OF 1419 - Abstract of Offers - W911S722B0005.pdf
PDF 199 KB Posted
- Attached to
- Fort Leonard Wood Concrete IDIQ
- Solicitation number
- W911S7-22-B-0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATTACHMENT 4 QA Responses - W911S7-22-B-0005 final.pdf | ||
| W911S722B0005 Amendment 0001.pdf | ||
| ATTACHMENT 3 - FY23 Specifications.pdf | ||
| W911S7-22-B-0005.pdf | ||
| ATTACHMENT 1 - Task List.xlsx | XLSX spreadsheet | |
| ATTACHMENT 2 - DBA WD MO20220001 ao 5 Aug 2022.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION 1
3. DATE OPENED PAGE OF 2. DATE ISSUED
09/26/2022 10/28/2022 1 I 2 PAGES
4. ISSUING OFFICE
MICC - Fort Leonard Wood
8112 Nebraska Ave
Fort Leonard Wood, MO 65473
1. SOLICITATION NUMBER
W911 S7-22-B-0005
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. ►
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
Victor E. Richards, Contracting Officer
SIGNATURE DATE SIGNED
5. PROJECT TITLE 9. OFFERS
Concrete Construction IDIQ 8. GOVERNMENT ESTIMATE NO. 1 NO. 2 (Check A, B or C and complete D, E, and F) A. OFFEROR A. OFFEROR
□ A. HIRED LABOR Mass Crushing & Excavating Inc. Schulte Construction Inc.
B. REASONABLE CONTRACT B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
(Without Profit)
6. NUMBER OF AMENDMENTS ISSUED
x
C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
1 (Including Profit)
7A.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST. D. E. UNIT F. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
ITEM QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNTNO.
Base Year 2,012,990.00 8,390,304.50 2,394,800.00
First Option Year 2,033,119.90 8,642,013.64 2,457,270.00
Second Option Year 2,053,451.10 8,901,458.38 2,520,340.00
Total 6,099,561.00 25,933,776.52 7,372,410.00
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)
Yes Yes
Bid Bond 20% Bid Bond 20%
I
PAGE OF
I PAGES
ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are
CONTINUATION SHEET
received on a construction project. Each Continuation Sheet wil l accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of
13 and attach additional continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE 4. OFFERS (Continued)
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A. B. C.
ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
OPTIONAL FORM 1419A (11-88)
1. SOLICITATION NUMBER
W911S7-22-B-0005 2 2
Concrete Construction IDIQ
Heenan Construction, LLC
Yes
2,952,156.00
3,075,249.45
3,233,686.41
9,261,091.86Total
Bid Bond 20%
| OF 1419 - Abstract of Offers - Construction |
| Abstract page 2 |
| 2022-11-01T10:37:59-0500 | |
| RICHARDS.VICTOR.E.1091614746 |
File details come from the government source that posted it. Updated .