This document is an Abstract of Offers for a federal construction contract solicitation, W911SG24B0015, for a roof repair project at Building 2480. The solicitation was issued by the Mission and Installation Contracting Command (MICC) Fort Bliss on behalf of the U.S. Army Directorate of Public Works located at Fort Bliss, Texas.
The project requires the removal and replacement of the existing roof with a new fully adhered 80 mil TPO roofing system, including R-38 insulation, 5/8 inch glass-mat roof board, and exterior components such as soffit, fascia, gutters, and vents. The contract will be awarded as a Firm-Fixed Price contract with an anticipated period of performance of 90 calendar days. The North American Industry Classification System (NAICS) code is 238160 Roofing Contractors, with a size standard of $19 million. The project magnitude is between $1,000,000 and $5,000,000, and the procurement will be solicited as a Historically Underutilized Business Zone (HUBZone) set-aside. The Abstract of Offers provides bid information for four offerors, including their bid security, amendments acknowledged, and unit prices for the contract items.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER PAGE OF
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)2. PROJECT TITLE
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
ABSTRACT OF OFFERS - CONSTRUCTION CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGE OF
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)
2. PROJECT TITLE
NO.:
NO.:
NO.:
NO.:
A. OFFEROR
A. OFFEROR
A. OFFEROR
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
A. ITEM NO.
B. ESTIMATED QUANTITY
C. UNIT
D. UNIT PRICE
E. ESTIMATED AMOUNT
E. ESTIMATED AMOUNT
D. UNIT PRICE
E. ESTIMATED AMOUNT
D. UNIT PRICE
E. ESTIMATED AMOUNT
D. UNIT PRICE
AUTHORIZED FOR LOCAL REPRODUCTION Previous edition is usable
OPTIONAL FORM 1419A (11-88)
8.2.1.3144.1.471865.466429
| 1. SOLICITATION NUMBER: W911SG24B0015 |
| 2. PROJECT TITLE: Roof Repair Bldg. 2480 |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): BID BOND/20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): BID BOND/20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): BID BOND/20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): BID BOND/20% |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: 0 |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: 0 |
| 4C. OFFERORS (Continued) AMENDMENTS ACKNOWLEDGED.: 0 |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: 0 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 1 of 13.: 1.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 3B. ESTIMATED QUANTITY: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 13 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 12 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 11 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 10 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 9 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 8 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 7 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 6 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 5 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 4 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 3 of 13.: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13.: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 2 of 13.: |
| 3B. ESTIMATED QUANTITY: 1.00000000 |
| 3C. CONTRACT ITEMS. UNIT: JOB |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 Of 13.: 847150.28000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 847150.28000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 252300.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 252300.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 216963.35000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 216963.35000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 997373.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 997373.00000000 |
| PAGE OF: 2.00000000 |
| PAGES: 3.00000000 |
| Offeror number. Column 1 of 4.: 3 |
| Offeror number. Column 2 of 4.: 4 |
| Offeror number. Column 3 of 4.: 5 |
| Offeror number. Column 4 of 4.: 6 |
| A. OFFEROR: West Coast Contractors |
| A. OFFEROR: The Roof and Metal Company |
| A. OFFEROR: J. Carrizal General Construction, Inc. |
| A. OFFEROR: Globe Builders |