Scope of Work
Install additional video surveillance (CCTV) to the system already installed in the hospital manufactured by Panasonic and Brocade.
All CCTV equipment will be installed per the locations that are identified in yellow on the attached spread sheet The cameras will be controlled and monitored using the existing Panasonic system All cameras will be installed using ladders
- Installation of 53 new video surveillance (CCTV) system manufactured by Panasonic. The system is standalone and will not require remote monitoring.
- All CCTV head-end equipment will be installed per drawing and SOW.
- Cameras to be controlled and monitored using the Panasonic system. Video will be viewed and monitored from the server. Client workstations are included in the proposal.
- All cameras are IP based network cameras. Power for the cameras will be provided via a managed POE switch located as shown on the drawings.
- All cameras will be surface/ceiling mounted.
- Cameras and CCTV equipment to be installed at locations discussed and Identified during the site visit walk through.
- Provide and install camera network cabling to 53 camera locations based off of option 1 additional CCTV spec summary 7.1, table 2. To include terminations, labeling, and testing.
- Provide and install cabling pathway for 14 inside hospital locations that don’t have pull sting, penetration or conduit back to cable tray. As listed on 7.1 optional additional CCTV spec summary, table 2
- Provide and install cabling pathway for 12 parking garage locations that don’t have pull sting, penetration or conduit back to the garage TR. Pathways will consist of outdoor rated “IMC” conduit and weatherproof boxes.
- Provide, install, terminate, label and test Outside Plant (OSP) 12 strand single mode fiber and associated enclosure equipment from parking garage TR to hospital basement vault location
- Provide, install, terminate, label and test Optical Fiber Nonconductive Plenum (OFNP) 12 strand single mode fiber and associated enclosure equipment from hospital basement vault location to computer room 3E118, RR1, 7th fiber termination panel
- Provide grounding and bonding to ANSI-J-STD-607-A standards for the garage TR and the (OSP) cable entering the parking garage and hospital vault.
- Provide Cat6 cable certification reports upon completion of project
- Provide fiber Optical Time Domain Reflectometer (OTDR) and light attenuation certification reports upon completion of project