ACC-DTA Army Manufacturing Rodeo sUAS Manufacturing Rodeo CSO Process.pdf

PDF 221 KB Posted

Attached to
U.S. Army Contracting Command – Detroit Arsenal (ACC-DTA) Army Manufacturing Rodeo: sUAS Manufacturing Rodeo
Solicitation number
W911RQ-27-S-C002
Issued by

About this file

This document is a briefing presentation on the Army Contracting Command–Detroit Arsenal (ACC-DTA) Commercial Solutions Opening (CSO) for the sUAS Manufacturing Rodeo, presented by Mr. Jeffrey W. Edens, ACC-RRAD Chief Contracting Officer on November 16, 2026.

The CSO follows a three-phase competitive process with specific submission and evaluation timelines. Phase 1 (Solution Synopsis) requires submissions by November 18, 2026, with government evaluation from November 18–20, 2026, to conduct initial screening and high-level technical feasibility review. Phase 2 (Detailed Technical Submission) is requested on November 20, 2026, with submissions due November 24, 2026, and government evaluation through November 30, 2026, to perform in-depth technical review. Phase 3 (Commercial Solutions Proposals) is requested on November 30, 2026, with submissions due December 7, 2026, and government evaluation from December 7–18, 2026. The target contract award date is December 18, 2026, contingent upon sufficient funding.

The procurement seeks small unmanned aircraft systems (sUAS) with six primary platform thresholds and four execution outcomes. Manufacturing thresholds include an affordable unit cost ceiling of $3,000, domestic supply chain assurance with constraint mitigation and adversary component exclusions, lethality with terminal standoff precision strike capability including GFE and MK118 integration, contested spectrum and EW/GNSS-denied survivability, scalable 1:20 ground control station (GCS) ratio architecture, and open architecture with modularity and interoperability (MOSA, MAVLink-M, ATAK CoT, APEX/sUPI). Execution outcomes require rapid production of 400 aircraft and 20 GCS with 10 percent early delivery by February 15, 2027; DCMA physical teardown and 100 percent CONUS assembly verification; warfighter operational benchmarking at Gauntlet III in March 2027; and scaled surge drills with depot co-production transition supporting options up to 10,000 units with RIA/TYAD integration.

View the file

Other files

File Type Posted
Att A_DCMA BOM Template.xlsx XLSX spreadsheet
W911RQ-27-S-C002 ACC-DTA.pdf PDF
W911RQ-27-S-C002 ACC-DTA.pdf PDF
Att A_DCMA BOM Template.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

UNCLASSIFIED

ACC-DTA

sUAS MANUFACTURING RODEO

Mr. Jeffrey W. Edens – ACC-RRAD CCO 16 NOV 2026

U.S. ARMY

CONTRACTING

COMMAND

DETROIT ARSENAL

ARMY CONTRACTING COMMAND- DETROIT ARSENAL 2

CUI

CUI

BRIEFING PURPOSE

▪ Subject: Process map and award schedule for Army Contracting Command – Detroit Arsenal (ACC-DTA)

Commercial Solutions Opening (CSO) Army Manufacturing Rodeo: sUAS Manufacturing Rodeo

▪ Agenda:

– CSO Process & Detailed Timeline

– Desired Outcomes

ARMY CONTRACTING COMMAND- DETROIT ARSENAL 3

CUI

CSO PROCESS & DETAILED TIMELINE

Phase 1: Solution Synopsis

Submission Receipt Date: November 18, 2026 Government Evaluation Period: November 18 - 20, 2026 Outcome of this Phase: Initial screening & high-level technical feasibility review and selection of submissions for

Phase 2.

Phase 2: Request for Phase 2 Detailed Technical Submission on November 20, 2026 Submission Receipt Date: November 24, 2026

Deadline for vendors who successfully passed Phase 1 to submit their Phase 2 submission.

Government Evaluation Period: November 24 - 30, 2026 Outcome of this Phase: In-depth technical review complete and selection of submissions for Phase 3.

Phase 3: Request for Commercial Solutions Proposals (CSP) on November 30, 2026 Submission Receipt Date: December 7, 2026

Finalists from Phase 2 are expected to submit proposals 7 days after the Phase 2 evaluation concludes.

Government Evaluation Period: December 7 - 18, 2026 Outcome of this Phase: Target Contract Award Date: December 18, 2026 (dependent upon sufficient funding).

ARMY CONTRACTING COMMAND- DETROIT ARSENAL 4

CUI

CSO DESIRED OUTCOMES

Section 6.1.3 (sUAS Manufacturing & Platform Thresholds):

– Outcome 1: Affordable Mass & Unit Cost Ceiling ($3,000)

– Outcome 2: Domestic Supply Chain Assurance & Constraint Mitigation (integrating the supply chain constraint analysis, actionable plan, and adversary component exclusions)

– Outcome 3: Lethality & Terminal Standoff Precision Strike (including GFE and MK118 integration)

– Outcome 4: Contested Spectrum & EW/GNSS-Denied Survivability

– Outcome 5: Scalable Control Ratio Architecture (1:20 GCS ratio)

– Outcome 6: Open Architecture, Modularity, & Interoperability (MOSA, MAVLink-M, ATAK CoT, APEX/sUPI)

▪ Section 6.1.4 (Proving Ground, Stress-Testing, and Scaled Execution):

– Outcome 1: Rapid Production Batch & GFE Ingestion (400 aircraft, 20 GCS, with 10% early delivery by 15 Feb

2027)

– Outcome 2: DCMA Physical Teardown & 100% CONUS Assembly Verification

– Outcome 3: Warfighter Operational Benchmarking at Gauntlet III (March 2027)

– Outcome 4: Scaled Surge Drills & Depot Co-Production Transition (options up to 10,000 units, RIA/TYAD integration, and stress drill resilience)

ACC-DTA�sUAS Manufacturing Rodeo
Briefing purpose
CSO Process & detailed timeline
CSO Desired outcomes�

File details come from the government source that posted it. Updated .