Base Year Work Period
| ITEM | DESCRIPTION | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT |
| 0001 | BASE YEAR PERIOD WORK | ||||
| 0001 | Provide all supervision, plant, labor, material and equipment necessary to perform all work in connection with construction and repair/replacement of existing building roofs, including associated installation items, on various structures at Fort Drum, NY, in strict accordance with the Statement of Work, specifications and drawings, and subject to the terms and conditions of the contract, from 1 November 2015 through 31 October 2016. | ||||
| A001 | Remove and dispose off-site the existing roof asphalt and/or fiberglass shingle roof system complete, including felt(s), metal drip strip, ice and water barrier (if applicable), and flashing (if applicable) down to the existing sheathing. Inspect existing roof sheathing and framing for any possible damage and/or deterioration. Remove and replace any discovered damaged or deficient, sheathing and framing, to match the existing. Also included in the referenced main ELINs roof replacement are the following: Provide, place and install one layer of new roofing felt, complete, over the existing and any repaired/replaced exposed roof sheathing; Provide, place and install new flashing, complete, where existing roofing systems abuts vertical surfaces and per specifications and as shown on the Drawing Sheet 2 of 2 (Typical Flashing Detail); Provide, place and install new water barrier membrane (elastomeric sheet waterproofing) as specified in Section 07 13 53, complete, along all eaves and all valleys as shown on the Drawing Sheet 2 of 2 (Typical Water Barrier Installation Plan); Provide and properly install, along entire existing roof ridge, a new metal ridge vent system, complete as specified in Sections 07 31 13 Asphalt Shingles and 07 72 00 Roof Ventilators, Gravity Type. Finally, the referenced ELINs and roof replacement shall be completely finished with, and include the supply and installation of, new aluminum metal drip strip along all eaves, and new specified "architectural” laminated asphalt shingles, as specified in Section 07 31 13 Asphalt Shingles, and as reviewed, selected and approved by the Government in the roofing material submittal process. Any other trim and accessories necessary shall be installed, as required for a complete roof installation, at no additional cost to the Government. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(1), Drawing Sheet 2 of 2 and Asphalt Shingles Specifications. | 125 | SQ | 678.00 | $84,750.00 |
| A002 | Inspect, remove, dispose off-site and replace existing wood roof substrate sheathing found to be damaged or deficient and shall match the existing sheathing dimensions. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(2) and Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 1,500 | SF | 5.76 | $8,640.00 |
| A003 | Inspect, remove, dispose off-site and replace existing wood roof soffit/eave framing and fascia boards members that are found to be damaged or deficient and shall match the existing framing or fascia board dimensions. Payment will be based on board feet (BF). Refer to Statement of Work 1d(3), Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 800 | BF | 9.42 | $7,536.00 |
| A004 | Remove and off-site dispose existing solid metal soffit covering and/or exposed wood soffit sheathing complete; inspect the existing exposed wood soffit framing along the underside of existing roof eave; installation of new perforated, continuously vented, finished metal soffit material to match the existing soffit color finish or approved equal, complete, along the underside of existing roof eave, over existing and/or repaired (if applicable) portions of open wood soffit framing. New metal soffit material color and finish shall be, as selected, reviewed and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(4), Drawing Sheet 2 of 2, Flashing-Sheet Metal Specifications. | 750 | SF | 6.54 | $4,905.00 |
| A005 | Remove existing building fascia material, dispose off-site and replace with new metal fascia material covering completely installed to match and cover existing wood fascia member (typically 8 inches to 10 inches wide – may vary) along eave or gable wall; inspect existing wood fascia board members and framing. New metal fascia material color and finish shall match existing fascia material and/or be, as selected and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on linear feet (LF) of covered area. Refer to Statement of Work 1d(5) and Drawing Sheet 2 of 2, Flashing-Sheet Metal Specifications. | 500 | LF | 4.00 | $2,000.00 |
| A006 | Install a new complete structural standing seam metal roof (SSSMR) system on an existing building or portion thereof; complete removal of the existing shingled roof system materials or existing metal roof system materials and disposal off-site, to allow for the complete inspection of the existing substrate and the installation of new roofing felts, in accordance with the Contract's Steel Standing Seam Roofing specifications Section 07 61 14.00 20 and prior to installation of the new SSSMR; as shown on the Drawing Sheet 2 of 2 (Metal Roofing Details). The new SSSMR system shall also include a complete new ridge vent system, ventilated eave covers, and rake closures. The SSSMR system shall include the ability for the new metal roof to release any warm air that infiltrates into the trapped air space, between the new metal roofing and the existing roof substrate. | 600 | SQ | 721.00 | $432,600.00 |
| New SSSMR material, ridge vent system, ventilated eave covers, and rake closures color and finish shall be compatible, blend and match with the various sloped-roof architectural building theme color and finishes, throughout the Fort Drum cantonment areas in PinePlains, MountainView and WSAAF. The new SSSMR material and associated system components’ color and finish, shall be as specified and shall match other area existing metal roof color and finishes, in the same vicinity, and/or be, as selected and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(6) and Drawing Sheet 2 of 2 and Steel Standing Seam Roofing Specifications. | |||||
| A006a | Install new wooden purlins (double layers), perpendicular to the roof slope along with installation of new wooden nailers over the existing rafters and, over the entire roof area, as shown on the Drawing Sheet 2 of 2 (Metal Roofing Details). Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(6a) and Drawing Sheet 2 of 2 and Steel Standing Seam Roofing Specifications. | 200 | SQ | 244.00 | $48,800.00 |
| A007 | Remove and dispose off-site and replace the existing Ethylene-Propylene-Diene-Monomer (EPDM) elastomeric membrane roofing system, complete, in accordance with the EPDM Roofing Specification Section 07 53 23, on a complete building or part thereof. This EPDM roof replacement shall include the following: removal and disposal off-site of all existing high density board (if applicable) and roof insulation, down to the existing roof deck substrate (metal roof deck and/or wood sheathing) including all existing associated flashing; installation and provision of new roof insulation to produce an R-48 value in accordance with Roof and Deck Insulation Specification Section 07 22 00; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; installation of new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 400 | SQ | 869.00 | $347,600.00 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Installation of new tapered insulation to recreate existing and additional crickets, to provide and insure, positive drainage of water to all existing roof drains; installation and provision of new wood nailers and wood blocking materials, for perimeter blocking to accommodate the new R-48 insulation; installation of new replacement flashing shall be of ultra-violet resistant materials and as required to properly install and fit the finished roofing system conditions in accordance with the manufacturer’s recommendations and meet the referenced specifications. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailers and wood perimeter blocking material as may be required to properly install the finished roofing at no additional cost to the Government. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(7), EPDM Roofing, Roof and Deck Insulation, and Flashing and Sheet Metal Specifications. | |||||
| A008 | Remove, dispose off-site and replace existing EPDM elastomeric roof system membrane, complete, in accordance with the EPDM Roofing Specification Section 07 53 23 (including all high density board if applicable), flashings. Mechanically fasten new 7/16” thick OSB board over existing insulation, in accordance with manufacturer’s recommendations, to meet a 100 mile per hour wind speed resistance; fully adhere and replace with complete new installed 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s recommendations) at no additional cost to the Government. NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(8) and EPDM Specifications. | 200 | SQ | 827.00 | $165,400.00 |
| A009 | Remove, dispose off-site and replace the existing metal coping, complete, on existing building roof system or a portion thereof; replacement shall include new installed coping, with variable surface dimensions for various buildings throughout the cantonment and/or WSAAF areas, complete with new fasteners and closures as recommended by manufacture to ensure and develop a watertight seal. New metal coping material color and finish shall be compatible, blend and match the existing coping material and with the various architectural building themes throughout the Fort Drum cantonment areas in Pine Plains, Mountain View and WSAAF. | 6,000 | SF | 3.86 | $23,160.00 |
| New metal coping color and finish shall be as specified in the Flashing and Sheet Metal Specifications 076000, and match existing coping material color and finish and/or be, as selected, reviewed and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the contract submittal process. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(9) and Flashing and Sheet Specifications. | |||||
| A010 | Inspect existing EDPM roof insulation; remove, dispose off-site and replace all damaged, deficient and wet insulation of the same type and thickness to match the existing roof insulation, complete. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(10) and Roof and Deck Insulation Specifications. | 750 | SF | 6.57 | $4,927.50 |
| A011 | Inspect, remove, dispose off-site, repair and replace a damaged or deficient portion of existing EDPM elastomeric membrane roof system; and remove the existing insulation to expose existing substrate for visual inspection. The repair shall consist of removing the existing damaged membrane and insulation down to the existing substrate, inspect substrate for damage and repair as conditions dictate. Install new insulation to match the thickness and type of the existing and then repair the roofing membrane as per the manufacturer’s instructions and recommendations. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(11) and EPDM Roof Specifications. | 1,500 | SF | 5.72 | $8,580.00 |
| A012 | Repair holes or small rips in a very small portion of the existing EPDM roofing membrane on an existing roofing system. Prior to securing the patching membrane, the area shall be properly cleaned and prepared to receive the patch as per the manufacturer’s instructions and recommendations. Payment will be based on square feet (SF) of area covered, for patch repair. Refer to Statement of Work 1d(12) and EPDM Roof Specifications. | 100 | SF | 5.09 | $509.00 |
| A013 | Repair existing base flashing and existing open seams utilizing cleaner, primer and cover tape. The repairs shall consist of the proper cleaning of the open seams and base flashing as recommended by the elastomeric membrane manufacturer prior to performing the repairs to the affected areas. Payment will be based on lineal feet (LF) of area covered. Refer to Statement of Work 1d(13) EPDM Roof and Flashing and Sheet Metal Specifications. | 200 | LF | 6.36 | $1,272.00 |
| A014 | Repair existing ballasted elastomeric membrane roofing systems. The repairs shall consist of the removal and storage of the existing ballast material to allow for the inspection of the existing membrane and to determine the location of the leak. The leak will then be repaired as recommended by the elastomeric membrane manufacturer and the existing removed ballast replaced to match the existing conditions. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(14) and EPDM Roofing Specifications. | 800 | SF | 5.51 | $4,408.00 |
| A015 | Remove and dispose off-site existing ballasted EPDM elastomeric membrane roofing system, complete, down to the roof deck substrate; remove and dispose off-site of all existing associated flashing; installation of new roof insulation shall produce R-48 value; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; the complete replacement with, and installation of, new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 150 | SQ | 805.00 | $120,750.00 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Utilization of tapered insulation to recreate existing and additional crickets for providing positive drainage of water to all existing roof drains. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailer material as may be required to properly install the finished roofing at no additional cost to the Government. Provide new wood nailer block materials, for perimeter blocking to accommodate new R-48 insulation; new replacement flashing shall be of ultra-violet resistant materials and as required to properly install the finished roofing system in accordance with the manufacturer’s recommendations and meeting the specification Section 07 13 53for elastomeric membrane roofing system. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d (15) and EPDM Roofing Specification. | |||||
| A016 | Remove and dispose off-site existing built-up roof system material (consisting of several layers – no ballast), complete, down to the roof deck substrate; remove and dispose off-site all existing associated flashing; installation of new roof insulation shall produce R-48 value; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; the complete replacement with, and installation of, new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 750 | SQ | 869.00 | $651,750.00 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Utilization of tapered insulation to recreate existing and additional crickets for providing positive drainage of water to all existing roof drains. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailer material as may be required to properly install the finished roofing at no additional cost to the Government. Provide new wood nailer block materials, for perimeter blocking to accommodate new R-48 insulation; new replacement flashing shall be of ultra-violet resistant materials and as required to properly install the finished roofing system in accordance with the manufacturer’s recommendations and meeting the specification Section 07 13 53for elastomeric membrane roofing system. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(16) and EPDM Roofing Specification. | |||||
| A017 | Repair the existing metal roof mansard knuckles caused by sliding snow and/or ice. The repairs for the mansard knuckles will consist of replacing the damaged knuckles with new ones that match the existing knuckles in profile and color. Payment will be based on each (EA) knuckle that is repaired. Refer to Statement of Work 1d(17). | 30 | EA | 890.00 | $26,700.00 |
| A018 | Repair the damaged metal roofing sections caused by sliding snow and/or ice. The repairs of the roofing sections will consist of repairing any damaged plumbing pipe venting projecting through the roof and securing a watertight metal roofing section to match the gauge and color of the existing metal roofing section. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(18). | 30 | EA | 445.00 | $13,350.00 |
| A019 | Remove existing gravity flow and /or turbine type ventilators from the existing roofs and the patching of the existing sheathing to allow for the installation of the new ridge vent system. The existing roof sheathing material shall be removed along the ridge as required by the manufacturer’s recommendation to allow for the proper installation of the new ridge vent system as described in Specification Sections 07 31 13 Asphalt Shingles and 07 72 00 Roof Ventilators, Gravity Type. Payment will be based on linear feet (LF) of ridge to receive the work. Refer to Statement of Work 1d(19) and Asphalt Shingles and Roof Ventilators-Gravity Type Specifications. | 500 | LF | 5.72 | $2,860.00 |
| A020 | Remove the existing individual roof vents, shingles, felts and sheathing as required to allow for the installation of new sheathing, felts, shingles and new turbine vents. Payment shall be based on each (EA) vent installed. Refer to Statement of Work 1d(20) and Roof Ventilators-Gravity Type Specs. | 15 | EA | 338.00 | $5,070.00 |
| A020a | Provide the batten insulation or blown insulation which shall produce a R-48 value. Insulation shall be applied as per manufacture instructions and as described in Specification Sections 07 21 16 (Mineral Fiber Blanket Insulation) or Specification Sections 07 21 23 (Loose Fill Thermal Insulation), whichever the case may be. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(21). | 750 | SF | 4.84 | $3,630.00 |
| A021 | Emergency Repairs to shingled roofs consisting of at least 200 S.F. per building. Contractor shall mobilize within 24 hours of notification and evaluate work required by coordinating with PW Construction Representative. Repairs shall be implemented as outlined in Statement of Work. | ||||
| A021a | Replace broken/missing asphalt/ fiberglass 3-tab shingles (at least 200 SF per building). Refer to Statement of Work 1e(1). | 150 | SF | 3.40 | $510.00 |
| A021b | Replace broken/missing asphalt/ fiberglass Architectural Laminated shingles (at least 200 SF per building). Refer to Statement of Work 1e(2). | 150 | SF | 3.84 | $576.00 |
| A021c | Repair/replacement of ice panel flashing along eaves on existing roofs. Refer to Statement of Work 1e(3). | 250 | SF | 3.60 | $900.00 |
| A022 | Emergency Repairs to shingled roofs consisting of less than or equal to 199 S.F. per building. Contractor shall mobilize within 24 hours of notification and evaluate work required by coordinating with PW Construction Representative. Repairs shall be implemented as outlined in Statement of Work. | ||||
| A022a | Replace broken/missing asphalt/ fiberglass 3-Tab shingles (less than or equal to 199 SF per building). Refer to Statement of Work 1f(1). | 150 | SF | 3.60 | $540.00 |
| A022b | Replace broken/missing asphalt/ fiberglass Architectural Laminated shingles (less than or equal to 199 SF per building). Refer to Statement of Work 1f(2). | 150 | SF | 3.60 | $540.00 |
TOTAL BASE PERIOD WORK, CLIN 2001 (ELINs C001-C022) $1,972,263.50
0002 Performance and Payment Bonds 1 EA $35,475.00 $35,475.00
TOTAL BASE PERIOD WORK, CLINs 2001 - 2002 $2,007,738.50
1st Year Work Period
| ITEM | DESCRIPTION | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT |
| 1001 | FIRST YEAR PERIOD WORK | ||||
| 1001 | Provide all supervision, plant, labor, material and equipment necessary to perform all work in connection with construction and repair/replacement of existing building roofs, including associated installation items, on various structures at Fort Drum, NY, in strict accordance with the Statement of Work, specifications and drawings, and subject to the terms and conditions of the contract, from 1 May 2016 through 30 April 2017. | ||||
| B001 | Remove and dispose off-site the existing roof asphalt and/or fiberglass shingle roof system complete, including felt(s), metal drip strip, ice and water barrier (if applicable), and flashing (if applicable) down to the existing sheathing. Inspect existing roof sheathing and framing for any possible damage and/or deterioration. Remove and replace any discovered damaged or deficient, sheathing and framing, to match the existing. Also included in the referenced main ELINs roof replacement are the following: Provide, place and install one layer of new roofing felt, complete, over the existing and any repaired/replaced exposed roof sheathing; Provide, place and install new flashing, complete, where existing roofing systems abuts vertical surfaces and per specifications and as shown on the Drawing Sheet 2 of 2 (Typical Flashing Detail); Provide, place and install new water barrier membrane (elastomeric sheet waterproofing) as specified in Section 07 13 53, complete, along all eaves and all valleys as shown on the Drawing Sheet 2 of 2 (Typical Water Barrier Installation Plan); Provide and properly install, along entire existing roof ridge, a new metal ridge vent system, complete as specified in Sections 07 31 13 Asphalt Shingles and 07 72 00 Roof Ventilators, Gravity Type. Finally, the referenced ELINs and roof replacement shall be completely finished with, and include the supply and installation of, new aluminum metal drip strip along all eaves, and new specified "architectural” laminated asphalt shingles, as specified in Section 07 31 13 Asphalt Shingles, and as reviewed, selected and approved by the Government in the roofing material submittal process. Any other trim and accessories necessary shall be installed, as required for a complete roof installation, at no additional cost to the Government. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(1), Drawing Sheet 2 of 2 and Asphalt Shingles Specifications. | 125 | SQ | 698.34 | $87,292.50 |
| B002 | Inspect, remove, dispose off-site and replace existing wood roof substrate sheathing found to be damaged or deficient and shall match the existing sheathing dimensions. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(2) and Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 1,500 | SF | 5.93 | $8,895.00 |
| B003 | Inspect, remove, dispose off-site and replace existing wood roof soffit/eave framing and fascia boards members that are found to be damaged or deficient and shall match the existing framing or fascia board dimensions. Payment will be based on board feet (BF). Refer to Statement of Work 1d(3), Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 800 | BF | 9.70 | $7,760.00 |
| B004 | Remove and off-site dispose existing solid metal soffit covering and/or exposed wood soffit sheathing complete; inspect the existing exposed wood soffit framing along the underside of existing roof eave; installation of new perforated, continuously vented, finished metal soffit material to match the existing soffit color finish or approved equal, complete, along the underside of existing roof eave, over existing and/or repaired (if applicable) portions of open wood soffit framing. New metal soffit material color and finish shall be, as selected, reviewed and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(4), Drawing Sheet 2 of 2, Flashing-Sheet Metal Specifications. | 750 | SF | 6.74 | $5,055.00 |
| B005 | Remove existing building fascia material, dispose off-site and replace with new metal fascia material covering completely installed to match and cover existing wood fascia member (typically 8 inches to 10 inches wide – may vary) along eave or gable wall; inspect existing wood fascia board members and framing. New metal fascia material color and finish shall match existing fascia material and/or be, as selected and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on linear feet (LF) of covered area. Refer to Statement of Work 1d(5) and Drawing Sheet 2 of 2, Flashing-Sheet Metal Specifications. | 500 | LF | 4.12 | $2,060.00 |
| B006 | Install a new complete structural standing seam metal roof (SSSMR) system on an existing building or portion thereof; complete removal of the existing shingled roof system materials or existing metal roof system materials and disposal off-site, to allow for the complete inspection of the existing substrate and the installation of new roofing felts, in accordance with the Contract's Steel Standing Seam Roofing specifications Section 07 61 14.00 20 and prior to installation of the new SSSMR; as shown on the Drawing Sheet 2 of 2 (Metal Roofing Details). The new SSSMR system shall also include a complete new ridge vent system, ventilated eave covers, and rake closures. The SSSMR system shall include the ability for the new metal roof to release any warm air that infiltrates into the trapped air space, between the new metal roofing and the existing roof substrate. | 600 | SQ | 742.63 | $445,578.00 |
| New SSSMR material, ridge vent system, ventilated eave covers, and rake closures color and finish shall be compatible, blend and match with the various sloped-roof architectural building theme color and finishes, throughout the Fort Drum cantonment areas in PinePlains, MountainView and WSAAF. The new SSSMR material and associated system components’ color and finish, shall be as specified and shall match other area existing metal roof color and finishes, in the same vicinity, and/or be, as selected and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(6) and Drawing Sheet 2 of 2 and Steel Standing Seam Roofing Specifications. | |||||
| B006a | Install new wooden purlins (double layers), perpendicular to the roof slope along with installation of new wooden nailers over the existing rafters and, over the entire roof area, as shown on the Drawing Sheet 2 of 2 (Metal Roofing Details). Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(6a) and Drawing Sheet 2 of 2 and Steel Standing Seam Roofing Specifications. | 200 | SQ | 251.32 | $50,264.00 |
| B007 | Remove and dispose off-site and replace the existing Ethylene-Propylene-Diene-Monomer (EPDM) elastomeric membrane roofing system, complete, in accordance with the EPDM Roofing Specification Section 07 53 23, on a complete building or part thereof. This EPDM roof replacement shall include the following: removal and disposal off-site of all existing high density board (if applicable) and roof insulation, down to the existing roof deck substrate (metal roof deck and/or wood sheathing) including all existing associated flashing; installation and provision of new roof insulation to produce an R-48 value in accordance with Roof and Deck Insulation Specification Section 07 22 00; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; installation of new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 400 | SQ | 895.07 | $358,028.00 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Installation of new tapered insulation to recreate existing and additional crickets, to provide and insure, positive drainage of water to all existing roof drains; installation and provision of new wood nailers and wood blocking materials, for perimeter blocking to accommodate the new R-48 insulation; installation of new replacement flashing shall be of ultra-violet resistant materials and as required to properly install and fit the finished roofing system conditions in accordance with the manufacturer’s recommendations and meet the referenced specifications. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailers and wood perimeter blocking material as may be required to properly install the finished roofing at no additional cost to the Government. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(7), EPDM Roofing, Roof and Deck Insulation, and Flashing and Sheet Metal Specifications. | |||||
| B008 | Remove, dispose off-site and replace existing EPDM elastomeric roof system membrane, complete, in accordance with the EPDM Roofing Specification Section 07 53 23 (including all high density board if applicable), flashings. Mechanically fasten new 7/16” thick OSB board over existing insulation, in accordance with manufacturer’s recommendations, to meet a 100 mile per hour wind speed resistance; fully adhere and replace with complete new installed 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s recommendations) at no additional cost to the Government. NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(8) and EPDM Specifications. | 200 | SQ | 851.81 | $170,362.00 |
| B009 | Remove, dispose off-site and replace the existing metal coping, complete, on existing building roof system or a portion thereof; replacement shall include new installed coping, with variable surface dimensions for various buildings throughout the cantonment and/or WSAAF areas, complete with new fasteners and closures as recommended by manufacture to ensure and develop a watertight seal. New metal coping material color and finish shall be compatible, blend and match the existing coping material and with the various architectural building themes throughout the Fort Drum cantonment areas in Pine Plains, Mountain View and WSAAF. | 6,000 | SF | 3.98 | $23,880.00 |
| New metal coping color and finish shall be as specified in the Flashing and Sheet Metal Specifications 076000, and match existing coping material color and finish and/or be, as selected, reviewed and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(9) and Flashing and Sheet Specifications. | |||||
| B010 | Inspect existing EDPM roof insulation; remove, dispose off-site and replace all damaged, deficient and wet insulation of the same type and thickness to match the existing roof insulation, complete. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(10) and Roof and Deck Insulation Specifications. | 750 | SF | 6.77 | $5,077.50 |
| B011 | Inspect, remove, dispose off-site, repair and replace a damaged or deficient portion of existing EDPM elastomeric membrane roof system; and remove the existing insulation to expose existing substrate for visual inspection. The repair shall consist of removing the existing damaged membrane and insulation down to the existing substrate, inspect substrate for damage and repair as conditions dictate. Install new insulation to match the thickness and type of the existing and then repair the roofing membrane as per the manufacturer’s instructions and recommendations. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(11) and EPDM Roof Specifications. | 1,500 | SF | 5.89 | $8,835.00 |
| B012 | Repair holes or small rips in a very small portion of the existing EPDM roofing membrane on an existing roofing system. Prior to securing the patching membrane, the area shall be properly cleaned and prepared to receive the patch as per the manufacturer’s instructions and recommendations. Payment will be based on square feet (SF) of area covered, for patch repair. Refer to Statement of Work 1d(12) and EPDM Roof Specifications. | 100 | SF | 5.24 | $524.00 |
| B013 | Repair existing base flashing and existing open seams utilizing cleaner, primer and cover tape. The repairs shall consist of the proper cleaning of the open seams and base flashing as recommended by the elastomeric membrane manufacturer prior to performing the repairs to the affected areas. Payment will be based on lineal feet (LF) of area covered. Refer to Statement of Work 1d(13) EPDM Roof and Flashing and Sheet Metal Specifications. | 200 | LF | 6.55 | $1,310.00 |
| B014 | Repair existing ballasted elastomeric membrane roofing systems. The repairs shall consist of the removal and storage of the existing ballast material to allow for the inspection of the existing membrane and to determine the location of the leak. The leak will then be repaired as recommended by the elastomeric membrane manufacturer and the existing removed ballast replaced to match the existing conditions. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(14) and EPDM Roofing Specifications. | 800 | SF | 5.68 | $4,544.00 |
| B015 | Remove and dispose off-site existing ballasted EPDM elastomeric membrane roofing system, complete, down to the roof deck substrate; remove and dispose off-site of all existing associated flashing; installation of new roof insulation shall produce R-48 value; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; the complete replacement with, and installation of, new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 150 | SQ | 829.15 | $124,372.50 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Utilization of tapered insulation to recreate existing and additional crickets for providing positive drainage of water to all existing roof drains. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailer material as may be required to properly install the finished roofing at no additional cost to the Government. Provide new wood nailer block materials, for perimeter blocking to accommodate new R-48 insulation; new replacement flashing shall be of ultra-violet resistant materials and as required to properly install the finished roofing system in accordance with the manufacturer’s recommendations and meeting the specification Section 07 13 53for elastomeric membrane roofing system. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d (15) and EPDM Roofing Specification. | |||||
| B016 | Remove and dispose off-site existing built-up roof system material (consisting of several layers – no ballast), complete, down to the roof deck substrate; remove and dispose off-site all existing associated flashing; installation of new roof insulation shall produce R-48 value; installation and mechanical fastening of new 7/16” thick OSB over new insulation per manufacturer’s recommendations to meet a 100 mile per hour wind resistance; the complete replacement with, and installation of, new fully adhered 60 mil thick Elastomeric Sheet Waterproofing (TPO) membrane roof system Specification Section 07 13 53 to new OSB, including all new associated flashing materials, fasteners and closures (in accordance with manufacturer’s design and recommendations) to ensure and develop a watertight installation and to be provided at no additional cost to the Government. | 750 | SQ | 895.07 | $671,302.50 |
| NOTE: Removal of all existing coping material and replacement with new coping material to match the existing coping material shall be ordered under separate exhibit line item. Utilization of tapered insulation to recreate existing and additional crickets for providing positive drainage of water to all existing roof drains. On roofs that are being repaired or replaced, all existing wood nailers shall NOT be reused. It shall be the Contractor’s responsibility to provide all new wood nailer material as may be required to properly install the finished roofing at no additional cost to the Government. Provide new wood nailer block materials, for perimeter blocking to accommodate new R-48 insulation; new replacement flashing shall be of ultra-violet resistant materials and as required to properly install the finished roofing system in accordance with the manufacturer’s recommendations and meeting the specification Section 07 13 53for elastomeric membrane roofing system. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(16) and EPDM Roofing Specification. | |||||
| B017 | Repair the existing metal roof mansard knuckles caused by sliding snow and/or ice. The repairs for the mansard knuckles will consist of replacing the damaged knuckles with new ones that match the existing knuckles in profile and color. Payment will be based on each (EA) knuckle that is repaired. Refer to Statement of Work 1d(17). | 30 | EA | 916.70 | $27,501.00 |
| B018 | Repair the damaged metal roofing sections caused by sliding snow and/or ice. The repairs of the roofing sections will consist of repairing any damaged plumbing pipe venting projecting through the roof and securing a watertight metal roofing section to match the gauge and color of the existing metal roofing section. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(18). | 30 | EA | 458.35 | $13,750.50 |
| B019 | Remove existing gravity flow and /or turbine type ventilators from the existing roofs and the patching of the existing sheathing to allow for the installation of the new ridge vent system. The existing roof sheathing material shall be removed along the ridge as required by the manufacturer’s recommendation to allow for the proper installation of the new ridge vent system as described in Specification Sections 07 31 13 Asphalt Shingles and 07 72 00 Roof Ventilators, Gravity Type. Payment will be based on linear feet (LF) of ridge to receive the work. Refer to Statement of Work 1d(19) and Asphalt Shingles and Roof Ventilators-Gravity Type Specifications. | 500 | LF | 5.89 | $2,945.00 |
| B020 | Remove the existing individual roof vents, shingles, felts and sheathing as required to allow for the installation of new sheathing, felts, shingles and new turbine vents. Payment shall be based on each (EA) vent installed. Refer to Statement of Work 1d(20) and Roof Ventilators-Gravity Type Specs. | 15 | EA | 348.14 | $5,222.10 |
| B020a | Provide the batten insulation or blown insulation which shall produce a R-48 value. Insulation shall be applied as per manufacture instructions and as described in Specification Sections 07 21 16 (Mineral Fiber Blanket Insulation) or Specification Sections 07 21 23 (Loose Fill Thermal Insulation), whichever the case may be. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(21). | 750 | SF | 4.99 | $3,742.50 |
| B021 | Emergency Repairs to shingled roofs consisting of at least 200 S.F. per building. Contractor shall mobilize within 24 hours of notification and evaluate work required by coordinating with PW Construction Representative. Repairs shall be implemented as outlined in Statement of Work. | ||||
| B021a | Replace broken/missing asphalt/ fiberglass 3-tab shingles (at least 200 SF per building). Refer to Statement of Work 1e(1). | 150 | SF | 3.50 | $525.00 |
| B021b | Replace broken/missing asphalt/ fiberglass Architectural Laminated shingles (at least 200 SF per building). Refer to Statement of Work 1e(2). | 150 | SF | 3.96 | $594.00 |
| B021c | Repair/replacement of ice panel flashing along eaves on existing roofs. Refer to Statement of Work 1e(3). | 250 | SF | 3.71 | $927.50 |
| B022 | Emergency Repairs to shingled roofs consisting of less than or equal to 199 S.F. per building. Contractor shall mobilize within 24 hours of notification and evaluate work required by coordinating with PW Construction Representative. Repairs shall be implemented as outlined in Statement of Work. | ||||
| B022a | Replace broken/missing asphalt/ fiberglass 3-Tab shingles (less than or equal to 199 SF per building). Refer to Statement of Work 1f(1). | 150 | SF | 3.71 | $556.50 |
| B022b | Replace broken/missing asphalt/ fiberglass Architectural Laminated shingles (less than or equal to 199 SF per building). Refer to Statement of Work 1f(2). | 150 | SF | 3.71 | $556.50 |
TOTAL FIRST YEAR PERIOD WORK, CLIN 2001 (ELINs C001-C022) $2,031,460.60
0002 Performance and Payment Bonds 1 EA $35,830.00 $35,830.00
TOTAL FIRST YEAR PERIOD WORK, CLINs 2001 - 2002 $2,067,290.60
2nd Year Work Period
| ITEM | DESCRIPTION | ESTIMATED QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT |
| 2001 | SECOND YEAR PERIOD WORK | ||||
| 2001 | Provide all supervision, plant, labor, material and equipment necessary to perform all work in connection with construction and repair/replacement of existing building roofs, including associated installation items, on various structures at Fort Drum, NY, in strict accordance with the Statement of Work, specifications and drawings, and subject to the terms and conditions of the contract, from 1 May 2017 through 30 April 2018. | ||||
| C001 | Remove and dispose off-site the existing roof asphalt and/or fiberglass shingle roof system complete, including felt(s), metal drip strip, ice and water barrier (if applicable), and flashing (if applicable) down to the existing sheathing. Inspect existing roof sheathing and framing for any possible damage and/or deterioration. Remove and replace any discovered damaged or deficient, sheathing and framing, to match the existing. Also included in the referenced main ELINs roof replacement are the following: Provide, place and install one layer of new roofing felt, complete, over the existing and any repaired/replaced exposed roof sheathing; Provide, place and install new flashing, complete, where existing roofing systems abuts vertical surfaces and per specifications and as shown on the Drawing Sheet 2 of 2 (Typical Flashing Detail); Provide, place and install new water barrier membrane (elastomeric sheet waterproofing) as specified in Section 07 13 53, complete, along all eaves and all valleys as shown on the Drawing Sheet 2 of 2 (Typical Water Barrier Installation Plan); Provide and properly install, along entire existing roof ridge, a new metal ridge vent system, complete as specified in Sections 07 31 13 Asphalt Shingles and 07 72 00 Roof Ventilators, Gravity Type. Finally, the referenced ELINs and roof replacement shall be completely finished with, and include the supply and installation of, new aluminum metal drip strip along all eaves, and new specified "architectural” laminated asphalt shingles, as specified in Section 07 31 13 Asphalt Shingles, and as reviewed, selected and approved by the Government in the roofing material submittal process. Any other trim and accessories necessary shall be installed, as required for a complete roof installation, at no additional cost to the Government. Payment will be based on a single roofing square unit (SQ). Each single roofing square unit or (square) equals 100 SF. Refer to Statement of Work 1d(1), Drawing Sheet 2 of 2 and Asphalt Shingles Specifications. | 125 | SQ | 722.78 | $90,347.50 |
| C002 | Inspect, remove, dispose off-site and replace existing wood roof substrate sheathing found to be damaged or deficient and shall match the existing sheathing dimensions. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(2) and Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 1,500 | SF | 6.14 | $9,210.00 |
| C003 | Inspect, remove, dispose off-site and replace existing wood roof soffit/eave framing and fascia boards members that are found to be damaged or deficient and shall match the existing framing or fascia board dimensions. Payment will be based on board feet (BF). Refer to Statement of Work 1d(3), Drawing Sheet 2 of 2 and Rough Carpentry Specifications. | 800 | BF | 10.04 | $8,032.00 |
| C004 | Remove and off-site dispose existing solid metal soffit covering and/or exposed wood soffit sheathing complete; inspect the existing exposed wood soffit framing along the underside of existing roof eave; installation of new perforated, continuously vented, finished metal soffit material to match the existing soffit color finish or approved equal, complete, along the underside of existing roof eave, over existing and/or repaired (if applicable) portions of open wood soffit framing. New metal soffit material color and finish shall be, as selected, reviewed and approved by the Government Contracting Officer's Representative, from the manufacturer’s standard colors and finishes, through the Contract submittal process. Payment will be based on square feet (SF) of area covered. Refer to Statement of Work 1d(4), Drawing Sheet 2 of 2, Flashing-Sheet Metal Specifications. | 750 | SF | 6.98 | $5,235.00 |