This document contains a question and answer log for solicitation W911PT-21-R-0012 regarding the procurement of a magnetic particle inspection booth. The solicitation is for one Magnetic Particle Inspection Booth Gould Bass 3509A-01 or equal for Watervliet Arsenal in Watervliet, NY, with an option for one additional booth. Questions were accepted until 11 August 2021. The log addresses questions on receiving a drum of carrier and boxed accessories separately from the equipment, as well as temporarily storing an uncrated booth on-site for up to two weeks until installation. The Department of the Army Materiel Command TACOM Life Cycle Management Command is the contracting agency.

View the file

Other files

File Type Posted
Amendment 001-W911PT-21-R-0012.pdf PDF
W911PT-21-R-0012.pdf PDF
Comply Sheets Mag Particle Booth specification 14-21-6625.xlsx XLSX spreadsheet
W911PT-21-R-0012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WVA Magnetic Particle Inspection Booth

W911PT-21-R-0012

Question & Answer Log

Questions will not be accepted, nor answered, on Solicitation W911PT-21-R-0012 after 11-AUG-2021, 12:00 PM EST.

Document
Document Reference
Question/Comments
Answer/Response
Date Received
Date Posted

Solicitation

Can Watervliet receive the drum of Carrier & boxed accessories through WVA receiving and not with the equipment? Also I want to confirm that you do not need a drum pump for the oil. Typically companies prefer a specific type of pump for their operations.
The drum of Carrier and accessories can be sent to the standard WVA receiving department, WVA does not need a drum pump.
7/30/21

Solicitation

Per your contract I need to be on-site for the delivery and placement of the equipment. I am working with (2) riggers and there is a question as to whether WVA can hold the equipment on-site until I arrive to see its uncrating and placement. My question is can my riggers unload the crated equipment at WVA, then return with me when I am available to uncrate it and put in place. I would like to store it there for no longer than 2 weeks.
WVA prefers to have the delivery and installation occur at the same time. However, if needed WVA can accommodate a separate timeframe for delivery and installation, as long as the Government is given the dimensions for the container in advance.
08/02/21

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

Solicitation

File details come from the government source that posted it. Updated .