PERFORMANCE WORK STATEMENT (PWS)
Event Logistics Services for Ranger Rendezvous 2019
75TH Ranger Regiment-RHQ Fort Benning, GA
POP: 08-12 JULY 2019
POC: SSG Atencio, Ryan- Contracting/Acquisitions NCOIC
Part 1
General Information
1. GENERAL: This is a non-personnel services contract to provide event logistics services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein.
Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform event logistics services as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.
1.2 Background: The mission of Ranger Rendezvous in Fort Benning, Georgia is to provide a place and time to build morale and unit cohesion by participating in a Regimental change of command ceremony for 75th Ranger personnel. This will effectively contribute to the mental, physical, and social enrichment of participants.
1.3 Objectives: -Execute a successful event by providing basic logistics services.
- Reduce amount of organically produced manpower needed to run the event so that there can be maximum participation by Rangers
1.4 Scope: Event logistics services. Services include planning, coordinating, set up, tear down, and cleanup for the post-CoC reception events.
1.5 Period of Performance: 08-12 July 2019
1.6 General Information
1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. Quality control plan shall be delivered within 30 days after contract award. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.
1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.6.3 Recognized Holidays: Contractor is NOT required to perform services on holidays.
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
1.6.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 8a.m-4p.m Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.6.5 Place of Performance: The work to be performed under this contract will be performed at three locations on Fort Benning, GA. They are Freedom Hall, Fryer Drop zone, and Stewart-Watson Field. Contractor shall coordinate with the COR to be shown all locations.
1.6.6 Type of Contract: The government will award a Firm Fixed Price contract.
1.6.7 Security Requirements: None
1.6.8 Special Qualifications: Have a minimum of 5 years executing similar events, with examples of past work/performance.
1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
1.6.10 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract:
perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.11 Key Personnel: The follow personnel are considered key personnel by the government: contract manager/alternate contract manager. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 8:00 a.m. to 4:30p.m, Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1. DEFINITIONS:
2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications.
This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance
QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1 Facilities: The Government will provide Freedom Hall, Fort Benning, GA for the contractor staff to provide the support outlined in the PWS.
3.2 Utilities: The Government will provide all utilities in the facility will be available for the contractor’s use in performance of tasks outlined in this PWS. The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2. Materials: The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this PWS.
4.3. Equipment:. The Contractor shall provide all tables, chairs, lighting, sound equipment, cooling equipment, tents, shade covers, table cloths, eating and serving utensils, golf carts or equivalent transportation, generators, road cones, traffic barriers, trash receptacles, trash bags, cleaning equipment, cleaning products to meet the requirements under this PWS.
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1. Fryer DZ Static Display 08 July 2019: The contractor shall provide, stage, and pick up golf carts, or equivalent transportation at Fryer Drop Zone static display and jump observation area. (For drop off point, please see TE 1.) These golf carts are intended to assist the large population of elderly/disabled Rangers and their families that have to park and walk a long distance to view the jump. Exact pick up and drop off times are to be coordinated with the COR no later than 1 week prior to event execution.
5.1.1 Tent/Cooling Fan Set Up Fryer DZ Observation Area: Contractor shall set up shade tents and cooling fans, and misters over the jump observation area bleachers. Jump Observation overhang has power outlets that can be used. (See TE 3.)
5.2 Event Set Up- Stewart Watson Field 09 July 2019: Contractor shall set up shade tents, chairs, and cooling fans, and misters on Stewart Watson Field. See TE 4 for location. Stewart Watson Field has power outlets in 100m increments around the whole field. Exact time and location services are to be performed will be decided during the walkthrough, or no later than 1 week prior to event execution.
5.3 Post Change of Command Ceremony 10 July 2019: Contractor shall provide all materials, equipment, and labor to setup, and tear down, post COC ceremony. Ceremony shall consist of no less than 1500 people.
Contractor shall provide table clothes, tables, serving tables, and chairs, for 1500 personnel. Table clothes shall be CLOTH, plastic IS NOT acceptable. Chairs shall be decorative, with covers. Fold up type ARE NOT acceptable.
Cleanup shall include sweeping, mopping, and carpet cleaning up to 10,000sq feet of Freedom Hall. Exact time for services to be executed shall be given no later than 1 week prior to services being rendered. (See TE 5)
5.4. CONTRACTOR MANAGEMENT REPORTING (CMR) : The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or also know as the Contracting Officer’s Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors); (6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of
Contractor and sub-Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.
PART 6
ATTACHMENT/TECHNICAL EXHIBIT LISTING
6. Attachment/Technical Exhibit List:
6.1. Attachment 1/Technical Exhibit 1 – Performance Requirements Summary
6.2. Attachment 2/Technical Exhibit 2 – Deliverables Schedule- contractor shall provide deliverables schedule no later than 3 days prior to events starting.
6.3 Technical Exhibit 3/3.1- Fryer DZ Overhead view and concept of setup
6.4 Technical Exhibit 4- Stewart Watson Field Overhead view and concept of setup
6.5 Technical Exhibit 5- Freedom Hall overhead View
TECHNICAL EXHIBIT 1
Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective (The Service required—usually a shall statement)
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
The contractor shall complete all tasks detailed in paragraph 5-Specific Tasks
The contractor provided all services outlined in paragraph 5- Specific Tasks
Zero Deviation 100% inspection
TECHNICAL EXHIBIT 2
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To Outline of all materials, labor, and equipment necessary to complete all tasks outlined in Paragraph 5- Specific Tasks
Within 30 days of contract award
3 copies within 30 days of contract award
Paper/Hard Copy or email
COR/COR Email
TECHNICAL EXHIBIT 3
FRYER DZ, FORT BENNING, GA
TECHNICAL EXIBIT 3.1
DECKER STRIP (RIGHT NEXT TO FRYER,DZ)
TECHNICAL EXHIBIT 4
STEWART WATSON FIELD, FORT BENNING,GA
TECHNICAL EXHIBIT 5
FREEDOM HALL FORT BENNING, GA