This performance work statement outlines requirements for a portable restroom trailer to be delivered to West Point outside of Patton, New York. The contractor shall provide a 10-station trailer with separate men's and women's sides by September 1, 2023 for a minimum of six months with the option to extend on a month-to-month basis for an additional six months. The men's side shall include three urinals, two toilet stalls, and two sinks, while the women's side shall have five toilet stalls and two sinks. The trailer must have central air and heat, mirrors, and an aesthetically pleasing appearance. The contractor will be responsible for hooking the trailer up to existing water and electricity, emptying the waste tank every other day, and reporting labor in the Army Contractor Manpower Reporting Application. Related solicitation W911SD-23-R-0196 from the Department of the Army seeks to award a contract for the portable latrine services described.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
The Contractor shall deliver a 10 station restroom trailer with separate men’s and women’s sides.
No handicap access is needed.
Men’s side shall have 3 urinals, 2 toilet stalls and 2 sinks. Women’s side shall have 5 toilet stalls and 2 sinks.
The trailer shall have central air and heat and mirrors and shall be aesthetically pleasing.
The contractor shall provide keys to West Point so that we are able to lock the unit when not in use.
The trailer shall be delivered to West Point outside of Patton, hooked up to water line and electrical, and be operational and ready for use by 1-September, 2023 for a minimum of 6 months with the option to extend month to month after that for up to an additional 6 mos.
The contractor shall hook the trailer up to existing water and electricity.
The contractor shall empty of the waste tank every other day (MWF or TTS) The contractor shall report manpower in the Army Contractor Manpower Reporting Application https://cmra.army.mil/. (See attached for complete details.)