Questions from Industry

W911RX-19-R-0001, MATOC

20 Sept 18

Q. 1. Can you confirm if the response is due Monday, November 12, 2018 or Friday, October 12, 2018?

Answer: Responses are due Monday, November 12, 2018

Q. 2. Do you have an estimated average for the size of task orders on this MATOC?

Answer: Paragraph three, "anticipated task orders shall be firm fixed price with a magnitude up to $5,000,000.00". That is our closes estimate at this time.

Q.3. Please advise if W911RX-19-R-0001 is a new requirement or if there is an incumbent. If existing, who is the incumbent and what is the current contract value and contract number?

Answer: This is a new requirement with no incumbent Contractor existing.

Wk. 24th – 28th Sept 18 Q. Do any of the projects include upgrades of heavy industrial equipment (gear boxes, cranes, etc.) or is it mainly buildings and facilities (plumbing, electrical, roofing, etc.)?

Answer: Yes, opportunities may exist for projects for fixing or replacing Industrial cranes and other heavy equipment under this potential contract.