QUESTION_for_CCTV_17_SEPT_18.docx

DOCX document 12 KB Posted

Attached to
Closed Circuit Television Network Video Recorders
Solicitation number
W911SG-18-R-0042
Issued by

About this file

Question and Answer

View the file

Other files

File Type Posted
Amendment_0001_Correcting_Proposal_Due_Date_for_CCTV.pdf PDF
QUESTIONS_ASKED_AND_ANSWERS.docx DOCX document
ACCESS_TO_FORT_BLISS.docx DOCX document
NOTICE_OF_PRE._Proposal_Site_Visit_docx.docx DOCX document
Buffalo_Soldier_ACP_Images.docx DOCX document
MSG_Pena_ACP_Images.docx DOCX document
Cassidy_Gate_Images.docx DOCX document
W911SG-18-R-0042_Soliciation_for_CCTV.pdf PDF
Old_Ironsides_ACP_Images.docx DOCX document
PWS_DES_ACP_Camera_System_QA_reviewed_corrections_12_July_2018.docx DOCX document
PFC_Minue_ACP_Images.pdf PDF
CSM_Barreras_ACP_Images.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION

1) In section 5.1.6 It states that the contractor shall use existing conduit for the installation of the cameras. Is the installer responsible for non-existing pathways necessary to complete this project? Ie conduit, trenching, poles?

ANSWER:

Yes, contractor is responsible for non-existing pathways (i.e. conduit, trenching, poles, etc.) necessary to complete the project.