SOW_Bldg. 756_Temporary Boiler_2024.pdf
PDF 80 KB Posted
- Attached to
- WEST POINT TEMP BOILER- BLDG 756 Federal contract opportunity
- Solicitation number
- W911SD-24-R-0066
About this file
This scope of work document outlines requirements for a temporary steam boiler installation at Building 756 at the United States Military Academy in West Point, New York. The contractor shall supply, install, test and operate a 800hp/250psi transportable steam boiler with natural gas connections from May 22nd to June 22nd, 2024. On-call maintenance and repair services are also required during the period of operation. The contractor must attend a mandatory site visit on March 14th and submit product specifications, a work plan, health and safety plan, and quality control plan for review. Within 10 days of completion, the contractor shall submit all records of the work including inspection reports, test reports and manufacturer's documentation.
The related federal contract opportunity is a request for quote for the above temporary steam boiler requirement. Quotes are due by April 8th, 2024. This requirement is a 100% small business set-aside under NAICS code 238220. Firms must be registered as a small business in SAM.gov to be eligible for award. Offerors must attend the mandatory site visit, provide product specifications, and submit a signed SF-1449 form including pricing and required clauses. The award will be issued by the Mission and Installation Contracting Command, Installation Contracting Office at West Point, New York.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911SD-24-R-0066- TEMP BOILER -BLDG 756.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DPW, CONSTRUCTION, ESTIMATING & CONTRACT SERVICES BRANCH
4th Floor Bldg. 667A
West Point N.Y. 10996
Subject: Scope of Work
Contract name: Bldg. 756 Temporary Boiler - Summer 2024
Project Location: Bldg. 756 Bradley barracks courtyard
Date: 17 January 2024
Scope:
Contractor to provide all labor, material, equipment, and supervision in accordance with all applicable codes and specifications to the following locations at USMA West Point, NY 10996:
1) Supply, install, and test operate one 800hp/250psi max pressure transportable steam boiler with natural gas connections, on-call service, and chemical treatment for the duration of boiler operation.
2) Temporary steam boiler shall be delivered and installed and fully operational from May
22nd to June 22nd, 2024.
Description of Work:
Contractor shall install, inspect, and test the installation and operation of the transportable steam boiler no later than May 22nd for start of full operational service. On June 22nd, the contractor will disconnect and demobilize the temporary boiler and all associated material and equipment.
1) Supply and install one transportable steam boiler to Bldg. 756, and have all associated work needed for installation completed and the boiler ready and in operation by May 27th.
The existing building power and disconnect is 200-amp, 230/480 VAC. The contractor must supply and install all electrical connections from boiler equipment to building power, supply and install all steam piping, condensate piping, and fittings as necessary for a complete installation from temp boiler to building connections for full operational condition. Supply and install all temporary electrical cable and appurtenances needed to connect boiler to the supplied electrical power panel. The designated site location and attachment locations (electrical disconnect, water connections, piping, etc.) to existing building systems will be shown at site visit. Supply and install natural gas piping, fittings, and regulator needed for connections from boiler to building gas supply. The contractor shall have a qualified boiler operator, laborer, electrician, pipe fitters (steam) for this project at the site visit to review this location and determine the exact details (specific location, attachment details, piping length, electrical, etc.). The contractor shall have a qualified electrician for all the electrical cables, and connections. The government PM will be notified when the boiler is ready to be connected and PM will then notify Electric shop for terminations.
2) Supply all labor and materials required to disconnect existing building piping for temporary boiler hook-up. Supply all labor and materials required to reconnect all piping after temporary boiler are removed. All existing system components, electrical connections, structures, roadways, etc. shall be returned to their original existing conditions upon completion of this work for acceptable closing.
Specific Requirements:
a) All work shall be performed in accordance with applicable federal, state, local, and
USMA requirements laws and regulations.
b) Supply material needed to support temporary boiler at site locations; Plywood, chalks, etc. shall be installed under and chalked around tires and front trailer supports to protect the surface underneath boiler trailer.
c) Remove building louvers as necessary to run piping and electrical cables into building.
Install temporary enclosures around temporary piping to cover the opening where louvers were removed.
d) Contractor must install carbon steel piping to connect boiler to building connections and welding of branch connections, fittings, and flanges shall meet all requirements of the ASME
Boiler and Pressure Vessel Code regulations, and OSHA standards. Newly installed steam and condensate piping shall be IAW: ASTM A234 Pipe Fittings of carbon steel for moderate and high temperature service and ASME B36.1 Standardization of dimensions of welded and seamless steel pipe for high and low temperatures and pressures.
e) Supply all supervision, labor, equipment, and materials needed for installation and removal of temporary boiler.
f) In addition to the work described above, the contractor shall also provide on-call maintenance and repair service for their supplied equipment during the periods of operation as described above. Contractor shall respond within two hours of placed call. After normal work hours, the contractor shall respond within four hours of placed call. The COR will initiate these on-call maintenance and repair services. There will be no additional payment for repair parts or materials needed as these are included in the cost of provided operational chiller units.
Submittals:
The contractor shall provide the following submittals as a minimum for review and approval.
The government will review each deliverable:
1) Contractor bid/proposal:
Work plan for the execution of the design, procurement, installation, and testing of the work.
This plan shall describe how they will be executed and how it will be accomplished so as to not interfere with the ongoing operations of the affected buildings and facilities.
Coordination / Schedule:
Contractor shall attend a site visit/existing conditions survey as scheduled by the COR. The contractor shall:
1) Coordinate the date and time of the work with COR within 5 days of Notice to Proceed.
2) Complete material, equipment, delivery, and installation by May 27th.
Quality Control:
The contractor shall develop a Quality Control Plan to ensure that the requirements of the contract are provided as specified. This plan shall be submitted for review and approval prior to executing any design or construction work. The plan shall contain the minimum of the following:
1) An inspection program covering all the services to be performed under this contract.
2) A description of the process to be used for verifying compliance with the contract requirements including non-destructive examinations of welds.
3) The methodology to be used for identifying deficiencies in the quality of services performed before the level of performance has an adverse impact on the execution of the project.
4) A description of the daily quality control reports to be generated during the performance of the work including photographs of the work.
5) Qualifications of the QA/QC representative.
Health, Safety and Environmental Protection:
The contractor shall develop and submit for review and approval their Health and Safety Plan along with their Environmental Protection Plan for this work. These plans shall cover the being performed including fall protection. These plans shall comply with all federal, state, local, and
USMA requirements, laws, and regulations.
Reports / Records:
Within 10 days of completion of construction, the contractor shall submit all records of the work including but not limited to quality inspection reports (including photographs), test reports, and manufacturer’s documentation.