This document is a contract amendment (Standard Form 30) for solicitation W911PT25R0011, adding five new Contract Line Item Numbers (CLINs 0029-0033) for machine rigging services at the Watervliet Arsenal in New York. The amendment covers rigging services for five specific machines: a Horizontal Shaper Bed (WV12212), a Horizontal Shaper (WV12718), a Manual Lathe (WV02254), and two CNC Lathes (WV12784 and WV12783), with each machine being moved from its current location to an "excess" status.
Key details include a Performance of Performance period from July 1, 2025 to June 30, 2026, a project magnitude between $250,000 and $500,000, and 100% Payment and Performance Bonds requirement. The Contracting Officer Representative is Timothy Fontaine, and the contract will be administered by the Army Contracting Command-WVA Services Team. Each CLIN follows the NY2 Wage Determination and will be inspected and accepted by the government at the destination, with delivery to the Watervliet, NY address. The solicitation appears to be a 100% set-aside for HUBZone Small Businesses.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W16H1F504300KV
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
To add CLIN0029-CLIN0033 for 5 additional machines to have rigging performed.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-May-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911PT25R0011
X 9B. DATED (SEE ITEM 11)
13-May-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-May-2025
CODE
ARMY CONTRACTING COMMAND-WARREN (WVA)
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
W911PT 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911PT25R0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
MACHINE LIST
Priority WV# Type of Machine Location Action To Location Price
1 WV12803 Gundrill (Trotec) 25(1)-H-00 Excess N/A $
2 WV13028 Surface Grinder (KAAST) 20-E-08 Move 20-A-5 $
3 WV12320 Filament Winder 110-D-17 Excess N/A $
4 WV12726 Filament Winder 110-D-15 Excess N/A $
5 VA-97-02 CMM 35-G-05 Excess N/A $
6 WV11961 Surface Grinder (G & L) 20-A-07 Excess N/A $
7 WV12779 Grinding Machine (Holroyd) 25(2)-B-06 Excess N/A $
8 WV6318 Spring Tester Incoming Inspection Excess N/A $
9 WV10434 Slotter (Morey) 20-E-08 Move 20-A-6 $
10 WV10273 ID Grinder (Heald) 35-B-10 Excess N/A $
11 WV8758 ID Grinder (Bryant) 35-B-12 Excess N/A $
12 WV12692 Dual Spindle Horizontal Mill (Producto)
20-E-01 Excess N/A $
13 WV12588 Hollow Spindle Lathe (R&D) 35-A-31 Excess N/A $
14 WV12525 Lathe (Hardinge) 25(1)-G-02 Excess N/A $
15 WV12528 Lathe (Hardinge) 25(1)-G-03 Excess N/A $
16 WV12315 Lathe (Cinn. Milacron) 25(1)-G-04 Excess N/A $
17 WV12316 Lathe (Cinn. Milacron) 25(1)-H-04 Excess N/A $
18 WV12345 V.T.L. (Bullard) 35-F-20 Excess N/A $
19 WV12186 Vertical Mill (White Sundstrand
25(1)-A-00 Excess N/A $
20 WV12633 Vertical Mill (Seaburg) 25(1)-D-08 Excess N/A $
21 WV9365 Surface Grinder (G & L) 25(2)-E-07 Excess N/A $
22 WV8732 Grinding Machine (G & L) 25(2)-C-04 Excess N/A $
23 WV10038 Gundrill (Ex-Cell-O) 35-E-12 Excess N/A $
24 WV06273 Radial Arm Drill (Cicinnati) 35-E-12 Excess N/A $
25 WV11207 Thread Mill (Wickes) 35-E-10 Excess N/A $
26 WV5739 Gear Shaper (Fellows) 35-E-10 Excess N/A $
27 WV09938 Horizontal Mill 25(1)-C-09 Excess N/A $
28 WV02195 Horizontal Mill 25(1)-C-09 Excess N/A $
29 WV12212 Horizontal Shaper Bed 110-B-40 Excess N/A $
30 WV12718 Horizontal Shaper 110-B-40 Excess N/A $
31 WV02254 Manual Lathe 110-D-36 Excess N/A $
32 WV12784 CNC Lathe (Hankook) 35-E-5 Excess N/A $
33 WV12783 CNC Lathe (Hankook) 35-E-6 Excess N/A $
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0029 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0029 1 Lot OPTION Machine Rigging MR002
FFP
Contractor to Rig Horizontal Shaper Bed # WV12212 from 110-B-40 to excess as per SOW #MR002.
Wage Determination General Decision Number: NY2 Latest Revision applies and is incorporated.
Magnitude of this entire Project is between $250,000 and $500,000.
Period of Performance is 180 calendar days from receipt of Notice to Proceed.
Contracting Officer Representative is Timothy Fontaine.
100% Payment and Performance Bonds are required.
FOB: Destination
NSN: AASSVC504300KV
MILSTRIP: W16H1F504300KV
PSC CD: Z1EC
NET AMT
CLIN 0030 is added as follows:
0030 1 Lot OPTION Machine Rigging MR002
FFP
Contractor to Rig Horizontal Shaper # WV12718 from 110-B-40 to excess as per SOW #MR002.
Wage Determination General Decision Number: NY2 Latest Revision applies and is incorporated.
Magnitude of this entire Project is between $250,000 and $500,000.
Period of Performance is 180 calendar days from receipt of Notice to Proceed.
Contracting Officer Representative is Timothy Fontaine.
100% Payment and Performance Bonds are required.
FOB: Destination
NSN: AASSVC504300KV
CLIN 0031 is added as follows:
0031 1 Lot OPTION Machine Rigging MR002
FFP
Contractor to Rig Maunal Lathe # WV02254 from 110-D-36 to excess as per SOW #MR002.
Wage Determination General Decision Number: NY2 Latest Revision applies and is incorporated.
Magnitude of this entire Project is between $250,000 and $500,000.
Period of Performance is 180 calendar days from receipt of Notice to Proceed.
Contracting Officer Representative is Timothy Fontaine.
100% Payment and Performance Bonds are required.
FOB: Destination
NSN: AASSVC504300KV
CLIN 0032 is added as follows:
0032 1 Lot OPTION Machine Rigging MR002
FFP
Contractor to Rig CNC Lathe (Hankook) # WV12784 from 35-E-5 to excess as per
SOW #MR002.
Wage Determination General Decision Number: NY2 Latest Revision applies and is incorporated.
Magnitude of this entire Project is between $250,000 and $500,000.
Period of Performance is 180 calendar days from receipt of Notice to Proceed.
Contracting Officer Representative is Timothy Fontaine.
100% Payment and Performance Bonds are required.
FOB: Destination
NSN: AASSVC504300KV
CLIN 0033 is added as follows:
0033 1 Lot OPTION Machine Rigging MR002
FFP
Contractor to Rig CNC Lathe (Hankook) # WV12783 from 35-E-6 to excess as per
SOW #MR002.
Wage Determination General Decision Number: NY2 Latest Revision applies and is incorporated.
Magnitude of this entire Project is between $250,000 and $500,000.
Period of Performance is 180 calendar days from receipt of Notice to Proceed.
Contracting Officer Representative is Timothy Fontaine.
100% Payment and Performance Bonds are required.
FOB: Destination
NSN: AASSVC504300KV
SECTION E - INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for CLIN 0029:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
Destination Government Destination Government
The following Acceptance/Inspection Schedule was added for CLIN 0030:
The following Acceptance/Inspection Schedule was added for CLIN 0031:
The following Acceptance/Inspection Schedule was added for CLIN 0032:
The following Acceptance/Inspection Schedule was added for CLIN 0033:
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule for CLIN 0029 has been added:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 01-JUL-2025 TO
30-JUN-2026
N/A ARMY CONTRACTING COMMAND-WVA
SERVICES TEAM
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
518-266-4535 FOB: Destination
W911PT
The following Delivery Schedule for CLIN 0030 has been added:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 01-JUL-2025 TO
30-JUN-2026
N/A ARMY CONTRACTING COMMAND-WVA
SERVICES TEAM
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
518-266-4535
The following Delivery Schedule for CLIN 0031 has been added:
CAGE
POP 01-JUL-2025 TO
30-JUN-2026
N/A ARMY CONTRACTING COMMAND-WVA
SERVICES TEAM
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
518-266-4535
The following Delivery Schedule for CLIN 0032 has been added:
CAGE
POP 01-JUL-2025 TO
30-JUN-2026
N/A ARMY CONTRACTING COMMAND-WVA
SERVICES TEAM
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
518-266-4535
The following Delivery Schedule for CLIN 0033 has been added:
CAGE
POP 01-JUL-2025 TO
30-JUN-2026
N/A ARMY CONTRACTING COMMAND-WVA
SERVICES TEAM
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4050
518-266-4535
(End of Summary of Changes)
File details come from the government source that posted it. Updated .