UPLAND FILL PLACEMENT AREA2,200CUBIC YARDS$181.30$398,860.00$6.50$14,300.00$15.00$33,000.00$7.20$15,840.00$30.00$66,000.00

TOTAL, ITEMS 0001 THROUGH 0119 $58,381,620.85 $58,578,541.31 $75,195,182.00 $63,433,297.40 $66,425,263.00