SMALL BUSINESS SET-ASIDE FOR the fabrication of quantity 100 aluminum 120-millimeter (mm) sabots.
Solicitation number
W911QX-25-Q-0009
Issued by

About this file

The document is a Salient Characteristics amendment for the fabrication of quantity 100 aluminum 120-millimeter (mm) sabots. The Government requires the Contractor to fabricate the sabots using 7075-T6 aluminum in either a three (3)-petal or four (4)-petal configuration. The first lot of 20 sabots must be delivered within 90 days of contract award, and the remaining 80 sabots must be delivered within 150 days of award. The Government will inspect the sabots at the Contractor's facility prior to delivery to ensure proper fit with the provided penetrators. Shipping and handling to Aberdeen Proving Ground, MD 21005 is included. This requirement is being solicited as a Small Business Set-Aside under Solicitation Number W911QX-25-Q-0009 by the Department of the Army Materiel Command, Army Contracting Command Aberdeen Proving Ground.

View the file

Other files

File Type Posted
Solicitation (Under SAT).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template last updated 07/28/2016

Salient Characteristics for Non-Commercial Supply 21 October 2024

Signature (typed name):

Technical Point of Contact (TPOC)

The Government requires the fabrication of aluminum sabots, in accordance with the below minimum specifications:

1. The Contractor shall fabricate quantity (qty) 100 aluminum 120-milimeter (mm) sabots per the specifications provided by the Government in drawing #28084184.

o The Contractor shall use 7075-T6 aluminum in either a three (3)-petal or four (4)-petal configuration.

o Each sabot set shall assemble around the penetrator in accordance with (IAW) drawing Attachment 1 - #ARL-TF-20240701 as detailed in drawing Attachment – 2 - #ARL-TF-20240801 provided by the Government.

2. The Contractor shall deliver the first lot of qty 20 no later than 90 days after contract award.

o The Government will perform an inspection at Contractors facility to determine proper fit with the penetrator IAW drawing Attachement 1 - #ARL-TF-20240701 as detailed in drawing Attachment 2 - #ARL-TF-20240801 prior to delivery.

The Government will furnish solid models to the Contractor, via solidworks files or a neutral format file, in addition to penetrators for inspection.

3. The remaining qty of 80 shall be delivered no later than 150 after contract award.

Multiple lot delivery is acceptable.

4. An inspection report shall be included with each delivery.

5. Shipping and handling to Aberdeen Proving Ground (APG), MD 21005 shall be included.

Melissa.M.Murphy Highlight

Melissa.M.Murphy Highlight

Melissa.M.Murphy Highlight

Template last updated 07/28/2016

Contracting Officer:

10/21/2024

X Morgan J. Evans

Contracting Officer (KO) Signed by: EVANS.MORGAN.JAYNE.1261050435