SEE ADDENDUM
(No Collect Calls)
W911PT21Q0098 07-Sep-2021
b. TELEPHONE NUMBER
518-266-3933
8. OFFER DUE DATE/LOCAL TIME
04:00 PM 07 Oct 2021
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W911PT9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
PETER HASCHYTZ
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ARMY CONTRACTING COMMAND-WARREN (WVA)
ATTN: CCTA-HDW/BLDG 10
1 BUFFINGTON STREET
WATERVLIET NY 12189-4000
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS AX
13b. RATING
DO-B9
CODE15. DELIVER TO CODE W16H1F 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
TRANSPORTATION OFFICER
MATTHEW ARMBRUSTER
WATERVLIET ARSENAL
TAWV-IML-S/BLDG 35
SHIPPING AND RECEIVING
WATERVLIET NY 12189-4000
TEL: 518-266-5858 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
NAICS:
333517
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF83
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W911PT21Q0098
Section SF 30 - BLOCK 14 CONTINUATION PAGE
SPECIFICATION
U.S. ARMY
WatervlietArsenal
Watervliet, NY Equip. Engineering SOW # 20-21-3419 Date: 12 July 2021
ONE NEW 100 TON PRESS
This statement of work defines the requirements for a Greenerd HCS-100-27L3 100 Ton Press or equal.
REQUIRED OPTIONS:
Features:
-Table and ram plates held parallel within .003” per foot.
-Ram travel square to table within .001” in any 4” section of stroke.
-Bed bolster plate ground steel; 4” thick, removable for machining.
-Clear area 24” x 3” behind table -Two ground rods guide the ram throughout the stroke. Prevents ram rotation.
-Continuously filtered oil; 10-micron filter with replaceable filter element.
-Adjustable up and down limits.
-Pressure and distance reversal.
-Electronic “Joystick” Ram Control: Joystick provides control of ram travel and ram force.
Free hand must actuate and hold a palm button for joystick to be activated. Pushing the joystick forward starts downward movement of the ram. A separate limiting control can be adjusted to pre-set a maximum force available at the ram. Release of either the joystick or the palm button maintains the ram position, but pressure will be released.
-Electronic press control with two line keypad (touchscreen).
-Pressure must be displayed when in use on control.
Accessories:
-Removable Ram Nose Tool with 1” wide flat.
-Straightening anvils that cradle the OD of the part, quantity 2. Anvil height 10” from table to centerline of part. Capable of handling up to a 6” diameter part. There will not be any rollers on the Anvils for rotating the part.
Specifications:
Tons of Ram Force ................................................................................adjustable from 5 to 100 Table Dimensions........................................................................................... 72” L-R x 24” F-B Throat ...................................................................................................................................... 14”
Daylight (maximum open distance) ........................................................................................ 18” Stroke .................................................................................. adjustable from 1” to maximum 18” Floor to Table .......................................................................................................................... 36” Clearance between ribs under press bolster (table) ................................................................... 9” Press Size .................................................................................... 72” L-R x 82” F-B x 128” Tall Guiding System ............................................................................................................ Ram Link Pump Capacity ............................................................................................... 27 GPM & 3 GPM Cylinder Bore .......................................................................................................................... 10” Ram Diameter ........................................................................................................................... 7” Ram Speed: Close, inches per minute Ram Speed: Press, inches per minute Ram Speed: Open, inches per minute Maximum System Pressure Motor .............................................................................................................. 10 HP, 1,800 RPM Weight, approximate lbs. ...................................................................................................22,000
Work to be Performed by the Contractor. This project is classified as a turn-key with the contractor being responsible for all-work associated with the installation. The Contractor shall be solely responsible for costs associated with skidding and shipment, rigging and installation at WVA. The contractor is responsible for the removal of wood block flooring and existing concrete preparation. The contractor shall also provide competent English speaking service personnel to install the machine, rough and finish level the machine, startup, and conduct the acceptance tests specified. The contractor personnel shall remain until the machine activation and testing have been successfully completed. Watervliet Arsenal personnel will not provide assistance for installation, diagnosis, troubleshooting, or repair of the equipment during activation and testing.
Note: It is preferred to not have to drilling into concrete floor, to hold machine down on concrete. Typical floor thickness at Watervliet is 8”-10”.
Contractor personnel shall coordinate the shipment of the machine to Watervliet.
Contractor personnel shall arrange for rigging services to off load the machine and contractor personnel shall be on-site at Watervliet when the machine arrives and is off loaded. The Contractor shall ensure any outside rigging services only use certified chain hoists, with all rigging slings tagged and certified for the weights being lifted. Contractor personnel shall supervise the placement of the machine on the installation site by the rigging service. Arsenal forklifts and Arsenal personnel are typically not available to assist with installation. All forklifts used shall be propane powered forklifts and equipped with a roll cage and backup signal. Operators of forklifts shall have and be able to produce valid forklift licenses. Arsenal overhead pendant cranes (within load capacities) may be used by the contractor/rigging service for the installation to be operated by Arsenal personnel. Crane capacity within each building is limited (2 tons). The Contractor shall provide alternate lifting means if installation tasks exceed capacity.
Contractor personnel shall also adhere to the WVA requirements to wear OSHA approved safety glasses and safety shoes while in the manufacturing shop areas. The contractor shall provide all equipment and materials necessary for the installation of the machine.
The contractor shall remove from WVA and dispose of all wastes (other than hazardous wastes) generated from uncrating and unpacking the machine at a permitted off-post disposal facility, in accordance with Attachment D of this specification and the document "WATERVLIET ARSENAL (WVA) INFORMATION FOR CONTRACTORS" which is available on the Watervliet Arsenal website.
IMPORTANT: Under normal circumstances the contractor will be allowed to work as long as is desired during normal work days. Contractor work outside Watervliet’s normal work days cannot be guaranteed. Watervliet is on a condensed work schedule. Normal work hours/days for this schedule are four 9-hour workdays (Friday off) one week and four 9-hour days, one 8-hour day (Friday) the following week. Contractor work on the Friday off and weekends cannot be guaranteed. Foreign National contractor personnel require escort, which may restrict installation site availability based on Watervliet’s ability to provide the escort.
Certification The contractor shall provide written certification that the machine tool including all specified systems, accessories, geometric accuracies are provided with offer.
Work Piece Acceptance Test: As part of the acceptance testing at WVA, the contractor shall conduct a test on a part provided by WVA that the provided machine is capable of performing on standard WVA parts.
Warranty:
Upon final acceptance of the machine a Standard Commercial Warranty shall commence for duration of One Year, to include as a minimum, parts and labor for the duration of the warranty, at no cost to the Government. The one year period shall commence from the date of notification by the Contracting Officer of the final acceptance.
ATTACHMENT D
Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulation, policy, Host Tenant Agreement, Interagency Service Support Agreement, or Status-of-Forces Agreement. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR).
2. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick- Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials;
recyclable materials; materials that are resource-efficient; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse.
3. Compliance with License and Certification Requirements: Contractor shall obtain all license and certification required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specification of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award.
4. Notification of Federal and State Regulators: Contractor shall immediately notify the Designated Government Representative (DGR) and COR of the arrival on site of any Federal, State, and/or DoD environmental regulator or enforcement agent and/or the receipt of any correspondence from a Federal or State environmental agency.
5. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. If an inspection is conducted, it will not stop or disrupt ongoing contract activities. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality.
6. Reporting Noncompliance: Contractor shall immediately report any nonconformance and/or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies to the COR and DGR.
7. Verification of National Environmental Policy Act Documents: Contractor shall obtain from the COR or DGR, a copy of AMC's National Environmental Policy Act Policy and 32 CFR 651 which addresses actions to be taken by contractor. These documents include but is not limited to the analysis-associated decision document of an Environmental Impact Statement and Record of Decision; Environmental Assessment and Finding of No Significant Impact or Notice to Proceed; or Record of Environmental Consideration on the proposed contract actions prior to commencement of such actions.
8. Conformance with Environmental Management System: Contractor shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose risk of contamination, or can negatively impact the natural and/or human environment.
9. Assignment of Environmental Compliance Designee (ECD): Contractor shall appoint an ECD for all contract work periods exceeding 180 consecutive days. Contractor shall appoint a primary and alternate ECD for each production, shop or work area that uses and/or stores hazardous materials and/or generates hazardous wastes. Contractor ECDs shall monitor implementation of all environmental regulatory requirements, report all environmental noncompliance to the work site supervisor, correct all environmental noncompliance, and verify implementation of directed actions to correct identified environmental noncompliance. Contractor shall have at least one ECD on duty at all times at each shop or work area. Contractor shall require all personnel designated as ECDs to complete the initial ECD training through the installation or Major Subordinate Command (MSC) environmental compliance point of contact within 15 days of the start of contract performance. Contractor personnel appointed as ECDs may perform other duties provided they do not prevent the performance of ECD duties. Contractors may request a waiver of this requirement through the COR and DGR, if using and/or storing very small quantities of hazardous materials.
10. Competency Training for Contractor Personnel: Contractor shall not allow personnel to perform any activities and/or tasks on AMC installations without proper and adequate qualifications or job competency training. In the event of any identified noncompliance, the Contractor shall, if requested, provide proof of contract personnel training or qualification (individual name, training/qualification type, training/qualification certificate, and date of training/qualification) to perform those contract activities associated with the identified noncompliance.
11. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste generated, which cannot be recycled to an approved and permitted off-post disposal facility.
11.1. Contractor shall make every effort to divert construction, demolition debris, and all other solid waste to comply with the Army Integrated Solid Waste Management Policy.
11.2. The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.
11.3. The Contractor shall make maximum effort to reduce and prevent waste.
12. SEGREGATION OF HAZARDOUS WASTE
a. All waste items collected on this contract must be segregated and kept physically separate from any other waste items. All wastes must be properly containerized and labeled. Waste containers are to be supplied by the Contractor and must be designed for the waste type being disposed of according to all Federal, State and Local laws. In the event the waste classification is unknown prior to containerization, the container must be marked “under analysis”. All waste must be properly sampled and characterized at the Contractors expense, with copies of all analytical results submitted to the Environmental Department within 24 hours of receipt. Any waste characterized as Hazardous Waste must be properly labeled and will be relocated to the WVA RCRA Storage Area by Government employees or it’s Hazardous Waste Contractor under separate contract.
b. All waste items must be so marked, that they are readily identified to this contract throughout the process. In addition, the contractor must ensure that there is a clear audit trail for all items until final treatment/disposal is accomplished.
c. The Contractor is responsible for proper disposal of all excess samples, they shall be added to the corresponding waste container.
12.1 TREATMENT OF HAZARDOUS WASTE ON GOVERNMENT FACILITY
a. Treatment of hazardous waste (including solidification) on Government facilities is not permitted. Treatment is defined as any process which meets the definition of treatment as set forth in applicable local, state, and Federal (including 40 CFR 260.10) laws and regulations.
b. The contractor shall not drain and/or flush PCB items at Government installations.
Draining will be allowed only to prevent leaking and to meet DOT regulations.
c. Treatment, disposal, or release of gas (other than inert) to the atmosphere on Government premises is not permitted by this contract. The contractor may perform gas extraction for other than inert gas cylinders at the pickup location using self-contained apparatus. This apparatus shall emit no gas into the atmosphere, and purge the entire cylinder contents into a closed receiver for transport to a recycling or disposal site.
12.2 WASTE DISPOSAL REQUIREMENTS AND DOCUMENTATION
a. The Contractor shall not, under any circumstances, transport or dispose of any Hazardous Waste from the WVA. Non-RCRA regulated (Non-Hazardous) waste will be properly disposed of by the Contractor, at the Contractor’s expense. The contractor shall, without additional expense to the Government, be responsible for paying all fees, preparing or obtaining any necessary licenses, permits, notifications, waste profiles, or reports, which result from a contractor’s transportation, recycling, or disposal decision of such wastes.
b. The Contractor shall pay any and all fees, surcharges, fines or civil penalties resulting from errant or illegal waste profiling, packaging, labeling, documentation, transport or disposal of any waste from the project. The Contractor shall contact the Environmental Department immediately upon learning of any of the above.
c. All references to manifests in this provision relate to the “appropriate shipping paper” as required. The Contractor shall obtain and prepare all manifests, required for acceptance of waste into a Qualified Facility, and any other shipping documents. The contractor shall provide the COR with a copy of the completed form(s), for review by the appropriate Government official at least five (5) business days prior to removal.
Prior to removal from the site, completed copies of all manifests shall be furnished to the Environmental Office. Disposal receipts, weight slips and/or recycling receipts shall be submitted to the Environmental Office within 24 hours of receipt by Contractor. Each manifest, as well as all other documentation required herein, shall be clearly and distinctly marked with the generator and the contract and task order number, as applicable.
Emergency response information and twenty-four hour emergency phone numbers shall be listed on the manifest as well. If blocks are not provided, this information shall be placed in the upper, right-hand corner of each document.
d. The contractor shall notify the Environmental Department at least five (5) business days BEFORE attempting analysis or pickups of any waste for disposal.
e. The Government reserves the right to take appropriate action, such as the pursuit of monetary consideration and/or annotation of negative past performance if the contractor fails to meet the above applicable notification of waste removal from the pick-up location.
f. Contractor may not ship waste outside of the United States to circumvent Environmental Protection Agency (EPA) land disposal restrictions.
13. Use of Hazardous Materials: Contractor shall assign all hazardous materials management responsibilities to the appointed ECD. Contractor shall contact the DGR or COR to obtain technical assistance from Environmental Office for assisting the ECD with achieving and maintaining compliance with hazardous material storage, issue, use, and disposal requirements. Contractor shall submit to the COR and/or DGR a hazardous material inventory. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days. The inventory list will contain the hazardous material type and maximum quantities of materials anticipated to be stored on-site. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. The Contractor shall maintain copies of Safety Data Sheets for all hazardous materials used and stored on-site during performance of the contract.
Contractor shall not supply or deliver any hazardous materials or chemicals to an installation that are listed on EPA toxic chemical list without prior written approval from DGR and/or COR.
14. Prevention of Storm Water Pollution: The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as applicable to the Pollutant Discharge Elimination System general permit requirements. Applicable permits include:
1) The Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activities (MSGP); and,
2) All Construction Activity Storm Water permits minimum control measures include, but not limited to:
• Public Education and Outreach on Storm Water Impacts
• Public Involvement and Participation
• Illicit Discharge Detection and Elimination
• Construction Site Storm Water Run-off Control
• Post Construction Storm Water Management in New Development and Redevelopment
• Pollution Prevention/Good Housekeeping for Municipal Operations Contractors will comply with the MSGP permit when the activity is identified as a permitted industrial activity. BMPs include, but are not limited to:
• Practicing spill prevention and good housekeeping.
• Installing and managing erosion and sediment control.
• Contractors will obtain permit coverage for construction activities disturbing over one acre of land (total acreage is cumulative across all portions of the project). BMPs include, but are not limited to:
• Preparing and implementing a site-specific Storm Water Pollution Prevention Plan (SWPPP) as outlined in the permit and prior to any soil disturbance.
• Installing and managing erosion and sediment control.
• Make available, upon request, permit associated documentation.
• Practicing spill prevention and good housekeeping.
• Schedule inspections and provide corrective actions for noted deficiencies.
15. Storm Water Management Low Impact Design/Development (LID): The Contractor shall perform, track, participate, implement, and comply with Section 438 of the Energy Independence and Security Act; Executive Order 13514; and the DOA memorandum (2010) for full implementation of low impact design/development (LID) techniques to restore predevelopment hydrology to the maximum extent technically feasible for both new and renovation construction projects regardless of size. In support of LID, Contractors will adhere to installation landscape codes and the guidance found in the Installation Design Guide concerning Low Impact Design/Development for storm water management. The following LID practices include, but are not limited to:
• Restoring predevelopment hydrology to the maximum extent technically feasible
• Promoting natural removal of pollutants such as nutrients, oil and grease, and sediments from storm water
• Managing rainfall at the point where it falls
• Meeting the requirements of the MS4 permit
• Important Note: Utilization of permanent retention/detention ponds is prohibited without authorization from the Installation Planning Division.
16. Use of Pesticides: N/A
17. Protection of Work Site Resources: Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, the Contractor shall coordinate harvesting of saleable timber with the DGR and/or COR. Contractor shall notify the DGR and/or COR if any trees are required to be disposed or removed.
The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the DGR or COR.
18. Prevention of Spills: Contractor shall adopt the installation's Spill Prevention Control and Countermeasures Plan (SPCC) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. In case of a spill, the person in control of the spill site or their designated representative shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department).
19. Protection of Sensitive Areas: Contractor shall comply with all installation designated sensitive and/or off-limit area restrictions. Sensitive areas are generally demarked indicating what activities (e.g., driving, digging, foot traffic) are prohibited. The Contractor shall also adhere to the following installation sensitive areas requirements:
19.1. Cultural Resources Sites: Do not excavate, remove, damage, or otherwise deface any archeological resource located on public lands.
20. Corrective Action for Noncompliance: Contractor shall when given a verbal and/or written notice of environmental noncompliance or nonconformance by the COR, take immediate corrective action. Failure or refusal to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken.
21. Noise: Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or use of explosives will not be permitted without written permission from the Contracting Officer, and then only during the designated times. Pile-driving operations shall be coordinated through the DGR and COR.
22. Mercury: Mercury is prohibited, unless specified otherwise, and with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches, in rubbish containers is prohibited. Remove without breaking, pack to prevent breakage, and transport out of the activity in an unbroken condition for disposal as directed.
Immediately report to the DGR and COR instances of breakage or mercury spillage.
Clean mercury spill area to the satisfaction of the Contracting Officer. Cleanup of a mercury spill shall not be recycled and shall be managed as a hazardous waste for disposal.
23. Universal Waste / e-Waste Management: Universal waste including but not limited to some mercury containing building products such florescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions.
24. Pollution Prevention / Hazardous Waste Minimization: Minimize the use of hazardous materials and the generation of hazardous waste. Consult with the Environmental Office for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for supporting waste minimization goals.
COMMERCIAL NARRATIVES
C.__ REQUEST FOR QUOTE RESPONSES
ALL RESPONSES MUST BE ELECTRONIC. YOU MUST SUBMIT YOUR QUOTE RESPONSES USING
THE FOLLOWING METHODS:
(a) Email to: peter.j.haschytz.civ@army.mil
(b) Request for Quotes must be filled out completely and sent in its entirety to be considered responsive.
C.__ ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
(a) The contractor and all associated subcontractors’ employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9 “Personal Identity Verification of Contractor Personnel”) as directed by DoD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
(b) For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05, The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of six (6) months or more. At the discretion of the sponsoring activity, an initial CAC may be issued on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personal Management.
(c) For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards, and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures elsewhere in Section C; Non-disclosure Statement; for OCONUS locations, refer to the Status of Forces Agreement and other theater regulations.
A.__ NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS
(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:
(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE
REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE
ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.
(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE
DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO
COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN TERMINATION
OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT ELECTS TO EXTEND
DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid. They are not acceptable excuses for failing to meet the delivery after award).
(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST AS
IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-CONFORMING
PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS TO THE ARSENAL.
(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR
CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.
NOTICE: Throughout this document we may use the terms “we” and “you”, the term “we” means the government of the United States of America, and the term “you” means the contractor.
(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:
“Watervliet Arsenal Information for Contractors” document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available.”
POC - CONTRACT SPECIALIST/BUYER: Peter Haschytz II
TELEPHONE NUMBER: 518-266-3933
E-MAIL ADDRESS: peter.j.haschytz.civ@army.mil
CONTRACTOR DUNS NUMBER/CAGE CODE/FAX NUMBER:
Please provide the following information for your company.
VENDOR NAME: _________________________
VENDOR POC: __________________________
POC PHONE: ____________________________
E-MAIL ADDRESS (see note below): __________________________
DUNS NUMBER _______________________
CAGE CODE (if known) __________________
TAX ID NUMBER ________________________
VENDOR FAX NUMBER ________________
NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you.
If we experience difficulties with e-mail, it will be data faxed.
(c) AWCF BULK FUND ____ DOES X DOES NOT APPLY
(d) POSTERS:
(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, “Employee Rights on Government Contracts”.
(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, “Employee Rights under the Davis Bacon” and the Office of Federal Contract Compliance poster on “Equal Employment Opportunity is the Law.”
(3) These posters can be accessed electronically at http://www.dol.gov .
(4) Hard copies of the posters will be made available upon request to the contracting officer.
(e) PAYMENTS:
Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://wawf.eb.mil/ using the “my invoice” system. You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.
(f) RELEASE OF INFORMATION:
The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor’s responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.usapa.army.mil/pdffiles/r360_1.pdf
F.__ DELIVERY INFORMATION (FEB 2020) (ACC-WVA)
(a) Effective 1 March, 2020, all commercial carriers must request an appointment for delivery to Watervliet Arsenal through the Carrier Appointment System (CAS). Carriers can register for CAS at https://eta.sddc.army.mil/. In the event that a carrier is either unable to register for CAS, or if CAS is down, carriers must call the transportation desk at 518-266-5858 to schedule an appointment
Note(s):
i. Late/early arrivals may be rescheduled to the next available appointment date.
ii. This will not apply to small package carriers such as FEDEX, UPS, or
DHL.
(b) Notice: Normal delivery hours for receipt of supplies at Watervliet Arsenal are as follows:
Monday through Thursday Business Hours: 6:30 A.M. EST to 3:30 P.M. EST
Friday Business Hours: Every other Friday from 6:30 A.M. EST to 2:00 P.M. EST
Fridays will be staggered with every other Friday being a closed business day. The first Friday of 2021 to be closed is January 1, 2021.
BASED ON THE ABOVE, CONTRACTORS SHOULD CALL THE
CONTRACT/PURCHASE ORDER ADMINISTRATOR IN ADVANCE IF DELIVERY IS
SCHEDULED FOR A FRIDAY TO FIND OUT IF THE ARSENAL WILL BE OPEN FOR
BUSINESS.
Also, when a federal holiday is normally observed on a Friday, the Arsenal may be closed on the preceding Thursday. In these instances, please contact the contract/purchase order administrator in advance of delivery if Thursday delivery is anticipated to determine if the arsenal will be open for business.
THE ABOVE INFORMATION SHOULD BE NOTED WHEN SCHEDULING DELIVERIES
AS WATERVLIET ARSENAL WILL NOT BE LIABLE FOR ANY STORAGE,
DEMURRAGE OR SHIPPER LABOR COSTS INCURRED AS A RESULT OF
CONTRACTOR ATTEMPTED DELIVERIES ARRIVING DURING NON-BUSINESS
HOURS.
(c) ITEM DESCRIPTION:
The material delivered hereon must be tagged or otherwise identified by placing the purchase order/contract number on the packing slip or it will be returned at the contractor’s expense. If more than one item is involved, material must be segregated by item and must be tagged or otherwise identified by item number. National stock number, when applicable, must be shown on all vendor’s documents, such as Bill of Lading, Notice of Shipment, delivery or packing slip, etc.
L.___ HQ-AMC LEVEL PROTEST PROCEDURES
Complete AMC Protest Procedures can be found at: http://www.amc.army.mil/Connect/Legal-Resources/ An agency protest may be filed with either the contracting officer or to HQAMC but not both following the procedures listed on the website above.
Disclosure of Unit Price Information (Jun 2004) (ACC-WRN (WVA))
This constitutes notification pursuant to Executive Order 12600, Pre-Disclosure Notification Procedures for Confidential Commercial Information (June 23, 1987), of our intention to release unit prices of the awardee in response to any request under the Freedom of Information Act, 5 USC 552. Unit price is defined as the contract price per unit or item purchased. We consider any objection to be waived unless the contracting officer is notified of your objection to such release prior to submission of initial proposals.
EVALUATION—COMMERCIAL ITEMS (APR 2009) (ACC-WRN (WVA))
(a) We will award a contract to the offeror that:
1. submits the lowest evaluated bid or offer, and
2. submits a bid or proposal that meets all the material requirements of this solicitation, and
3. meets all the responsibility criteria at FAR 9.104
(b) To make sure that you meet the responsibility criteria at FAR 9.104 we may:
1. arrange a visit to your plant and perform a preaward survey;
2. ask you to provide financial, technical, production, or managerial background information.
(c) Options. We will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. We may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate us to exercise the option(s).
(d) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, we may accept an offer (or part of an offer), regardless of whether there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
PROMPT PAYMENT NOTICE TO FAR 52.212-4 (MAY 2013) (ACC-WRN(WVA))
In accordance with the prompt payment regulations at 5 CFR 1315 referenced in FAR 52.212-4 Contract Terms and Conditions – Commercial Items, specifically 5 CFR 1315-4(b)(1)(B), Government acceptance shall be deemed to have occurred constructively on the 30th day after the contractor delivered the supplies or performed the services.
CLAUSES INCORPORATED BY FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
N/A
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
Invoice as 2-in-1 (Services Only)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC HQ0303
Issue By DoDAAC W911PT
Admin DoDAAC** W911PT
Inspect By DoDAAC N/A
Ship To Code N/A
Ship From Code N/A
Mark For Code N/A
Service Approver (DoDAAC) N/A
Service Acceptor (DoDAAC) W911PT
Accept at Other DoDAAC N/A
LPO DoDAAC N/A
DCAA Auditor DoDAAC N/A
Other DoDAAC(s) N/A
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS
Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
Contract Specialist Peter Haschytz II, peter.j.haschytz.civ@army.mil, 518-266-3933
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each 100 Ton Press
FFP
Greenerd HCS-100-27L3 100 Ton Press, or Equal, per Watervliet Arsenal Equipment Engineering Specification # 20-21-3419, Revision Dated 12 July 2021.
MID: TBD
FOB: Destination
PSC CD: 3443
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 150 dys. ADC 1 TRANSPORTATION OFFICER
MATTHEW ARMBRUSTER
WATERVLIET ARSENAL
TAWV-IML-S/BLDG 35
SHIPPING AND RECEIVING
WATERVLIET NY 12189-4000
518-266-5858 FOB: Destination
W16H1F
CLAUSES INCORPORATED BY REFERENCE
52.203-3 Gratuities APR 1984 52.203-6 Alt I Restrictions On Subcontractor Sales To The Government
(JUN 2020) -- Alternate I
OCT 1995
52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights
JUN 2020
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2020
52.209-2 Prohibition on Contracting with Inverted Domestic Corporations--Representation
NOV 2015
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
JUN 2020
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-15 Defense Priority And Allocation Requirements APR 2008 52.211-17 Delivery of Excess Quantities SEP 1989 52.212-1 Instructions to Offerors--Commercial Items JUL 2021 52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S.