Industry Questions Answers W911RX26QA020.pdf
PDF 32 KB Posted
- Attached to
- Crane 2BCT
- Solicitation number
- W911RX26QA020
About this file
This is an Industry Questions & Answers document that addresses three clarifications regarding a federal contract opportunity.
The document confirms that no lift plan is required to be provided by contractors for this project. Vehicle tonnage specifications are stated in US tons rather than metric tonnes. The period of performance is confirmed as March 10th through 13th, 2026, clarifying that despite schedule updates referenced in an amendment, this four-day timeframe remains accurate.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry Questions & Answers
Is there a lift plan for this project or will you need one provided?
Answer No lift plan needed
Are the tons listed for the vehicles US tons or Metric tonne?
Answer US tons
The amendment states that the schedule was updated but the period of performance still states - March 10th-13th. Is this correct?
Answer Yes, March 10th- 13th 2026 is the accurate time frame.