SCOPE OF WORK
1.0 SCOPE
Contractor shall provide all labor, material, equipment and supervision in accordance with all applicable codes and these specifications to: To supply, install and test one 125 Ton Trailer
Mounted air cooled Chiller at Bldg 2101 Spellman Hall and supply, install and test one – 400 Ton
Trailer Mounted Air Cooled chiller with pumps at Bldg 735 Scott Barracks, West Point, NY 10996.
All Chillers shall be installed and fully operational from May 1stth thru Oct 15th 2016.
2.0 DESCRIPTION OF THE WORK
Contractor shall install, inspect and test the installation of the trailer mounted Chillers not later than May 1st. On Oct 15th Contractor shall remove the temporary chillers and all associated material and equipment.
1) Supply and install one 125 Ton Chiller at Building 2101 and have all associated work needed for installation completed and the Chiller in operation by May 1st. The temporary chiller shall use the existing building AC pumps. Building power is 208/230 VAC. Supply chiller to match power or if required install transformer to use with the temporary Chiller and house power. Install approx. 200 feet of 6” rubber hose with ends to attach chiller to building piping. Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary Electrical cable and appurtenances needed to connect Chiller to the existing disconnect in building. Proposed site location and attachment locations to existing building systems will be shown at pre-bid site visit. Contractor shall have HVAC subcontractor on pre-bid site visit to review this location and determine the exact details
(specific location, attachment details, piping/cable lengths etc.).
2) Supply and Install one 400 Ton Chiller with pump at building 735 and have all associated work needed for installation completed and Chiller ready to go for May 1st operation.
Chiller at this location will feed chilled water to Bldg 735 Scott Barracks and Bldg 745E Mac
Short. The temporary Chiller must have its own pump to operate properly with the existing building system. Existing building power and disconnect is 230/460 VAC. Supply Chiller to match existing power or if required install transformer to use with temporary Chiller and
House Power. Supply and Install 6” rubber hose with ends to attach Chiller to building piping. Supply and install all pipe fittings as necessary for a complete installation. Supply and install all temporary Electrical cable and appurtenances needed to connect Chiller to the existing disconnects in the building. Proposed site location will be shown at site visit. All building attachment locations (electrical disconnect, piping, etc) will be shown at pre- bid site visit. Contractor shall have HVAC contractor on pre-bid site visit to review this location and determine the exact details (specific location, attachment details, piping/cable lengths etc.).
4) Supply all labor and materials required to disconnect existing building piping for temporary chiller hook up. Then supply all labor and materials required to reconnect all piping after temporary Chiller is removed. All existing system components, electrical components, structures, roadways, etc. shall be returned to their existing condition upon completion of this work.
2.1 Specific Requirements
a) All work shall be performed in accordance with the applicable Federal, State, Local and USMA requirements, laws and regulations.
b) Supply material needed to support Temp Chiller at site location. Plywood, boards etc. shall be installed under the tires and front trailer supports to protect the surface under trailer.
c) Remove Building louvers as necessary to run piping and electrical cables into building 2101. Install temp enclosure around temp piping to cover the opening where louvers were removed.
d) Use rubber/hard piping to connect chiller to building. Flex hosing/piping shall not be used.
e) Supply all supervision, labor, equipment and materials needed for Installation and
Removal of Temp Chiller.
f) In addition to the work described above, Contractor shall also provide on-call maintenance and repair service of their equipment during the period of operation as described above. Contractor shall respond within two hours. After normal work hours, Contractor shall respond within four hours. The COR will initiate these on-call maintenance and repair services. There will be no additional payment for repair parts or materials as these are considered to be included in the cost of providing functional Chiller units.
2.2 Submittals
Contractor shall provide the following submittals as a minimum for review and approval. The
Government shall have 14 calendar days to review each deliverable:
i) With their bid/proposal:
- Work Plan for the execution of the design, procurement, installation and testing of the work. This plan shall describe how the work will be executed and how it will be accomplished so as to not interfere with the ongoing operations of the affected buildings and facilities.
2.3 Coordination/Schedule
Contractor shall attend a Site Visit/Existing Conditions Survey as scheduled by the COR. Contractor shall :
i) Coordinate the date and time of the work with the COR within 5 days of Notice to Proceed
iii) Complete material and equipment delivery and installation by May 1st.
2.4 Quality Control
Contractor shall develop a Quality Control Plan to ensure that the requirements of the contract are provided as specified. This plan shall be submitted for review and approval prior to executing any design or construction work. The plan shall contain as a minimum:
i) An inspection program covering all of the services to be performed under this contract
ii) A description of the process to be used for verifying compliance with the contract requirements including non-destructive examination of welds
iii) The methodology to be used for identifying deficiencies in the quality of services performed before the level of performance has an adverse impact on the execution of the project
iv) A description of the daily quality control reports to be generated during performance of the work including photographs of the work
v) Qualifications of the QA/QC representative
2.5 Health and Safety and Environmental Protection
Contractor shall develop and submit for review and approval their Health and Safety Plan and their Environmental Protection Plan for this work. These plans shall cover the work being performed including fall protection. These plans shall comply with all Federal, State, Local and USMA requirements, laws and regulations.
2.6 Records
Within 10 days of completion of construction, Contractor shall submit all records of the work including but not limited to quality inspection reports (including photographs), test reports and manufacturer’s documentation.