0011211482
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
A. Provide a revised/Updated statement of w ork (highlighted section in SOW) B. Provide building Draw ings C. Provide responses to RFI's
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 32
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Aug-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911SG18R0079
X 9B. DATED (SEE ITEM 11)
06-Aug-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2018
CODE
MICC-FT BLISS W911SG
111 PERSHING RD
FT BLISS TX 79916
W911SG 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911SG18R0079
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title of File
Dwg Bldg. 2420
Dwg Bldg. 2449
**Specifications, features and pictures within the Statement of Work**
(End of clause)
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
REQUEST FOR INFORMATION
Install Onity HT24 Lockset
RFI’s
Contractor question
1. The kick plates on the doors in building 2449 are bright brass. The Unity locks are dull chrome finish, therefore, will the spring loaded hinges also be dull chrome color (US26D)?
DPW Engineering response: The hinges shall be submitted to match the Onity Lock finish of Satin Nickel.
Contractor question
2. Building 2420, should we replace all the hinges with new spring loaded hinges? Our professional recommendation is replace all spring loaded hinges.
DPW Engineering response: No, adjust hinges and only replace hinges that are not working.
Contractor question
3. When can we expect the building print layout to help with the handing of the locks?
DPW Engineering response: It should be going to you with the RFI answers.
Contractor question
4. What doors, in particular, have been identified for immediate replacement?
DPW Engineering response: Please see Floor Plan.
Contractor question
5. The cheaper alternative to the mortise lock version of the Onity lock is the cylindrical type. On building 2420 - would a wraparound plate be acceptable with a cylindrical lock type set-up, potentially saving thousands of dollars for the customer. Further, in Building 2449, the Onity locks being used will be the cylindrical type due to the knob locks that are being replaced.
DPW Engineering response: Install mortise type locks with deadbolt on all doors.
Contractor question
6. How many doors require a panic device set up?
DPW Engineering response: 1 at 2420 (1 double door) and 2 at 2449 (1 single door and 1 double door)
7. Door trim: What exactly is needed on the replacement doors? Kick plates? Peep holes?
Etc.
DPW Engineering response: New door, lock, kick plate, peepholes and hinges. If the door has a name tag holder, install the existing name tag holder on the new door.
Contractor question
8. What is the fire rating on the replacement doors?
DPW Engineering response: Match the fire rating on the existing doors.
Contractor question
9. Bldg. 2449- Change the existing cylindrical type locks to Mortise type locks with the deadbolt function? If so, the existing doors will need to be cut/prep to fit the mortise type locks.
DPW Engineering response: Yes, change the existing cylindrical type locks to Mortise type locks with the deadbolt function.
Contractor question
10. Bldg. 2449- Do we need to add self-closing hinges to the bid?
DPW Engineering response: Yes, add spring loaded hinges to the bid as per changes to scope of work.
Contractor question
11. A list of which doors that need to be replaced is needed.
DPW Engineering response: See floor plan.
Contractor question
12. Need to verify if the finish of locks will be 26D/Satin Chrome
DPW Engineering response: The finish is Satin Nickel.
Contractor question
13. To treat/repair the doors, do you want us to use Lacquer or Varnish?
* We recommend Lacquer since it's more durable and more resistant against humidity.
* In addition, Lacquer dries quicker.
DPW Engineering response: Lacquer.
14. If one of the commercial spring hinges is damaged, do you want us to replace all three or just the damaged ones?
DPW Engineering response: No, adjust hinges and only replace hinges that are not working.
Contractor question
15. We noticed that the commercial spring hinges on various doors are different color/material. Since the Onity HT24 Lockset requested comes in satin chrome, do you want us to replace all the hinges that are not satin chrome to match the lockset, even if they are not damaged, for consistency?
DPW Engineering response: No, adjust hinges and only replace hinges that are not working.
Contractor question
16. We noticed that the kick plates on various doors are different color/material. Do you want us to use the same ones or replace them with satin chrome, for consistency?
DPW Engineering response: Only replace the kick plates on doors that are replaced.
Contractor question
17. On the documentation provided, on Page 64, the Onity HT 24 Lockset states that they are "for non-fire rated doors only". The existing doors have a 20-minute fire rating. Please let us know if you still want to use this specific Lockset.
* This can be a security issue.
DPW Engineering response: According to the Manufacturer, “The HT24 is fire rated in accordance with UL10C.” Could the “for non-fire rated doors only” be for the type of batteries?
Contractor question
18. Can you please provide the number of doors that will need to be replaced, including those that are bent?
DPW Engineering response: Please see floor plan.
Contractor question
19. If any of the metal door frames are damaged and need replacement, will there be a budget set-aside for the additional work?
DPW Engineering response: No, there is no budget set-aside for the additional work.
20. For both Onity OnPoint Encoder computer systems, will we be using the existing duplex receptacles or electrify a new electrical circuit?
DPW Engineering response: Use existing duplex receptacles.
The following have been modified:
STATEMENT OF WORK
STATEMENT OF WORK
Install Onity Locksets and Door Repair/Replacement in Buildings 2449 and 2420
PART 1
GENERAL INFORMATION
1. General. This is a construction contract to provide non-personal services for Onity Lock installation and door repair/replacement in two barracks buildings on Fort Bliss.
1.1. Background. The Onity locksets are to reduce spending on maintenance and lockouts and to improve security as compared to the hard key locksets currently in use. The Government (Housing Division) is currently using the Onity lockset system. The Onity Lockset system to install is Onity HT24. Onity locksets shall be installed in Building 2449 (fifty-two, 52 and two exterior doors) and building 2420 (forty-three, 43 and one exterior door). Damaged bedroom doors shall be repaired/replaced as necessary.
1.2. Objectives. Contractor to furnish construction and related services to the Government in a professional and collaborative environment to sustain mission requirements. Construction services and finished products to be delivered on schedule, safely, and compliant with regulatory codes and standards.
1.3. Description of Work. Successful implementation of this contract requires the Contractor to make available and execute the following services, as associated with construction services:
Consultation, Evaluation, and Assessment Protection of Existing Features Deconstruction, Demolition and Disposal Construction, Permanent and Temporary Storage and Delivery Quality Control Safety Management, Training, and Administration Coordination, Project and Construction Management Services Administration, Documentation and Delivery of Requisite Deliverables Commissioning, Systems Operation and Verification Shop Drawings Creation and Computer Drafting Warranty Origination, Registration and Support
1.3.1. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and non-personal services necessary to perform work on systems as per this contract and incidental tasks related to successful implementation. The Government shall not exercise any supervision or control over the subcontractors performing the construction herein. Such construction subcontractors shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.3.2. The Contractor shall be responsible for:
1.3.2.1. Execution of the work as per this Scope of Work and Onity lock system manufacturer requirements.
1.3.2.2. The Contractor shall comply with applicable laws and regulations, including Federal Law, New Mexico and Texas State Laws, Occupational Safety and Health Administration (OSHA) Laws and regulations, Part 6 of this Statement of Work (SOW) and precipitating codes.
1.4. Period of Performance. The period of performance shall be forty-five (45) calendar days after issuance of Notice to Proceed (NTP).
1.5. Place of Performance. The work to be performed under this contract will be performed at Fort Bliss Military Reservation, Facilities 2449 and 2420.
1.5.1. Laydown / staging area. Staging and laydown area will be provided as a portion of the construction foot print. Contractor shall assess and evaluate laydown area for acceptability. Contractor shall submit written approval of provided area to the Contracting Officer Representative (COR) and Contracting Officer (KO) prior to NTP.
1.6. Occupancy. Building will be occupied for duration of project.
1.7. Attachments.
B. Product Specifications
1.8. INSPECTIONS
1.8.1. Inspection Requirements. The Contractor is responsible for performing or having performed all inspections and tests necessary to substantiate that the raw materials, components, intermediate assemblies, and end products furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts.
1.8.2. Inspection -- Dismantling, Demolition, or Removal of Improvements. Unless otherwise designated by the specifications, all workmanship performed under the contract is subject to Government inspection at all times and places where dismantling or demolition work is being performed. The Contractor shall furnish promptly, and at no increase in contract price, all reasonable facilities, labor, and materials necessary for safe and convenient inspection by the Government. The Government shall perform inspections in a manner that will not unduly delay the work.
1.8.2.1. The Contractor is responsible for damage to property caused by defective workmanship. The
Contractor shall segregate and remove from the premises any unsatisfactory facilities, materials, and equipment used in contract performance, and replace them with satisfactory items within seventy-two
(72) hours of written notice. The Contractor and any surety shall be liable, to the extent specified in the contract for any damage or cost of repair or replacement.
1.8.3. Inspection of Construction. The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the KO and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
1.8.3.1. Government inspections and tests are for the sole benefit of the Government and do not – Relieve the Contractor of responsibility for providing adequate quality control measures; Relieve the Contractor of responsibility for damage to or loss of the material before acceptance; Constitute or imply acceptance;
or Affect the continuing rights of the Government after acceptance of the completed work.
1.8.4. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the KO’s written authorization.
1.8.5. The Contractor shall promptly furnish all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the KO. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
1.8.6. The Contractor shall replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
1.8.7. If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the KO will make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
1.8.8. Unless otherwise specified in the contract, the Government will accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the KO determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
1.9. HOURS OF OPERATION
1.9.1. Normal Work Hours. The Contractor shall perform all work during normal work hours. Normal work hours are defined as the time period from 07:30 hours (7:30AM) to 16:30 hours (04:30 PM) MST, Mondays through Fridays except on Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor will not be reimbursed when the Government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.9.2. Federal Government Holidays.
New Year’s Day 1st day of January Martin Luther King Jr.'s Birthday 3rd Monday of January Presidents Day 3rd Monday of February Memorial Day Last Monday of May
Independence Day 4th day of July Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veterans Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December
1.9.2.1. When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the proceeding Friday is observed as a legal holiday. This list of holidays relates to Government duty days and is not intended to supplement or otherwise alter the provisions of any Wage Determination regarding applicable paid holidays.
1.9.2.2. It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel shall not be a reason for an additional period of performance, or entitlement of compensation except as set forth within the contract. In the event the Contractor’s personnel work during the holiday, the Contractor may reimburse them; however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked, unless stipulated otherwise. This provision does not preclude reimbursement for authorized overtime work if applicable.
1.9.2.3. When the Department of Defense grants excused absence to its employees, the Contractor agrees to continue to provide sufficient personnel to perform critical tasks already in operation or scheduled, and shall be guided by the instructions issued by the KO or the Contracting Officer Representative (COR).
1.9.2.4. If Government personnel are furloughed, the Contractor shall contact the KO or the COR to receive direction. It is the Government’s decision as to whether the contract price/cost will be affected as a result of Government shutdown and/or furloughed Government employees. In the event that Government shutdown and/or furloughed Government employee does impact contract price/cost, a negotiated settlement will be reached as deemed appropriate by the KO.
1.9.3. Approval of Work outside Normal Work Hours. Approval of work other than normal work-hours of the military reservation will be based upon the requirements of the task, technical or safety factors and not for the convenience of the Contractor. This is not intended to restrict the Contractor to an 8-hour day if the segment of project requires continuous work until completed because of mission requirements, the technical nature thereof, in the interest of safety, or to prevent damage to the project or other property. The Contractor will give prior notice of such requirements to the KO. When weekend or holiday work is required, the Contractor shall make his request to perform same to the KO not less than 48 hours in advance so that arrangements may be made to provide full-time inspection of the work. When the Government requires the Contractor to work outside normal hours, the Contractor will be notified at the onset of the project, but not less than 24 hours in advance.
1.10. SECURITY.
1.10.1. Security Requirements. Contractor personnel (including sub-contractors) who are assigned to work in a secure facility shall be escorted by the activity that owns the secure facility.
1.10.2. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the
Government may require changes in contractor security matters or processes.
1.10.3. For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.
1.10.4. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.10.5. Physical Security. The Contractor shall be responsible for safeguarding all Government equipment, information and property provided for Contractor use IAW AR 190-13, The Army Physical Security Program. At the close of each work period, Government facilities, equipment and materials shall be secured by the Contractor.
1.10.6. Key Control. The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons.
1.10.6.1. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be reimbursed by the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost reimbursed by the Contractor. Any Government property stolen or damaged in association with keys being duplicated, misplaced, or lost by the Contractor personnel, shall be reimbursed to the Government.
1.10.6.2. The Contractor shall prohibit the use of Government issued keys/key cards by any person other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the KO.
1.10.6.3. Lock Combinations. The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s Quality Control Plan.
1.10.7. Security of Classified Items, Systems and Information. The Contractor, as a general rule, shall not have access to classified information; however, should classified documents fall into the possession of the Contractor, the Contractor shall immediately contact the COR for disposition instructions.
1.11. SAFETY.
1.11.1. Accident Prevention. The Contractor shall provide and maintain work environments and procedures which will (1) safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities; (2) avoid interruptions of Government operations and delays in project completion dates; and (3) control costs in the performance of this contract.
1.11.1.1. For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall: Provide appropriate safety barricades, signs, and signal lights;
Comply with the standards issued by the Secretary of Labor at 29 Code of Federal Regulations (CFR) part 1926 and 29 CFR part 1910; and Ensure that any additional measures the KO determines to be reasonably necessary for the purposes are taken.
1.11.1.2. If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
1.11.1.3. Whenever the KO becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the KO will notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall take corrective action within twenty-four (24) hours. If the Contractor fails or refuses to promptly take corrective action, the KO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued.
1.11.1.4. Before commencing the work, the Contractor shall –
1.11.1.4.1. Submit a written proposed plan for implementing this paragraph (1.11.1). The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and
1.11.1.4.2. Meet with representatives of the KO to discuss and develop a mutual understanding relative to administration of the overall safety program.
1.11.2. Reporting of Fire and Safety Hazards. The Contractor shall train personnel to recognize fire and safety hazards and encourage personnel in the performance of their duties to report fire and safety hazards and unsafe conditions to their supervisor. The Contactor shall take corrective action to remedy reported deficiencies IAW the terms of this contract. The COR shall be notified of deficiencies beyond the terms of this contract.
1.11.3. Environment and OSHA. The Contractor shall comply with all local, State, and Federal environmental and occupational safety laws, rules, and regulations. Any apparent conflict between compliance with such local, State, and Federal environmental and occupational safety laws, rules, regulations, and compliance with the requirements of the contract shall be immediately brought to the attention of the KO or authorized representative for final resolution. The Contractor shall notify the KO or authorized representative in writing in addition to any verbal notification of such conflict. The Contractor shall be liable for all fines, penalties, and costs which result from violations of, or failure to comply with, all such local State, or Federal laws, rules, and regulations. All unsafe acts or conditions fostered by the Contractor or Contractor personnel may be grounds for the KO or authorized representative to halt any and all Contractor performance with a commensurate deduction of monies due to the Contractor until such unsafe conditions are corrected. The Contractor shall take due caution not to endanger personnel during performance of this contract. Upon discovery of a serious hazard such as fire, or large fuel spill, the Contractor shall notify the KO or designated representative and COR.
1.11.4. Reporting Mishaps. The Contractor shall adhere to reporting of mishaps IAW AR 385-10, The Army Safety Program and DA Pam 385-40, Army Accident Investigations and Reporting. In addition, the Contractor shall report: (1) Injury or occupational illness to on-duty Contractors; (2) Contractor accidents involving Army property and personnel.
1.11.5. Personnel Safety. The Contractor shall immediately correct all safety deficiencies upon notification of the deficiencies by the KO, designated representative or COR, and shall notify the KO of the corrective action to be taken.
1.12. PERSONNEL
1.12.1. For purposes of this paragraph, the term “personnel” or “employee(s)” refers to any person performing work related to this contract, the Contractor’s employees, agents, representatives, or Subcontractors.
The Contractor shall staff this effort with trained, competent and capable employee(s) for the discipline they are assigned to. Contractor personnel shall present a clean, neat, and professional appearance. The Contractor shall ensure that employees meet all applicable federal, state, local, and installation certification, licensing, medical requirements, and qualifications to perform all assigned tasks and functions as defined in this contract prior to commencement of work. The Contractor shall not permit any personnel to work under this contract if such person is identified by a Government authorized representative to the Contractor as a potential threat to the health, safety, security, general well-being, or operational mission of the Army and Fort Bliss Military Reservation. All Contractors’ personnel shall comply with installation security, access procedures, and Contractor’s Safety Plans.
1.12.2. Contractor’s personnel, whose tasks involve operation of any vehicles, shall possess a valid U.S. state driver’s license, certificates and permits, applicable for the type and class of vehicle being operated.
1.12.3. Contractor’s personnel shall either be a United States Citizen or authorized to work in the United States or possess a valid U.S. Immigration T-151 or I-94, Alien Registration Card.
1.12.4. Identification of Contractor Employees. The Contractor (to include Subcontractors) shall provide each employee an Identification (ID) Badge, which includes at a minimum, the Company Name, Employee Name and a color photo of the employee. ID Badges for Key Personnel shall also indicate their job title. ID Badges shall be worn at all times during which the employee is performing work under this contract. Each Contractor (to include Subcontractors) employees shall wear the ID Badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit. The Contractor (to include Subcontractors) shall be responsible for collection of ID Badges upon completion of the contract or termination of employee. A listing of issued identification cards shall be furnished to the KO prior to the contract performance date and updated as needed to reflect Contractor and Subcontractor personnel changes. All contract personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.12.5. Conflict of Interest & Employment of Government Personnel. The Contractor shall not knowingly employ any person who is a U.S. Government employee if employing that person would create a conflict of interest. Additionally, subcontracted parties and service providers shall not knowingly employ any person who is an employee of the Government, either military or civilian, unless such person seeks and receives written approval according to DOD 5500.7-R, Joint Ethics Regulations (JER) by the individual’s commander or director. A copy of the authorization will be provided to the COR. In addition, the Contractor is prohibited from employing Government Quality Assurance Representatives (QAR) whom the Contractor knows or should have known are responsible for monitoring any contracts/subcontracts awarded to the service provider.
1.12.6. Conduct of Employees. Employees shall conduct themselves IAW installation policies concerning conduct and DOD 5500.7-R, JER. The KO may require the Contractor to remove from the job site any employee working under this contract for reason of misconduct, security, found to be, or suspected to be under the influence of alcohol, drugs, or other incapacitating agents. Contractor employees shall be subject to dismissal from the premises if such action is necessary in the best interests of the Government. The removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the services as required by this SOW.
1.12.7. Contractor Vehicles.
1.12.7.1. All Contractor vehicles shall be readily identifiable. Identification shall include displaying Contractor’s name in a clear and unobstructed location on the vehicle.
1.12.7.2. Motor vehicles entering Fort Bliss Operational Area shall be properly licensed, insured, and registered with the Installation Access Pass Office.
1.12.8. Gate Policy for Fort Bliss. All contractor personnel must get their passes at the Chaffee Commercial Pass Office. Fort Bliss has started implementing a rapid pass gate entry security service. Under the rapid pass program, Contractor personnel are vetted through a series of national and local record checks to determine whether they meet Fort Bliss’ criteria for access. The determination of whether to authorize a pass (badge) is made by the Government. Participation in the rapid pass program is optional. The number of gates open to non-registered Contractor personnel will be limited to gates which can safely accommodate traffic backups. However, all gates will be open to rapid pass registered Contractor personnel. Contractors who choose not to participate in the rapid pass program will be required to obtain a daily pass.
1.12.8.1. Installation access requirements and procedures may change during the term of the contract. The Contractor shall comply with all changes, and such compliance shall not be grounds for a request for an equitable adjustment or other contract modification.
1.12.9. Contractor Advertising. The Contractor shall not place or display advertising of any kind on Government property.
1.12.10. Key Personnel. The personnel listed below are considered essential to the work being performed hereunder. Prior to substituting, removing, replacing, or diverting any of the specified individuals, the Contractor shall notify the KO fifteen (15) working days in advance and shall submit a written request and justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this Contract. The proposed substitution of personnel must meet or exceed the education, experience, and other technical requirements of the personnel being replaced. No change in personnel shall be made by the Contractor without the prior written consent of the KO. However, in urgent situations, as determined or agreed to by the KO, an oral request to substitute key personnel may be approved and subsequently ratified by the KO in writing. Such ratification shall constitute the consent of the KO required by this paragraph. The KO will notify the Contractor within ten (10) working days after receipt of all required information of the decision on the substitution(s). In the event the proposed substitution of key personnel does not meet or exceed the education, experience, and other technical requirements of the personnel being replaced, the Government reserves the right to require continued performance of previously approved key personnel or to require substitution of acceptable replacements for the individuals specified below. The key personnel listed below may, with the consent of the contracting parties, be amended from time to time during the course of the Contract to either add or delete personnel as appropriate.
Construction Superintendent
Construction Project Manager Construction Safety Manager Construction Quality Control Manager
1.12.11. Supervision of Contractor Employees. The Government will not exercise any supervision or control over Contractor or Subcontractor employees while performing work under the contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the Government for Contractor or Subcontractor employees.
1.13. ADMINISTRATIVE
1.13.1. Conferences / Meetings. The Contractor shall attend post award conferences convened by the contracting activity or contract administration office. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the KO will apprise the Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. Contractor shall document attendance, discussions and outcomes of meetings (meeting minutes) and digitally disseminate information to persons in attendance.
1.13.2. Data Rights. The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.13.3. Contract Drawings and Specifications. The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the KO. The Contractor shall check all drawings furnished immediately upon receipt; Compare all drawings and verify the figures before laying out the work; promptly notify the KO of any discrepancies; Be responsible for any errors that might have been avoided by complying with this paragraph; and Reproduce and print contract drawings and specifications as needed. In general large-scale drawings shall govern small-scale drawings; and the Contractor shall follow figures marked on drawings in preference to scale measurements. Omissions from the drawings or specifications or the mis-description of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or mis-described details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms.
2.1. Definitions. Federal Acquisition Regulation (FAR), Dictionary of US Army Terms, AR 310-25 and
Authorized Abbreviations and Brevity Code, AR 310-50, are the references for definitions and acronyms not listed below.
2.1.1. Contract Administrator. The official Government representative delegated authority by the KO to administer a contract. This individual is normally a member of the appropriate Contracting/Procurement career field and advises on all technical contractual matters.
2.1.2. Contractor. A supplier or vendor awarded a contract to provide specific supplies or services to the Government. The term used in this contract refers to the prime.
2.1.3. Contracting Officer (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
2.1.4. Contracting Officer’s Representative (COR). An employee of the U.S. Government appointed by the KO to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has the authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.5. Controlled Area. A controlled space extending upward and outward from a specified point. This area is typically designated by a commander or director, in which sensitive information or operations occur and require limitations of access.
2.1.6. Deliverable. Quantifiable goods or services that will be provided as specified in the contract.
Deliverables can be tangible or intangible items as a portion or part of the development process, function, or characteristic of a project; may include non-manufactured things such as, photographs, meeting minutes and-or reports.
2.1.7. Physical Security. Actions that prevent the loss or damage of Government property.
2.1.8. Quality Assurance Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.
2.1.9. Quality Control. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.10. Subcontractor. One that enters into a contract with a prime Contractor. The Government does not have privity of contract with the Subcontractor.
2.1.11. Work Day. The number of hours per day the Contractor provides services IAW the contract.
2.1.12. Work Week. Monday through Friday, except for Federal holidays unless specified otherwise.
2.1.13. Acronyms.
AFARS Army Federal Acquisition Regulation Supplement APM Alternate Project Manager ANSI American National Standards Institute AR Army Regulation AT Antiterrorism CA Corrective Action CDR Contract Deficiency Report CFR Code of Federal Regulations CMR Contract Manpower Reporting
COR Contracting Officer Representative CQC Contractor Quality Control CRM Cultural Resource Manager DA Department of the Army DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense
DPW Directorate of Public Works DWG Drawing EPDM Ethylene Propylene Diene Monomer FAA Federal Aviation Administration FAR Federal Acquisition Regulation FPCON Force Protection Condition HVAC Heating, Ventilation and Air Conditioning GIS Geographic Information System IAW In Accordance With IAQ Indoor Air Quality ICC IBC International Code Council International Building Code IDIQ Indefinite Delivery Indefinite Quantity JER Joint Ethics Regulations KO Contracting Officer KTR Contractor KS Contract Specialist MUTCD Texas Manual of Uniform Traffic Control Devices NFPA National Fire Protection Association NHPA National Historic Preservation Act NLT No Later Than NTP Notice to Proceed OPSEC Operation Security OSHA Occupational Safety and Health Administration POC Point of Contact QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control SF Square Feet SMACNA Sheet Metal and Air Conditioning Contractors National Association SOW Statement of Work TPO Thermo Poly Olefin USACE United States Army Corps of Engineers RFI Request for Information UFGS Unified Facilities Guide Specifications
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. Government Furnished Property – NA.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Items and Responsibilities.
4.1. Contractor Furnished Items. Everything included in this paragraph and its subparagraphs is basic to the contract and should be included in the contract price.
4.1.1. The Contractor shall provide all labor, supervision, transportation, vehicles, supplies, equipment, and materials required to perform work under this contract. The Contractor shall, as necessary provide all equipment needed to perform the Scope of Work safely and to the requirements of the SOW.
4.2. Materials. The Contractor shall furnish all materials and supplies as necessary to meet the requirements under this contract.
4.3. Equipment. The Contractor shall provide all required equipment to meet the requirements under this contract, e.g. aerial lifts, forklifts, cranes, fencing, dumpsters, etc.
4.4. Services. Required amounts (for contract performance) of water/electricity may be available to the Contractor from existing system outlets and supplies. The Contractor shall, at own expense, make all temporary connections and install distribution lines and extensions as required, to perform the work and maintain safe operating conditions. All temporary lines shall be furnished, installed and connected, and maintained by the Contractor in a workmanlike manner satisfactory to the KO and shall be removed by the Contractor at their own expense prior to final acceptance of the project. The Government will not be liable for any loss or damages suffered by the Contractor which may result from failure or interruption of any of the above utility services. Should the Contractor request a location for use as administrative functions, the Contractor shall be responsible for coordinating with utility providers, providing and installing the required meters.
4.5. Facilities, Security of Storage Area. If the Contractor elects to utilize the storage area made available by the Government, the Contractor shall be responsible for constructing a fence…