This document contains Questions and Answers related to a Request for Information (RFI) for the roof repair of Building 11147 under Solicitation W911SG24B0017. The RFI covers various aspects of the project, including requests for as-built drawings, details on the roof deck type and slope requirements, HVAC unit requirements, and information on fall protection and safety guardrails. The contract opportunity is for a Firm-Fixed Price contract to remove the existing built-up gravel roof and replace it with a new 80 mil TPO roofing system with R-38 insulation and glass-mat roof board. The project is expected to have a period of performance of 90 calendar days after the notice to proceed and is being procured under the HUBZone set-aside with a NAICS code of 238160 (Roofing Contractors) and a size standard of $19M. The contract value is estimated between $250,000 to $500,000. The contracting agency is the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI QUESTIONS AND ANSWERS
W911SG24B0017
Roof Repair Bldg. 11147
1.) Requesting as-built drawings for this project.
ANSWER: no updated as-builts drawings available.
2.) The anchor points amount, and location are not clear. Can you please advise?
ANSWER: Anchor points and spec should meet the OSHA standards
3.) What is the deck type?
ANSWER: Concrete deck
4.) Is the slope on the deck or do we need to create the slope with tapered insulation? If so, what is the minimum slope?
ANSWER: Tapered insulation, and the minimum slope is ½”. 12 to achieve positive drainage
5.) The existing air conditioning units are sitting on a metal frame. Do we change the frame to an actual roof curb?
ANSWER: The A/C is sitting on the curbs.
6.) Do we need to add tax rate to the price?
ANSWER: No
7.) Are there elevations available for this project?
ANSWER: No. the contractor must verify dimension and high on field.
8.) Are there photos available for this project?
ANSWER: No, it needs Public Affairs (PA) permit to disclose pictures of this building.
9.) Is building 1 story, 2 story, etc.?
ANSWER: 1-story building.
10.) Photos and size of soffit?
ANSWER: No, it needs Public Affairs (PA) permit to disclose pictures of this building.
11.) Required remediation company for the base?
ANSWER: unknown. The asbestos survey is required.
12.) Are there any roof drains?
ANSWER: No, the building does not have roof drains
13.) Temp HVAC – Available to connect to building or per room?
ANSWER: Building is vacant
14.) Will crane be required to remove HVAC units?
ANSWER: the contactor’s decision. It is means and methods of the contractor
15.) Safety Guardrail is there a model number, what was supplied is a document number?
ANSWER: this is only for fall protection system during construction.
16.) Safety Guardrail location? Entire perimeter?
ANSWER: this is only for fall protection system during construction.
17.) Fall protection post, model number?
ANSWER: Anchor points and spec should meet the OSHA standards
18.) Fall protection post locations?
ANSWER: Anchor points and spec should meet the OSHA standards