Questions_and_Answers_for_Industry,_W911RX-17-Q-0023,_Old_PX_HVAC_System,_9_Feb_17.docx
DOCX document 13 KB Posted
- Attached to
- Replace and Install HVAC
- Solicitation number
- W911RX-17-Q-0023
About this file
Questions from Industry
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Corrected_Exhibit_B,_RFQ_17-Q-0023.pdf | ||
| Exhibit_D,_PRS,_W911RX-17-Q-0023.docx | DOCX document | |
| Exhibit_C,_Wage_Determination_W911RX-17-Q-0023.pdf | ||
| Exhibit_A,_PWS,_W911RX-17-Q-0023,_.pdf | ||
| Exhibit_B,_RFQ_17-Q-0023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBJECT: W911RX-17-Q-0023, Old PX HVAC Replace/Install
Questions from Industry
9 Feb 17 Q: Bidders observed stored material in the warehouse area directly beneath the Carrier unit. Will the government clear this area for work inside the building?
A: Arrangements will be made for the customer to move their items.
Q: Will the government allow the Contractor to construct a new or expanded penetration through the roof, as required?
A: Yes. However, keep in mind all penetrations will have to be sealed properly to prevent the elements entering the building.
Q: Is an offer guarantee required?
A: No
Q: The loading dock area will be obstructed for a period of time necessary for a crane to set the new unit in place on the roof. Additionally, personnel working in the warehouse area will need to be cleared from the area beneath the unit during this process. Are these conditions acceptable to the government?
A: Yes
Q: Based on our experience, the cooling season at Fort Riley commences on or around 4/15. However, due to the lead time on the new unit, installation may occur after 4/15. Will the government accept installation after 4/15?
A: YES. The unit is unserviceable now so it really doesn’t matter.