This file contains responses to a Request for Information (RFI) related to the WSMR Bridge Repair project at White Sand Missile Range, New Mexico. The RFI responses document contractor feedback and clarifications regarding the bridge repair solicitation W911SG26BA016, which is an Invitation for Bids set aside for HUBZone-owned small businesses under NAICS code 237310. The project involves bridge repair and rehabilitation work with an estimated construction magnitude between $500,000 and $1,000,000, with a firm-fixed-price contract structure. The project is located at White Sand Missile Range in New Mexico, and the contracting agency is the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood.

Key requirements for this opportunity include mandatory performance and payment bonds, original bid guarantees, a superintendent who must work directly for the prime contractor (considered a non-subcontractable key position), and simultaneous performance of all work. The applicable sales tax rate for Dona Ana County, New Mexico is 6.4975%. Bid opening was scheduled at MICC-Fort Bliss, 111 Pershing Road, Room 220, Fort Bliss, Texas 79916. This RFI response document provides contractor input that likely informed the development of the final solicitation and identifies specific questions, concerns, or clarifications requested by potential bidders regarding project requirements and specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION W911SG-26-B-A016

Day of Bid Inquiry: August 24, 2026 From: E. Arrieta Company Name: Fulcrum Contracting Group LLC Address: 3073 Stormy Point Drive, El Paso, Texas 79938 Phone Number: 915.227.3333 Email: e.arrieta@fulcrumelp.com Bid Inquiry: please see inquiry 1 to 5 below with the question in underlined text

· Question 1: (Detail 02 in Drawing C3) given the erosion conditions, we suggest installing readymix flowable fill (or concrete) between the cutoff wall and apron to provide support to the apron itself. If this is an acceptable solution, can you please specify whether to use either concrete or fill and make this a requirement for all bidders?

Response: The Contractor may substitute flowable fill for select backfill in accordance with Section 516 “Flowable Fill,” of the NMDOT Standard Specifications for Highway and Bridge Construction, latest edition. Flowable fill shall consist of a flowable mixture of Portland cement, fly ash, aggregates, admixtures and water.

· Question 2: Can you please provide estimated dates for the 120 days period of performance

Response: Specific calendar dates are not known at this time and will not be finalized until the contract is formally awarded.

· Question 3: What is the availability of water for construction and staging area?

Response: The construction water source is located at the Small Missile Range (SMR), accessible via a fire hydrant at the following approximate coordinates: 32°28'49.23"N, 106°25'7.05"W. The hydrant is approximately 14 miles from the project location. The Contractor must install a backflow prevention device approved by the WSMR Water Plant Manager, in accordance with Section 2.3.1 of the Statement of Work (SOW). The location of the Staging Area is described in the plans.

· Question 4: What is the expected procedure for accessing the site, including sanitary services such as porta potties, concrete delivery, concrete pump, everyday work and so forth?

Response: Site access must be coordinated through the Contractor’s designated representative, who will be issued the SMR gate code via the Contracting Officer's Representative (COR) and in accordance with the SOW. The Contractor's representative is solely responsible for personally meeting, escorting, and granting site access to all subcontractors, delivery personnel, and service providers.

· Question 5: Hot, or cold weather concrete practices are very likely to happen. Previous to the proper authorization, are we allow to work off “regular” working hours, overnight in some cases?

Response: Hours of operation are defined in the SOW. Any work proposed outside of these hours must be submitted in writing to the COR for review. Approval will be granted on a case-by-case basis and is strictly contingent upon COR availability to inspect critical work elements.