Attachment 1 Statement of Work Rev. 1

View the file

Other files

File Type Posted
Bid_Abstract,_W911S7-19-B-0002,_LORA_Cabin.pdf PDF
8204_a2v8_REV1.pdf PDF
8204_a3v8_REV1.pdf PDF
W911S7-19-B-0002-0001.pdf PDF
8204_P2v8_REV1.pdf PDF
8204_c1v8_REV1.pdf PDF
8204_P1v8_REV1.pdf PDF
Attachment_17,_Responses_to_Question_and_Answer,_W911S7-19-B-0002.pdf PDF
8204_FP1v8_REV1.pdf PDF
8204_s2v8_REV1.pdf PDF
8204_a1v8_REV1.pdf PDF
Sign_-_In_Sheet.pdf PDF
8204_P1v8.pdf PDF
8204_c1v8.pdf PDF
8204_s1v8.pdf PDF
8204_e4v8.pdf PDF
8204_e3v8.pdf PDF
8204_e1v8.pdf PDF
Attachment_2_Camden_County_Wage_Determination.pdf PDF
8204_P2v8.pdf PDF
8204_s2v8.pdf PDF
8204_M1v8.pdf PDF
8204_FP1v8.pdf PDF
Attachment_1_Statement_of_Work.pdf PDF
8204_a2v8.pdf PDF
W911S7-19-B-0002_LORA_Cabin.pdf PDF
8204_a3v8.pdf PDF
8204_a1v8.pdf PDF
8204_e2v8.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART IV SPECIFICATIONS

CONSTRUCT CABIN AT LORA

LOA 05696-8J, C.0006246

C8204.14

INDEX

SECTION NO. DESCRIPTION

DIVISION 1 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 33 00 Submittals

DIVISION 2 - SITEWORK

02 41 00 Demolition

DIVISION 3 - CONCRETE

03 20 00 Cast-In-Place Concrete 03 30 00 Concrete Reinforcing

DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry 06 61 16 Solid Surface Fabrications

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

07 41 13 Metal Roof Panels 07 84 00 Firestopping 07 92 00 Caulking and Sealants

DIVISION 8 - DOORS AND WINDOWS

08 11 13 Steel Doors and Frames 08 14 00 Wood Doors 08 71 00 Hardware 08 81 00 Glazing

DIVISION 9 - FINISHES

09 29 00 Gypsum Board 09 30 10 Ceramic and Porcelain Tiling 09 90 00 Painting and Coatings

DIVISION 10 – SPECIALITIES

10 28 13 Toilet Accessories 10 44 16 Fire Extinguishers

DIVISION 12 - FURNISHINGS

12 32 00 Manufactured Wood Casework

DIVISION 22 – PLUMBING

22 00 00 Plumbing, General Purpose

DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING

23 00 00 Air Supply, Distribution, Ventilation and Exhaust Systems 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 Thermal Insulation for Mechanical Systems

DIVISION 26 – ELECTRICAL

26 20 00 Interior Distribution System 26 51 00 Interior Lighting

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 64.00 10 Fire Detection and Alarm System, Addressable

DIVISION 31 – EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 93 00 Turf

CONSTRUCT CABIN AT LORA

LOA 05696-8J, C.0006246

C8204.14 POC: Michael Mueller/573-596-0914

DBA Wages

SECTION 01 11 00

SUMMARY OF WORK

1 DESCRIPTION OF WORK:

1.1 Work to be Done: The work consists of furnishing all plant, labor, equipment, supplies, and materials, and performing all work in accordance with these specifications and drawings as indicated at Fort Leonard Wood, Missouri.

1.2 Location: The site of the proposed work is in the Lake of the Ozarks Recreational Area of the Fort Leonard Wood Military Reservation, Fort Leonard Wood, Missouri.

2 PRINCIPAL FEATURES: The work to be performed will include, but not be limited to, the following principal features: Construct new wood framed cabin at Lake of the Ozarks Recreational Area consisting of concrete foundation, western red cedar siding and interior walls, cedar laminated flooring, standing seam metal roof and wood truss roof structure.

3 SEQUENCE OF WORK: The area concerned in this project is Government owned and will be in use during the course of this project.

4 SCHEDULING:

4.1 The Contractor shall schedule all activity at the job site through the DPW Contract Inspection Branch a minimum of 24 hours in advance of work.

4.2 Contractor shall schedule his working hours to coincide with the working hours of the military reservation. Normal working hours of the reservation are 7:30 a.m. to 4:00 p.m., Monday thru Friday, legal public holidays excepted. The Contractor shall not perform work on the reservations beyond the aforementioned working hours without the written approval of the Contracting Officer.

4.3 If the Contractor, for his convenience, desires to perform work during other than normal working hours or on other than normal workdays, he shall notify the Contracting Officer and the Directorate of Public Works Inspection Branch at least 72 hours in advance. The Contractor shall not perform work beyond the normal working hours or normal workdays without written approval of the Contracting Officer and the DPW Inspection Branch approval. The Contractor shall reimburse the Government for any additional expense occasioned the Government thereby, such as, but not limited to, overtime pay for Government inspectors, utilities service, etc.

4.4 Time extensions due to adverse weather or material lead time, must be received in writing prior to scheduled completion date 5 UTILITY INTERRUPTIONS: Coordinate with the Contracting Officer, DPW Contract Inspection Branch, and the user for any utility work that interrupts service to the facility, any area outside the facility, or any real property facility. Establish a schedule of interruptions listing starting and ending times of disconnection 48 hours prior to interruption.

6 FIELD MEASUREMENTS: The Contractor shall verify all measurements at the project site and shall be responsible for all dimensions, fittings, and the proper installation of all materials and equipment specified.

7 PERMITS: The Contractor shall be responsible for obtaining permits for each worksite.

7.1 Digging: A digging permit is required prior to ANY earthwork operations.

The DPW Contract Inspection Branch will assist the Contractor in obtaining this free permit.

7. 2 Land Disturbance: A land disturbance permit is required for any projects that disturb one (1) acre or more. Land disturbance is defined as any activity that disturbs the roots of vegetation such as clearing, grubbing and grading.

The Contractor shall apply for the permit from the Missouri Department of Natural Resources (MODNR), after the FLW Environmental Office has approved the permit application. MODNR by law may take up to 180 days to review and issue a permit.

Copy of the permit shall be forwarded to the DPW Environmental Office. The Contractor shall not begin land disturbance operations until they have received and complied with the MODNR permit. MODNR charges a fee for the permits.

7.3 Hot Work Permit: The Contractor shall obtain a written “Hot Work Permit” (DA Form 5383-R) prior to commencing all hot work outside an approved shop area. Permits will be issued by the FLW Fire & Emergency Services at Fire Station #1, Bldg. 580, Phone: (573) 596-0883. The Contractor shall be liable for any fire loss to Government property attributable to negligence on the part of the Contractor, including failure to comply with fire prevention measures prescribed by terms of this contract. The Inspection Branch will assist the Contractor in obtaining this free permit

7.4 Confined Space Permit: The Contractor shall obtain a written “Confined Space Permit” prior to commencing all confined space activity above and/or below ground. Title 29 CFR 1910.146 OSHA (Confined Space Entry) and FLW Regulation 385-7 sets forth the definition of confined spaces and establishes responsibility and procedures for protection of personnel that shall be entering, work in, and existing confines space. If a permit is required the Contractor shall contact the FLW Fire Department, Fire Station #1, Assistant Chief of Operations, Bldg 580, Phone: (573) 596-0883 prior to, and after the permit required entry is conducted.

The Contractor shall keep the permit copy within the work area until all workers have been accounted for after completion of the workday. The Inspection Branch will assist the Contractor in obtaining this free permit.

8 SAFETY REQUIRMENTS:

8.1 General Safety: During progress of work, the Contractor shall protect all personnel, whether Government or civilian, from any and all safety hazards caused by the construction operations. The contractor shall follow all Federal, State and local laws in accordance with 29 CFR 1910 (General Industries Standards), and 29 CFR 1926 (Construction Standards).

8.2 Fire Prevention: The current version of FLW Regulation 420-2 “Post Fire Regulations” is by this reference made a part of this solicitation and resultant contract. The Contractor’s operation shall conform to all applicable portions of this document. All personnel entering on duty as Contractor’s employees shall be instructed in the fire prevention program of the Post and shall be advised of the requirement of the Post Fire Regulations as they pertain to this particular contract.

8.3 Traffic Control: Contractor shall provide all temporary signs and markers as necessary to maintain safety in the worksite. All signs shall conform to the latest edition of the Manual of Uniform Control Devices (MUTCD) and shall be coordinated with, and approved by, DPW Inspection Branch. Contractor shall ensure road user movement is inhibited as little as practical.

9. SPECIAL REQUIREMENTS:

9.1 Use of Fire Hydrants – The temporary use of fire hydrants as sources of water is not authorized without prior approval by the Fire Department, 596-0886.

Fire hydrant connections shall include an approved backflow preventer. Use of backflow preventers must comply with Missouri Department of Natural Resources, Division 60, Public Drinking Water Program, Chapter 11 – Backflow Prevention, Title 10CSR60-11. Government furnished backflow preventers shall be utilized and are available at Bldg. 1601, Water Treatment Plant on a first come basis. The

Contractor shall be required to sign a hand receipt prior to obtaining a backflow preventer. The Contractor shall be accountable to return the checked out backflow preventer equipment undamaged and as soon as possible. The contractor shall furnish and use an approved fire plug wrench to open and close the hydrant. Pipe wrenches shall not be used. When the hydrant is not being used it shall be shut off. When the need for the hydrant is finished, the hydrant shall be shut off , the temporary connection and backflow preventer shall be removed, the fire hydrant caps shall be replaced and the Fire Department shall be notified that the hydrant will no longer be used.

9.2 Building Number – Contractor shall provide a facility number sign with the street address included. Display in a prominent location near the entrance of the job site. Sign numbers shall be white, minimum of 4” tall on brown background, Bold Helvetica style. Sign shall be mounted 7' from ground to bottom of sign and shall be maintained in a legible condition from start of actual work on site to final acceptance.

9.3 The Contractor shall enter into a contract with the Service Owner (SO), American Water Jeff Hollis at jeffery.hollis@amwater.com, for the SO to install and “tap in” the new utility infrastructure from the new facility point of demarcation to the SO’s utility system. The Contractor shall pay directly to the SO. A “Connection Charge Agreement” needs to be signed between the Contractor and the SO. The SO will not be a construction sub-contractor.

10. SECURITY:

10.1 In unoccupied facilities, the Contractor shall be responsible for the security of the facility; i.e., all exterior doors shall be locked, windows closed and locked, etc.

10.2 The Contractor shall not be on site without prior notification to the DPW Contract Inspection Branch.

10.3 Contractor personnel shall have valid civilian ID’s.

11 APPLICABLE PUBLICATIONS/REFERENCES: The publications referenced herein after shall be the most recent at the time of solicitation, unless otherwise specified at the beginning of each Specification Section under paragraph 1. APPLICABLE PUBLICATIONS and or REFERENCES.

12 WORKSITE HOUSEKEEPING:

12.1 The Contractor shall remove all trash and disposal material from the worksite before the end of each day, to the extent it is consistent with standard construction practices on Government work sites. The Contractor shall take all possible precautions to maintain the work site, at all times, in a condition that will prevent damage or injury to person or property, Government or otherwise. The above precautions shall include protection from weather conditions. The Contractor shall be responsible for all damages caused by the negligent acts or omissions of his employees, sub-contractors, or agents during Contract performance.

12.2 Materials to be used within 1 week of delivery and scrap material to be used as work progresses shall not be required to be in screened area. However, all such items shall be placed in an orderly manner (i.e. dirt, rock, etc., in piles and stackable items such as pipe, brick, lumber, etc., stacked off the ground on pallets in an orderly manner).

12.3 Grass and weeds at work/storage site shall be kept at a height of 4”or less. Work site/storage site shall be policed for trash and disposal material a minimum of once per day.

12.4 All trailer and material storage sites shall have an identification board/sign, with company and job name on it, i.e. ABC Construction – ABC building complex. Signs shall meet the following criteria: min 3’ X 3’ max of 4’ X 8’ in size, 3” high legible print, and be approved by DPW Inspection Branch.

13 RESPONSIBLITY FOR DAMAGE

13.1 Damage to Personal Property: The Contractor shall be solely responsible for all damage to Government and occupant personal property caused by the Contractors’ personnel, subcontractors, his agents, or by the performance of his work.

13.2 Damage by Negligence: Damage resulting in gas leaks, electrical outages, loss of heat during cold weather, water leaks, unsecured facilities, weather damage, or oil/hazardous waste spills shall be responded to by the Contractor within 2 hours and repaired within one workday. If the Contractor fails to comply with these requirements, the Government reserves the right to repair the damage and charge the cost to the Contractor. Contractor shall protect all areas through which he will be transporting demolition debris or construction materials.

Any damaged turf, sidewalks, roads, vegetation, site amenities, etc, shall be replaced or repaired by the Contractor prior to final Contract closeout.

14 DISPOSAL OF MATERIALS: All materials removed and not reused or designated as salvage material in this project shall become the property of the Contractor, unless otherwise specified, and shall be the Contractor's responsibility for lawful disposal.

14.1 The Contractor may use the Fort Leonard Wood Compost area for the disposal of wood chips, leaves, and grass clippings generated by this project.

14.2 All other wastes generated during Contractor operations shall be disposed of off post by the Contractor at his/her expense.

14.2.1 The disposal of demolition waste is regulated by the Missouri Department of Natural Resources under Chapter 260, Revised Statutes of Missouri and 10 Code of State Regulations Chapter 80-4. Such waste, in types and quantities established by the Department, shall be taken to a demolition landfill or a sanitary landfill off of the Installation for disposal. The Contractor shall provide any information requested by the landfill operator to complete forms required by the Missouri Department of Natural Resources or other Government-required landfill records.

14.2.2 Wastes classified as hazardous wastes under the Resource Conservation and Recovery Act shall be disposed of off the installation, unless otherwise specified in this contract. No hazardous waste shall be disposed of without prior review of the disposal documents, and the approval of the Contracting Officer and the Directorate of Public Works Environmental Coordinator, or his designated representative. The Contractor shall provide an original copy of the disposal document from the approved EPA or State permitted disposal facility for each shipment of hazardous waste generated in this project to the Contracting Officers Representative.

15 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES:

15.1 All Contractor and sub-contractor personnel performing tasks on this SOW shall comply with all applicable installation, facility and area commander installation/facility access and local security policies and procedures which will be provided to the Contractor by a Government representative upon written request to the Contracting Officer. Contractor shall provide all information required for background checks to meet installation access requirements as performed by the installation Provost Marshal Office, Director of Emergency Services or Security Office. Requesting Contractor shall submit request for installation pass to the KO at https://vcc1.icmvcc.com/im3500/. There is no charge to the Contractor for this pass. Contractor personnel shall comply with all personal identity verification requirements as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of the base contract to this task order, should the Force Protection Condition (FPCON) at any facility or installation change, the Government may require changes in Contractor security matters or processes.

15.1.1 In the event that the automated system at

https://jkodirect.jten.mil is not available (e.g., server problems), Level I AT Awareness Training can be provided by a qualified instructor. However, if the training is not completed online, the Level I AT Awareness Instructor qualification must be coordinated with the Installation Antiterrorism Officer (or Installation Security equivalent) and the resultant name(s) of approved instructors shall be provided to the KO.

15.2 Antiterrorism (AT) Level I Training: All contractor and sub-contractor employees requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training available at https://jkodirect.jten.mil.Users need to enroll in "Course #JS-US007-14" to receive credit for the training within 10 calendar days of contract award; or for new employees within 10 working days of beginning performance on this contract.

Contractor shall submit certificates of completion for all personnel to the KO within five calendar days of completion of the training. There is no charge to the Contractor for this training. The burden to complete this training is approximately 1-hour per employee.

15.3 iWatch Training: Within 10 calendar days of contract award and within

10 calendar days of new Contractor employees commencing work on this contract, all Contractor and sub-contractor employees shall review the FLW Directorate of Emergency Services (DES) web link for iWatch training located at http://www.wood.army.mil/LEC/iWatch/iWatch.htm. This locally developed training will inform employees of the types of behavior to watch for and how to report suspicious activity. Suspicious activity shall be reported to the KO. There is no charge to the Contractor for this review. The burden to complete this training is approximately 20-minutes per employee.

15.4 OPSEC Standard Operating Procedure/Plan (SOP): The KO will ensure the contractor (after selected) is aware of the MSCoE OPSEC Plan and is in compliance with the MSCoE OPSEC Plan during contract performance.

15.5 OPSEC Training: New contractor employees must complete Level I OPSEC training within 30 calendar days of their reporting for duty in accordance with AR 530-1. All contractors shall complete annual OPSEC Awareness training if the contract duration is longer than 30-days. MSCoE OPSEC Officer will provide training. Coordination of training shall be through Rick Bowser, (573)563-2402.

Proof of training, including a detailed listing of attendees, shall be provided to the KO. A nominal fee shall be charged to the Contractor for this training equal to 1-hour of Government time. The burden to complete this training is approximately 1-hour per training evolution. There are no restrictions to number of attendees in a given training evolution.

END OF SECTION

SECTION 01 33 00

SUBMITTAL PROCEDURES

1. GENERAL: All items of equipment and/or materials that are defined or described in the contract require submission in accordance with this section. Brochures, samples, certificates of compliance, test reports, as applicable, shall be submitted by the Contractor to the Contracting Officer, and approval given by the Contracting Officer before any equipment or material is installed under this contract.

1.1. All of the data required shall be submitted prior to inclusion into the Work. Approval of materials and equipment requiring color selection will be withheld until all of the required information has been submitted and is in the hands of the Contracting Officer. All submissions must be in sufficient detail to adequately determine that the item will meet the requirements of this specification.

1.2. All submittals shall be transmitted to the Contracting Officer for review and approval within 30 calendar days after contract award date on Engineer Form 4025 in quadruplicate. The forms shall be completed as directed. No submittal will be accepted unless it is on the subject form. The forms will be furnished to the Contractor by the Government. All attachments to the transmittal form, such as catalog cuts, brochures, certifications, etc., shall be submitted in four (4) copies.

1.3. The Contractor shall complete and submit to the Contracting Officer for approval, four copies of ENG Form 4288 Submittal register. At a minimum, the submittal register shall include a listing of all items listed in paragraph 2 of this Section. This submittal register shall be provided with the initial set of submittals the Contractor submits for approval. ENG form 4288 will be furnished to the Contractor by the Government. This register will be maintained by the Government to insure that all required materials are submitted and approved IAW the contract requirements.

1.4. Scheduling: A minimum of 14 calendar days will be scheduled for review and approval of material submittals and possible resubmittal of any items subject to approval. For shop drawings submittals, a minimum of 21 calendar days will be allowed for review and approval and possible resubmittal. Unless otherwise specified in the contract, the Notice to Proceed with performance will be issued within 50 calendar days after contract award date. If shop drawings are required, Notice to Proceed with performance will be issued within 60 calendar days after contract award date. The scheduling shall be coordinated with the approved progress schedule.

2. MATERIAL APPROVAL SUBMITTALS:

At a minimum the following list of materials will require approval under the Contract Clause, FAR 52.236-5, titled Material and Workmanship. The Contracting Officer may require submission of additional materials as deemed necessary. If additional items are required to be submitted a revised ENG form 4288, SUBMITTAL REGISTER, shall be prepared by the Contractor and submitted with the additional material submittals. The Contractor shall not proceed with any work using materials which are subject to approval, until materials are approved.

Sections, material, certificates, and/or procedures requiring approval:

01 11 00 Summary of Work 01 33 00 Submittals 02 41 00 Demolition 03 20 00 Cast-In-Place Concrete 03 30 00 Concrete Reinforcing 06 10 00 Rough Carpentry 06 61 16 Solid Surfacing Fabrications 07 41 13 Metal Roof Panels 07 84 00 Firestopping 07 92 00 Caulking and Sealants 08 11 13 Steel Doors and Frames 08 14 00 Wood Doors 08 71 00 Hardware 08 81 00 Glazing 09 29 00 Gypsum Board 09 30 10 Ceramic and Porcelain Tiling 09 90 00 Painting and Coatings 10 28 13 Toilet Accessories 10 44 16 Fire Extinguishers 12 32 00 Manufactured Wood Casework 22 00 00 Plumbing, General Purpose 23 00 00 Air Supply, Distribution, Ventilation and Exhaust Systems 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 Thermal Insulation for Mechanical Systems 26 20 00 Interior Distribution System 26 51 00 Interior Lighting 28 31 64.00 10 Fire Detection and Alarm System, Addressable 31 33 00 Excavation, Filling and Backfilling for Buildings 32 93 00 Turf

NOTE: For specific quantities and types of materials to be submitted see the individual SECTIONS

SECTION 02 41 00

DEMOLITION

PART 1 - GENERAL

1.1 SUBMITTALS: The procedures proposed for the accomplishment of salvage and demolition work shall be submitted for approval. The procedures shall provide for safe conduct of the work, careful removal and disposition of materials specified to be salvaged, protection of property which is to remain undisturbed, coordination with other work in progress, and timely disconnection of utility services. The procedures shall include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations.

1.2 GENERAL REQUIREMENTS: The work includes demolition or removal of all construction indicated or specified. All materials resulting from demolition work, except as indicated or specified otherwise, shall become the property of the Contractor and shall be removed from the limits of Government property. Rubbish and debris shall be removed from Government property daily unless otherwise directed so as to not allow accumulation inside or outside the building.

Materials that cannot be removed daily shall be stored in areas specified by the Contracting Officer.

1.3 DUST CONTROL: The amount of dust resulting from demolition shall be controlled to avoid creation of a nuisance in the surrounding area. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding and pollution.

1.4 PROTECTION: Protection of Existing Work: Before beginning any cutting or demolition work, the Contractor shall carefully survey the existing work and examine the drawings and specifications to determine the extent of the work. The Contractor shall take all necessary precautions to insure against damage to existing work to remain in place, to be reused, or to remain the property of the Government, and any damage to such work shall be repaired or replaced as approved by the Contracting Officer at no additional cost to the Government. The Contractor shall carefully coordinate the work of this section with all other work and construct and maintain shoring, bracing and supports, as required. The Contractor shall insure that structural elements are not overloaded and be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under any part of this Contract.

1.5 BURNING: The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.6 USE OF EXPLOSIVES: Use of explosives will not be permitted.

1.7 AVAILABILITY OF WORK AREAS: Areas in which salvage and demolition work is to be accomplished will be available in accordance with the schedule established by the Contracting Officer.

PART 2 - EXECUTION

2.1 EXISTING FACILITIES:

2.1.1 Utilities: Existing utilities shall be removed as indicated. When utility lines are encountered that are not indicated on the drawings the Contracting Officer shall be notified.

2.1.2 Filling: Holes, open trenches and other hazardous openings shall be filled.

2.2 DISPOSITION OF MATERIAL: Title to all materials and equipment to be demolished, excepting Government salvage, is vested in the Contractor upon removal from the building. The Government will not be responsible for the condition, loss, or damage to such property after notice to proceed.

2.2.1 Material for Contractor Salvage: Material for salvage shall be stored as approved by the Contracting Officer. Salvage materials shall be removed from Government property before completion of the Contract. Material for salvage shall not be sold on the site.

2.2.2 Unsalvageable Materials: Concrete, masonry, and other

noncombustible materials other than concrete permitted to remain in place shall be disposed in the disposal area as directed by Contracting Officer.

2.2.3 Material for Government Salvage: Control panel and controls within, electric actuators and hot water sensors, Boiler with controls and burner with associated piping, and hot water pumps. (Refer to Mechanical Plans)

2.3 CLEAN-UP:

2.3.1 Debris and Rubbish: Debris and rubbish shall be removed from area of work and job site as soon as possible.

2.3.2 Debris Control: Debris shall be removed and transported in a manner as to prevent spillage on streets.

SECTION 03 20 00

CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.1 REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)

ACI 117 (2010) Specifications for Tolerances for Concrete Construction and

Materials and Commentary

ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete

ACI 305.1 (2006) Specification for Hot Weather

Concreting

ACI 318 (2011; Errata 2011) Building Code Requirements for Structural Concrete and Commentary

AMERICAN HARDBOARD ASSOCIATION (AHA)

AHA A135.4 (1995; R 2004) Basic Hardboard

ASTM INTERNATIONAL (ASTM)

ASTM A167 (1999; R 2009) Standard Specification for

Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip

ASTM A480 (2012) Standard Specification for General

Requirements for Flat-Rolled Stainless and Heat- Resisting Steel Plate, Sheet, and Strip

ASTM A109/A109M (2008) Standard Specification for Steel, Strip, Carbon (0.25 Maximum Percent), Cold- Rolled

ASTM A1011/A1011M (2012b) Standard Specification for Steel, Sheet, and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy and High- Strength Low-Alloy with Improved Formability and Ultra-High Strength

ASTM B152/B152M (2013) Standard Specification for Copper Sheet, Strip, Plate, and Rolled Bar

ASTM B370 (2012) Standard Specification for Copper Sheet and Strip for Building Construction

ASTM C31 (2012) Standard Practice for Making and Curing

Concrete Test Specimens in the Field

ASTM C33 (2013) Standard Specification for Concrete Aggregates

ASTM C39 (2012a) Standard Test Method for

Compressive Strength of Cylindrical Concrete Specimens

ASTM C42 (2013) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete

ASTM C78 (2010e1) Standard Test Method for Flexural

Strength of Concrete (Using Simple Beam with Third-Point Loading)

ASTM C94 (2013) Standard Specification for Ready-Mixed

ASTM C143 (2012) Standard Test Method for Slump of

Hydraulic-Cement Concrete

ASTM C150 (2012) Standard Specification for Portland Cement

ASTM C172 (2010) Standard Practice for Sampling Freshly

Mixed Concrete

ASTM C173 (2012) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method

ASTM C192 (2012a) Standard Practice for Making and

Curing Concrete Test Specimens in the Laboratory

ASTM C231 (2010) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C260 (2010a) Standard Specification for Air-Entraining

Admixtures for Concrete

ASTM C494 (2012) Standard Specification for Chemical

Admixtures for Concrete

ASTM C552 (2012b) Standard Specification for Cellular Glass

Thermal Insulation

ASTM C578 (2012b) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation

ASTM C591 (2012b) Standard Specification for Unfaced

Preformed Rigid Cellular Polyisocyanurate Thermal Insulation

ASTM C881 (2010) Standard Specification for Epoxy-

Resin-Base Bonding Systems for Concrete

ASTM C920 (2011) Standard Specification for Elastomeric

Joint Sealants

ASTM C937 (2010) Grout Fluidifier for Preplaced-Aggregate

Concrete

ASTM C1017 (2007) Standard Specification for Chemical

Admixtures for Use in Producing Flowing Concrete

ASTM C1107 (2011) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM D471 (2012a) Standard Test Method for Rubber

Property - Effect of Liquids

ASTM D1751 (2004; R 2008) Standard Specification for

Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D1752 (2004a; R 2008) Standard Specification for

Preformed Sponge Rubber Cork and Recycled PVC Expansion

ASTM D5249 (2010) Backer Material for Use with Cold-and

Hot-Applied Joint Sealants in Portland-Cement Concrete and Asphalt Joints

ASTM E96 (2012) Standard Test Methods for Water Vapor

Transmission of Materials

NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)

NRMCA QC 3 (2011) Quality Control Manual: Section 3, Plant Certifications Checklist: Certification of Ready Mixed Concrete Production Facilities

NRMCA TMMB 100 (2001; R 2007) Truck Mixer, Agitator and Front

Discharge Concrete Carrier Standards

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 400 (1963) Requirements for Water for Use in Mixing or Curing Concrete

COE CRD-C 513 (1974) Corps of Engineers Specifications for Rubber Waterstops

COE CRD-C 521 (1981) Standard Test Method for Frequency and Amplitude of Vibrators for Concrete

COE CRD-C 572 (1974) Corps of Engineers Specifications for Polyvinylchloride Waterstops

1.2 SYSTEM DESCRIPTION

Provide concrete composed of Portland cement, other cementitious and pozzolanic materials as specified, aggregates, water and admixtures as specified.

1.2.1 Proportioning Studies-Normal Weight Concrete

Trial design batches, mixture proportions studies, and testing requirements for various classes and types of concrete specified are the responsibility of the Contractor. Except as specified for flexural strength concrete, mixture proportions shall be based on compressive strength as determined by test specimens fabricated in accordance with ASTM C192 and tested in accordance with ASTM C39.

a. Samples of all materials used in mixture proportioning studies shall be representative of those proposed for use in the project and be accompanied by the manufacturer's or producer's test reports indicating compliance with these specifications.

b. Make trial mixtures having proportions, consistencies, and air content suitable for the work based on methodology described in ACI 211.1, using at least three different water-cement ratios for each type of mixture, which will produce a range of strength encompassing those required for each class and type of concrete required on the project.

c. The maximum water-cement ratios required in subparagraph Water-Cement

Ratio below will be the equivalent water-cement ratio as determined by conversion from the weight ratio of water to cement plus pozzolan, silica fume, and ground granulated blast furnace slag (GGBF slag) by the weight equivalency method as described in ACI 211.1. In the case where silica fume or GGBF slag is used, the weight of the silica fume and GGBF slag shall be included in the equations in ACI 211.1 for the term P, which is used to denote the weight of pozzolan. If pozzolan is used in the concrete mixture, the minimum pozzolan content shall be 15 percent by weight of the total cementitious material, and the maximum shall be 35 percent.

d. Design laboratory trial mixtures for maximum permitted slump and air content. Make separate sets of trial mixture studies for each combination of cementitious materials and each combination of admixtures proposed for use. No combination of either shall be used until proven by such studies, except that, if approved in writing and otherwise permitted by these specifications, an accelerator or a retarder may be used without separate trial mixture study. Separate trial mixture studies shall also be made for concrete for any conveying or placing method proposed which requires special properties and for concrete to be placed in unusually difficult placing locations.

e. Report the temperature of concrete in each trial batch. For each water-cement ratio, at least three test cylinders for each test age shall be made, cured in accordance with ASTM C192 and tested at 7 and 28 days in accordance with ASTM C39. From these test results, plot a curve showing the relationship between water-cement ratio and strength for each set of trial mix studies. In addition, a curve shall be plotted showing the relationship between 7 day and 28 day strengths. Design each mixture to promote easy and suitable concrete placement, consolidation and finishing, and to prevent segregation and excessive bleeding.

f. Submit the results of trial mixture design studies along with a statement giving the maximum nominal coarse aggregate size and the proportions of ingredients that will be used in the manufacture of each strength or class of concrete, at least 14 days prior to commencing concrete placing operations. Aggregate weights shall be based on the saturated surface dry condition. Accompany the statement with test results from an approved independent commercial testing laboratory, showing that mixture design studies have been made with materials proposed for the project and that the proportions selected will produce concrete of the qualities indicated. No substitutions shall be made in the materials used in the mixture design studies without additional tests to show that the quality of the concrete is satisfactory.

1.2.2 Average Compressive Strength

The mixture proportions selected during mixture design studies shall produce a required average compressive strength (f'cr) exceeding the specified compressive strength (f'c) by the amount indicated below. This required average compressive strength, f'cr, will not be a required acceptance criteria during concrete production. However, whenever the daily average compressive strength at 28 days drops below f'cr during concrete production, or daily average 7-day strength drops below a strength correlated with the 28-day f'cr, adjust the mixture, as approved, to bring the daily average back up to f'cr.

1.2.3 Tolerances

Except as otherwise specified herein, tolerances for concrete batching, mixture properties, and construction as well as definition of terms and application practices shall be in accordance with ACI 117. Take level and grade tolerance measurements of slabs as soon as possible after finishing;

when forms or shoring are used, the measurements shall be made prior to removal.

1.2.4 Floor Finish

For the purpose of this Section the following terminology correlation between ACI 117 and this Section shall apply:

Floor Profile Quality Classification From ACI 117

This Section

Conventional Bullfloated Same

Conventional Straightedged Same

Floor Profile Quality Classification From ACI 117

This Section

Flat Float Finish or Trowel Finish

Very Flat Same. Use only with F-system

Levelness tolerance does not apply where design requires floors to be sloped to drains or sloped for other reasons.

1.2.4.1 Floors by the Straightedge System

The flatness of the floors shall be carefully controlled and the tolerances shall be measured by the straightedge system as specified in paragraph 4.5.7 of ACI 117, using a 10 foot straightedge, within 72 hours after floor slab installation and before shores and/or forms are removed. The listed tolerances shall be met at any and every location at which the straightedge can be placed.

Bullfloated 5/16

Straightedged 5/16

Float Finish 5/16

Bullfloated 5/16

Trowel Finish 5/16

1.2.5 Strength Requirements

Specified compressive strength (f'c) shall be 4000 psi at 28 days.

Concrete slabs on-grade shall have a 28-day flexural strength of 650 psi.

Concrete made with high-early strength cement shall have a 7-day strength equal to the specified 28-day strength for concrete made with Type I or II portland cement. Compressive strength shall be determined in accordance with

ASTM C39. Flexural strength shall be determined in accordance with ASTM C78.

a. Evaluation of Concrete

Compressive Strength. Fabricate compressive strength specimens (6 by 12 inch cylinders), laboratory cure them in accordance with ASTM C31 and test them in accordance with ASTM C39. The strength of the concrete will be considered satisfactory so long as the average of all sets of three consecutive test results equals or exceeds the specified compressive strength f'c and no individual test result falls below the specified strength f'c by more than 500 psi. A "test" is defined as the average of two companion cylinders, or if only one cylinder is tested, the results of the single cylinder test. Additional analysis or testing, including taking cores and/or load tests may be required at the Contractor's expense when the strength of the concrete in the structure is considered potentially deficient.

b. Investigation of Low-Strength Compressive Test Results. When any strength test of standard-cured test cylinders falls below the specified strength requirement by more than 500 psi or if tests of field-cured cylinders indicate deficiencies in protection and curing, take steps to assure that the load-carrying capacity of the structure is not jeopardized. When the strength of concrete in place is considered potentially deficient, cores shall be obtained and tested in accordance with ASTM C42. At least three representative cores shall be taken from each member or area of concrete in place that is considered potentially deficient. The location of cores will be determined by the Contracting Officer to least impair the strength of the structure. Concrete in the area represented by the core testing will be considered adequate if the average strength of the cores is equal to at least 85 percent of the specified strength requirement and if no single core is less than 75 percent of the specified strength requirement. Non-destructive tests (tests other than test cylinders or cores) shall not be used as a basis for acceptance or rejection.

Perform the coring and repair the holes; cores will be tested by the Government.

c. Load Tests. If the core tests are inconclusive or impractical to obtain or if structural analysis does not confirm the safety of the structure, load tests may be directed by the Contracting Officer in accordance with the requirements of ACI 318. Concrete work evaluated by structural analysis or by results of a load test as being understrength shall be corrected in a manner satisfactory to the Contracting Officer. All investigations, testing, load tests, and correction of deficiencies shall be performed by and at the expense of the Contractor and approved by the Contracting Officer, except that if all concrete is found to be in compliance with the drawings and specifications, the cost of investigations, testing, and load tests will be at the expense of the Government.

d. Evaluation of Concrete Flexural Strength. Fabricate flexural strength specimens (beams) laboratory cure them in accordance with ASTM C31 and test them in accordance with ASTM C78. The strength of the concrete will be considered satisfactory so long as the average of all sets of three consecutive test results equals or exceeds the specified flexural strength and no individual test result falls below the specified flexural strength by more than 50 psi. A "test" is defined as the average of two companion beams. Additional analysis or testing, including taking cores and/or load tests may be required at the Contractor's expense when the strength of the concrete in the slab is considered potentially deficient.

1.2.6 Air Entrainment

Except as otherwise specified for lightweight concrete, all normal weight concrete shall be air entrained to contain between 4 and 7 percent total air, except that when the nominal maximum size coarse aggregate is 3/4 inch or smaller it shall be between 4.5 and 7.5 percent. Concrete with specified strength over 5000 psi may have 1.0 percent less air than specified above.

Specified air content shall be attained at point of placement into the forms. Air content for normal weight concrete shall be determined in accordance with ASTM C231.

1.2.7 Slump

Slump of the concrete, as delivered to the point of placement into the forms, shall be within the following limits. Slump shall be determined in accordance with ASTM C143.

Structural Element Slump (inches)

Minimum Maximum

Walls, columns and beams 2 4

Foundation walls, substructure walls, footings, slabs

1 3

Any structural concrete approved for placement by pumping:

At pump 2 6

At discharge of line 1 4

When use of a plasticizing admixture conforming to ASTM C1017 or when a Type F or G high range water reducing admixture conforming to ASTM C494 is permitted to increase the slump of concrete, concrete shall have a slump of 2 to 4 inches before the admixture is added and a maximum slump of 8 inches at the point of delivery after the admixture is added.

1.2.8 Concrete Temperature

The temperature of the concrete as delivered shall not exceed 90 degrees F.

When the ambient temperature during placing is 40 degrees F or less, or is expected to be at any time within 6 hours after placing, the temperature of the concrete as delivered shall be between 55 and 75 degrees F.

1.2.9 Size of Coarse Aggregate

Use the largest feasible nominal maximum size aggregate (NMSA), specified in PART 2 paragraph AGGREGATES, in each placement. However, nominal maximum size of aggregate shall not exceed any of the following: three-fourths of the minimum cover for reinforcing bars, three-fourths of the minimum clear spacing between reinforcing bars, one-fifth of the narrowest dimension between sides of forms, or one-third of the thickness of slabs or toppings.

1.3 SUBMITTALS: Submit the following in accordance with Section 01300

SUBMITTALS:

Product Data

Portland Cement Vapor Barrier

Chemical Admixtures Grouts/Sealants

Design Data

Mixture Proportions

1.3.1 Mix Designs: At least 14 days prior to commencing concrete placing operations, the Contractor shall submit the results of trial mix along with a statement giving the maximum nominal coarse aggregate size and the proportions of all ingredients that will be used in the manufacture of each strength of concrete. Aggregate weights shall be based on the saturated surface dry condition. The statement shall be accompanied by test results from an independent commercial testing laboratory, attesting that the proportions selected will produce concrete of the qualities indicated. No substitutions shall be made in the materials used in the work without additional tests to show that the quality of the concrete is satisfactory.

1.3.2 Test Reports: Certified copies of laboratory test reports, including all test data, shall be submitted for aggregate, admixtures, and curing compound. These tests shall be made by an approved commercial laboratory or by a laboratory maintained by the manufacturers of the materials.

1.3.3 Certificates of Compliance: Cement will be accepted on the basis of manufacturer's Certification of Compliance, accompanied by mill test reports attesting that the materials meet the requirements of the specification under which it is furnished. No cement shall be used until notice of acceptance has been given by the Contracting Officer.

Cement may be subjected to check testing by the Government from samples obtained at the mill, at transfer points, or at the project site.

1.3.4 Certified copies of mill reports attesting that the reinforcing steel furnished meets the requirements specified shall be submitted prior to the installation of reinforcing steel.

1.3.5 Certificates of Compliance and product literature for nonslip surfacing, floor hardener, perimeter insulation, joint sealant and vapor barrier.

1.4 DELIVERY, STORAGE, AND HANDLING

Store cement and other cementitious materials in weathertight buildings, bins, or silos which will exclude moisture and contaminants and keep each material completely separated. Aggregate stockpiles shall be arranged and used in a manner to avoid excessive segregation and to prevent contamination with other materials or with other sizes of aggregates. Aggregate shall not be stored directly on ground unless a sacrificial layer is left undisturbed. Store reinforcing bars and accessories above the ground on platforms, skids or other supports. Other materials shall be stored in such a manner as to avoid contamination and deterioration. Admixtures which have been in storage at the project site for longer than 6 months or which have been subjected to freezing shall not be used unless retested and proven to meet the specified requirements. Materials shall be capable of being accurately identified after bundles or containers are opened.

PART 2 PRODUCTS

2.1 CEMENTITIOUS MATERIALS

Cementitious Materials shall be portland cement, conforming to appropriate specifications listed below. Restrict usage of cementitious materials in concrete that will have surfaces exposed in the completed structure so there is no change in color, source, or type of cementitious material.

i

2.1.1 Portland Cement

ASTM C150, Type I with a maximum 15 percent amount of tricalcium aluminate, or Type II. White portland cement shall meet the above requirements except that it may be Type I, Type II or Type III. White Type III shall be used only in specific areas of the structure, when approved in writing.

2.1.2 High-Early-Strength Portland Cement

ASTM C150, Type III with tricalcium aluminate limited to 5. Use Type III cement only in isolated instances and only when approved in writing.

2.2 AGGREGATES

Fine and coarse aggregates shall conform to the following.

2.2.1 Fine Aggregate

Fine aggregate shall conform to the quality and gradation requirements of

ASTM C33.

2.2.2 Coarse Aggregate

Coarse aggregate shall conform to ASTM C33, Class 5S.

2.3 CHEMICAL ADMIXTURES

Chemical admixtures, when required or permitted, shall conform to the appropriate specification listed. Admixtures shall be furnished in liquid form and of suitable concentration for easy, accurate control of dispensing.

2.3.1 Air-Entraining Admixture

ASTM C260 and shall consistently entrain the air content in the specified ranges under field conditions.

2.3.2 Accelerating Admixture

ASTM C494, Type C or E, except that calcium chloride or admixtures containing calcium chloride shall not be used.

2.3.3 Water-Reducing or Retarding Admixture

ASTM C494, Type A, B, or D, except that the 6-month and 1-year compressive and flexural strength tests are waived.

2.4 WATER

Water for mixing shall be fresh, clean, potable, and free of injurious amounts of oil, acid, salt, or alkali, except that non-potable water may be used if it meets the requirements of COE CRD-C 400.

2.5 NONSHRINK GROUT

Nonshrink grout shall conform to ASTM C1107, and shall be a commercial formulation suitable for the proposed application.

2.6 EPOXY RESIN

Epoxy resins for use in repairs shall conform to ASTM C881, Type V, Grade 2.

Class as appropriate to the existing ambient and surface temperatures. Submit manufacturer's product data, indicating VOC content. Manufacturer's catalog data for the items above, including printed instructions.

2.7 VAPOR BARRIER

Vapor barrier shall be polyethylene sheeting with a minimum thickness of 6 mils or other equivalent material having a vapor permeance rating not exceeding 0.5 perms as determined in accordance with ASTM E96.

2.8 JOINT MATERIALS

2.8.1 Joint Fillers, Sealers, and Waterstops

2.8.1.1…