DPW-As-built_requirements-Memo-3-29-16_(b).pdf
PDF 229 KB Posted
- Attached to
- New Sidewalk Construction Federal contract opportunity
- Solicitation number
- W911SG-18-R-0070
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_Released.pdf | ||
| DWG_-_New_Sidewalk_along_Chaffee.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 29, 2016
Lorenzo Molina (915)569-5520 Lorenzo.m.molina.civ@mail.mil
The following are the requirements for turning over as-built drawings to the Fort Bliss DPW Master Planning division.
1. 1 set of Autocad DWG files. (2CDs)
2. 1 set of PDF files. (2CDs)
3. 1 set of mylar hard copies.
4. The above must contain all the required disciplines for a complete and viable product, i.e. general, civil, architectural, landscaping, irrigation, plumbing, mechanical, electrical, fire and etc.
5. The drawings shall be stamped 'as-built' in the bottom right hand corner underneath the title block.
6. All modifications and RFI's shall be incorporated into the drawings and no drawings shall be marked up (or in other words "Red lined").
7. All external reference (XRef) files shall be included.
8. All external reference (XRef) files shall bound to make each drawing sheet.
9. Any maps including all civil drawings must be in a viable coordinate system. If the initial maps are received from Master Planning they will be in Texas State Plane Central FIPS 4203 NAD 1983 or GCS 1984 UTM 13N.
10. All drawings will have accurate dimensions.
11. All piping and ducting will have accurate sizes.
12. All underground utilities will have accurate depths listed.
13. All drawings sets shall be coherently organized not divided into fast track/non fast track or any other incomprehensible package.
14. All turning points, brass caps, survey points, etc will have their pertinent information listed on the drawings.
15 Internal engineering projects and PRIDE should follow these requirements also.