Amendment_0001.pdf

PDF 322 KB Posted

Attached to
Cold Temperature and Artic Protective System (CTAPS)
Solicitation number
W911QY18R0034
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
07_Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Attachment_7_Component_List_.xlsx XLSX spreadsheet
Attachment_2_Fabrics_Revised_.xlsx XLSX spreadsheet
Attachment_6__3D_Base_Layer_Undershirt_and_Drawer_Drawing.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Atatchment_6_Drawings.pdf PDF
Attachment_3_52.212-3_Reps_&_Certs.pdf PDF
Attachment_5_Solicitation_Clauses.pdf PDF
Attachment_2_Fabrics.xlsx XLSX spreadsheet
Attachment_4_Past_Performance_Questionnaire.pdf PDF
Attachment_1_Supply_Requirement.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment00001 to W911QY18R0034

For Cold Temperature and Artic Protective System (CTAPS) Project

Answers to Technical Questions:

1. Are all required materials already in stock/ available on request?

Answer: Most materials are in stock. The offerors will need to verify with the fabrics vendors the availability.

2. If all required materials are not available right away, have Natick placed a production order already?

Answer: No.

3. Does Natick have a vendor to perform a dyeing of the base layer material? Is it required piece dyeing or garment dyeing?

Answer: No, and either piece dyeing or garment dyeing is acceptable.

4. Would the fabric mill of the base layer material perform piece dyeing?

Answer: The offerors will need to verify with the mill if that is an option.

5. Does Natick expect the recommendations, suggestions and ideas for the Design Review to only be communicated with a physical sample or it can me Illustrations and make be small mock up component samples(not a full garment)?

Answer: Illustrations that are accompanied with small mock up component samples (not a full garment) is sufficient for the design review.

6. What is the timeline for the First Design Review after award date?

Answer: The first design review shall be held within 5 business days of contract award.

7. Once the recommendations are discuss and either approved or disapproved during the Design Review, does Natick require a Physical prototype to represent the changes? Let's call this Proto #1.

Answer: Once the recommendations are discussed and either approved or disapproved during the Design Review.

8. If Proto #1 is required, what is the purpose of the samples (let's call them Proto #2) that are being asked for, using a surrogate materials?

Answer: Natick does require a Physical prototype to represent the changes which will serve as the mock up sample using surrogate material.

9. Is there an option of a face to face Design review and Pre-production meeting?

Answer: Yes, these meetings can be held at NSRDEC.