Amendment_2-W911SG-18-R-0067.pdf

PDF 792 KB Posted

Attached to
Levee Repair
Solicitation number
W911SG-18-R-0067
Issued by

About this file

Amendment 2 -W911SG-18-R-0067

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011148556

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Incorporate the RFI's answ ers into the solicitation.

2. Include as an attachment the final plans revised named: DPW047008P FINAL PLANS (REVISED) AUGUST 2018- FY18 LEVEE REPAIRS SW SEGMENT

3. Incorporate revised Section of the SOW 31 11 00 CLEARING AND GRUBBING as an attachment named: Section 31 11 00 Clear&Grub.

4. Incorporate revised Section of the SOW 31 37 00 RIPRAP as an attachment named: Section 31 37 00 Riprap.

5. Incorporate revised Section of the SOW 35 41 00 LEVEE CONSTRUCTION as an attachment named: Section 35 41 00 Levee Construction

6. All other terms and conditions of this solicitation remains the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911SG18R0067

X 9B. DATED (SEE ITEM 11)

10-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Sep-2018

CODE

MICC-FT BLISS W911SG

111 PERSHING RD

FT BLISS TX 79916

W911SG 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911SG18R0067

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

RFI'S ANSWERS

RFI Levee Repair

W911SG-18-R-0067

1) Does engineering believe there is enough rip rap material in the bottom of the Arroyo to produce all the rip rap that is required for the complete project? Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

2) If there is not enough rip rap in the arroyo bottom will the contractor be required to import the remaining required amount of rip rap? Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

3) Will the borrow pit be used by WSMR personnel as well as other contractors during this project? Ans.

Yes

4) Is the rip rap wire covered or in gabions? Ans. No

5) For the levee repair project. Will it be needing marsh Buggy operation? Ans. No

6) Can the limits of clearing and grubbing be clarified? Construction Keyed Note 2 on sheet 3 indicates to clear and grub in the area necessary for the proposed improvements which would include the work associated with Construction Keyed Note 7 on sheet 3, but Spec Section 35 41 00 paragraphs 3.2, 3.3 &

3.4 indicate to clear & grub areas to receive embankment. Ans. See revised sheet 3 for the limits of clear & grub to be within the project’s limit of construction shown.

7) Specification Section 35 41 00 Paragraph 2.2.2 indicates that it is estimated that the screened Rip Rap will cover 50% of excavated material. Will further compensation be provided if the yield of screened rock is less than 50%? Ans. See specification Section 35 41 00 Paragraph 2.2.2; screening existing material is no longer required.

8) Can an estimated ratio of >4” rock and >12” rock be provided for what is anticipated to yield from the screened material? Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

9) What are the limits of Rip Rap Placement, and can a plan sheet be provided that clearly shows the rip rap limits? Plan Sheet 4 has two different cross sections that indicate the placement of >4” Rip Rap and >12” Rip Rap, but Construction Keyed Note 4 on sheet 3 does not clearly identify the limits of the two types of Rip Rap placement nor does the plan view on sheet 3. Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

10) Construction Keyed Note 4 subsection a on sheet 3 indicates to place the >4” Rip Rap from GPS location 3583478.096N 358797.867E to GPS location 3584228.524N 358809.498E. This note seems to indicate that the contactor is to place >4” Rip Rap from the proposed rebuilt crossing ramps at the north end of the Levee reconstruction to a distance of 2457 LF north of the previously mentioned crossing. Is this the true intent or can the limits of the >4” Rip Rap placement be provided/clarified? Ans. See revised drawings; riprap is no longer required to the north of the proposed rebuilt crossing ramps.

11) It is mentioned in the bidding documents that the contactor is to stockpile any existing base course for reuse on the project, but at the site visit it appeared that there was only a very limited amount of existing base course at the north end of the project located by the crossing ramps. Can the limits of existing base course be provided to the bidding contractors so they can accurately quantify the amount of base course that will be stockpiled and how much additional base course will be required to cover the crest of the levee? Ans. See revised drawings, sheet 4 shows existing base course.

12) Is the Rip rap running the entire length of the levee from gps location to gps location? Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

13) If there is not enough rip rap produced from the bottom of the arroyo is the contractor required to import the remaining amount to finish the Rip Rap section? Ans. See revised drawings deleting screening and requesting for the contractor to import and install rock riprap.

14) Specification 35 41 00 Levee Construction section 1.4.1 states that loose sedimentation obtained from its removal from the arroyo and/or clearing and grubbing are not allowed to be reused as embankment or backfill material. Is it the intension that the contractor will be required to obtain all embankment and/or backfill material from the proposed borrow location and no cut material from the arroyo will be allowed to be used? Ans. Yes; the material from the arroyo is sedimentation from the mountains and does not have engineering properties.

(End of Summary of Changes)