02 MAR 2023
Questions and Answers in Response to:
Combined Synopsis/Solicitation W911QY-23-R-1011
Service and Preventative Maintenance Agreement for Highly Sensitive, Mission Critical Agilent Instrumentation
Question 1:
1. Is this a new requirement or a follow-on service agreement to a previous contract? If this is a follow-on requirement, please provide the prior federal contract# or Award ID#.
Answer 1:
This is a follow-on contract.
Prior contract #: W911QY-21-P-0106 (PoP: 03 May 2021 to 02 May 2022) Prior contract #: W911QY-20-P-0108 (PoP 29 May 2020 to 28 May 2021)
Question 2:
2. Please advise when the last PMs have been completed on these systems (month/year).
Answer 2:
a) Agilent 7890A GC-FID System: Last PM Done March 2020
b) Agilent 7890B GC-MS System: Last PM Done July 2021
c) Agilent GC-MS w/ CTC CombiPAL System: Last PM Done July 2021
d) Agilent LC-MS Single Quad System: Last PM Done July 2021
e) ICP-OES System: Last PM done March 2022
Question 3:
Please advise if these systems were previously maintained exclusively by the OEM (Agilent) technicians or third-party technicians.
Answer 3:
Agilent Mineral analyzer ICP OES exclusively by the OEM. Other instruments OEM and third-party technicians.